Credit Assessment Load Factors (CALF) |
Guidance |
Obliged to submit Physical Notifications, due either to obligations placed on it under the Grid Code or because it has elected to take part in the Balancing Mechanism; and
It is not an Interconnector Primary BM Unit; and
It meets one of the following criteria:
It is a Production Primary BM Unit (i.e. it has a Production P/C Status); or
It is an Exempt Export Primary BM Unit (regardless of whether its P/C Status is Production or Consumption).
The Panel has delegated responsibility for the maintenance of the CALF principles and guidance, and the processing of CALF appeals, to the Imbalance Settlement Group (ISG).
The Central Registration Agent (CRA) and Energy Contract Volume Aggregation Agent (ECVAA) BSC Systems are used to support the credit process that CALF is used in:
CRA
Stores Primary BM Unit registration data such as Primary BM Unit Id, Primary BM Unit Type, Lead Party, GSP Group Id, GC, DC, WDCALF, NWDCALF and SECALF and various flags (e.g. Credit Qualifying Flag)
Calculates WDBMCAEC, NWDBMCAEC, WDBMCAIC and NWDBMCAIC
Sends data to ECVAA
ECVAA
Calculates estimations of metered volume
Processes Energy Contract Volume Notifications
Processes other data such as Final FPNs, CDCA metered volume data and Trading Charge data
Calculates different types of Energy Indebtedness (CEI, MEI and AEI = TEI)
Operates a rolling credit check process and alerts BSCCo of threshold breaches
BM Units – Registration of Balancing Mechanism (BM) Units guidance |
BSC Section K: Classification and Registration of Metering Systems and BM Units |
Spring: 1 March to 31 May
Summer: 1 June to 31 August
Autumn: 1 September to 30 November
Winter: 1 December to 28/29 February.
CALFs are key parameters employed in determining a Party’s Credit Cover Percentage. Where a Party’s Credit Cover Percentage exceeds certain specified values then the Party is deemed to be in Credit Default. The Party is required to take action to cure the Default, in order to avoid an escalation process. This escalation process includes publication of the Party’s details and rejection of some or all Energy Contract Volume Notifications and Metered Volume Reallocation Notifications.
Every Primary BM Unit has the following capabilities (in MW) calculated using CALFs, in accordance with BSC Section M1.6:
Working Day Balancing Mechanism Credit Assessment Export Capability (WDBMCAEC)
Non-Working Day Balancing Mechanism Credit Assessment Export Capability (NWDBMCAEC)
Working Day Balancing Mechanism Credit Assessment Import Capability (WDBMCAIC)
Non-Working Day Balancing Mechanism Credit Assessment Import Capability (NWDBMCAIC)
These capabilities provide an estimate of the MW export or import capability of a Primary BM Unit and are multiplied by the Settlement Period Duration (SPD) of 0.5 hours to get the estimation of metered volume in MWh, known as Credit Assessment Credited Energy Volume (CAQCE). Note that the ECVAA system will only use the two Working Day variants or Non-Working Day variants depending on whether the Settlement Date is a Working Day or a Non-Working Day.
The capabilities are derived from the relevant WDCALF, NWDCALF or SECALF, and the Generation Capacity (GC, in MW) or Demand Capacity (DC, in MW), of the Primary BM Unit. The diagram below shows the factors that determine how these capabilities are calculated and the relevant capability (import or export) that would be used (in bold).
A Primary BM Unit’s P/C Status is normally determined by summing the Relevant Capacities of all Primary BM Units in its Trading Unit (including the Primary BM Unit itself):
A Primary BM Unit’s Relevant Capacity is its GC value if its GC+DC is greater than zero. Its Relevant Capacity is its DC value if its GC+DC is less than or equal to zero.
If the sum of all the Primary BM Unit Relevant Capacities in a Trading Unit is greater than zero, then all Primary BM Units in that Trading Unit are normally Production Primary BM Units.
If the sum of all the Primary BM Unit Relevant Capacities in a Trading Unit is less than or equal to zero, then all Primary BM Units in that Trading Unit are normally Consumption Primary BM Units.
If a Primary BM Unit is a Sole Trading Unit on its own, then its P/C Status will only be affected by its own GC and DC values. However, if it is part of a Trading Unit with one or more other Primary BM Units, its P/C Status will also be affected by the GC and DC values of the other Primary BM Unit(s). A Primary BM Unit in a Trading Unit with other Primary BM Units may therefore have a Production P/C Status even if its individual Relevant Capacity is its DC value, or a Consumption P/C Status even if its individual Relevant Capacity is its GC value. You can find further information about Trading Units in BSC Section K4 and in BSCP31: Registration of Trading Units.
A Primary BM Unit’s P/C Status is re-determined whenever:
The Primary BM Unit joins or leaves a Trading Unit;
Another Primary BM Unit joins or leaves its Trading Unit; and/or
There is a change in the GC and/or DC value of the Primary BM Unit or any other Primary BM Unit in its Trading Unit.
Under these rules, a Primary BM Unit’s P/C Status can therefore change at any time. However, there are exceptions to these rules for Supplier Primary BM Units, Exempt Export Primary BM Units and Interconnector Primary BM Units (see below).
Following the implementation of Approved Modification P269 on 23 February 2012, the P/C Status of a non-Exempt Export Supplier Primary BM Unit (whether a Base Primary BM Unit or an Additional Primary BM Unit) is fixed as Consumption and cannot change. The GC and DC values of Supplier Primary BM Units do not affect their own P/C Status or the P/C Status of any other Primary BM Units in their Trading Unit. This is because all non-Exempt Export Supplier Primary BM Units are required to be part of the Base Trading Unit for their Grid Supply Point (GSP) Group, and this Base Trading Unit can only comprise other non-Exempt Export Supplier Primary BM Units and Exempt Export Primary BM Units (see 3.7 below).
Following the implementation of Approved Modification P268 on 23 February 2012, Exempt Export Primary BM Units relating to Exemptable Generating Plant must elect to fix their P/C Status as either Production or Consumption using the relevant form in BSCP15. They can change this election at any time. The GC and DC values of Exempt Export Primary BM Units do not affect their own P/C Status, regardless of whether they are a Sole Trading Unit or part of a Trading Unit with one or more other Primary BM Units. The GC and DC values of an embedded Exempt Export Primary BM Unit also do not affect the P/C Status of any other Primary BM Units if they are part of a Base Trading Unit (with Supplier Primary BM Units and other Exempt Export Primary BM Units in their GSP Group) or part of a Class 4 Trading Unit (with other Exempt Export Primary BM Units in their GSP Group). If an Exempt Export Primary BM Unit forms part of another type of Trading Unit with other, non-Exempt Export and non-Supplier, Primary BM Units then its GC and DC values will affect the P/C Status of these other Primary BM Units. See BSCP31 for more details.
Interconnector Primary BM Units are allocated in pairs (one Production Primary BM Unit and one Consumption Primary BM Unit) per Interconnector. The P/C Status of these Interconnector Primary BM Units is fixed and cannot change. The GC and DC values of Interconnector Primary BM Units do not affect their own P/C Status. If an Interconnector Primary BM Unit is part of a Class 5 Trading Unit, then its GC and DC values will affect the P/C Status of any non-Interconnector Primary BM Units (but not any other Interconnector Primary BM Units) in that Trading Unit. The GC value of a Consumption Interconnector Primary BM Unit, and the DC value of a Production Interconnector Primary BM Unit, is always zero and cannot change.
The registered Production or Consumption Status of a non-Interconnector, non-Credit Qualifying Primary BM Unit is used by BSC Systems to determine whether it is the Primary BM Unit’s GC or DC value that is multiplied by its WDCALF and NWDCALF value in the first five Working Days of the Credit Cover calculation. GC*WDCALF and GC*NWDCALF is used in the calculation of WDBMCAEC and NWDBMCAEC (in the case of a Production Primary BM Unit), and DC*WDCALF and DC*NWDCALF for WDBMCAIC and a NWDBMCAIC (for a Consumption Primary BM Unit). GC, DC and WDCALF and NWDCALF values are not used in the initial part of the Credit Cover calculation for Interconnector or Credit Qualifying Primary BM Units, for whom FPNs are used instead.
As the P/C Status of all non-Exempt Export Supplier Primary BM Units is fixed as Consumption, a WDBMCAIC and NWDBMCAIC will always be calculated for these Primary BM Units using their DC*WDCALF and DC*NWDCALF, unless the Panel has determined that the Primary BM Unit should be Credit Qualifying in accordance with BSC Section K3.7. Normally, the CALF value of a Supplier Primary BM Unit is positive so that, when applied to the Primary BM Unit’s negative DC value, it derives the Primary BM Unit’s estimated average (negative) demand.
An Exempt Export Primary BM Unit which submits FPNs will be Credit Qualifying in accordance with BSC Section K3.7. It is possible for a non-Credit Qualifying Exempt Export Primary BM Unit to have a Consumption P/C Status (and a credit assessment based on its DC, which may be non-zero) but an individual GC which is greater than DC and/or an average Metered Volume which is greater than zero over a season. This is known issue and, in this situation, the Lead Party can apply for a special WDCALF and NWDCALF values in accordance with Section 5 or Section 11 of this guidance. Exempt Export Primary BM Units, by electing their P/C Status, can also effectively choose whether their GC (WDBMCAEC, NWDBMCAEC) or DC (WDBMCAIC, NWDBMCAIC) is used in the Credit Cover calculation – except where the Exempt Export Primary BM Unit has a Production P/C Status but an individual Primary BM Unit Relevant Capacity of less than or equal to zero, in which case its DC will be used to calculate a WDBMCAIC and NWDBMCAIC.
WDCALF/NWDCALF values for Consumption Primary BM Units are determined from the net metered Consumption of that Primary BM Unit in the equivalent BSC Season of the previous year.
For Primary BM Units which have both a Production and Consumption capability, the WDCALF/NWDCALF value is determined from the ratio of the average net metered volume in MWh over the BSC Season, divided by the maximum generation in that season (for Production Units) or the maximum demand in that season (in the case of Consumption Units). This would yield a negative WDCALF/NWDCALF value where the Primary BM Unit is a net consumer but is assigned Production status or a net producer but is assigned Consumption status.
New Production Primary BM Units based upon Onshore or Offshore Wind technology will be allocated a generic WDCALF/NWDCALF value for the first twelve months, as will Primary BM Units of this type migrating from SMRS to CMRS. This generic value has been calculated from historical performance data published on the Department for Energy Security & Net Zero website. The value is currently set to 0.2900 and has been rounded to 2.d.p. Further changes to this generic value will only be made by the ISG or the Panel. After twelve months a WDCALF/NWDCALF value will be assigned based upon historical performance for the equivalent BSC Season of the preceding year, in accordance with paragraph 4.3 above.
New Production Primary BM Units based upon Biofuel technology will be allocated a generic WDCALF/NWDCALF value for the first twelve months, as will Primary BM Units of this type migrating from SMRS to CMRS. This generic value has been calculated from historical performance data published on the Department for Energy Security & Net Zero website and is currently set to 0.6230. Further changes to this generic value will only be made by the ISG or the Panel. After twelve months a CALF value will be assigned based upon historical performance for the equivalent BSC Season of the preceding year, in accordance with paragraph 4.3 above.
Production Primary BM Units based upon Pumped Storage technology migrating from SMRS to CMRS will be assigned a generic WDCALF/NWDCALF value until three months metered data is available. The generic WDCALF/NWDCALF value is based upon the historical average WDCALF/NWDCALF of existing Pumped Storage Primary BM Units in CMRS. This value is currently set to -0.0378. Further changes to this generic value will only be made by the ISG or the Panel. After three months metered data becomes available, the WDCALF/NWDCALF value for the next BSC Season will be calculated from metered data for the previous three months. After twelve months the WDCALF/NWDCALF value will be calculated from the net metered Production of the Primary BM Unit in the equivalent BSC Season of the preceding year, in accordance with paragraph 8.2.
Production Primary BM Units based upon Open Cycle Gas Turbine (OCGT) technology migrating from SMRS to CMRS will be assigned a generic WDCALF/NWDCALF value until three months metered data is available. The generic WDCALF/NWDCALF value is based upon the historical average WDCALF/NWDCALF of existing OCGT Primary BM Units in CMRS. This value is currently set to 0.0087. Further changes to this generic value will only be made by the ISG or the Panel. After three months metered data becomes available, at which point the WDCALF/NWDCALF value for the next BSC Season will be calculated from metered data for the previous three months. After twelve months the WDCALF/NWDCALF value will be calculated from the net metered Production of the Primary BM Unit in the equivalent BSC Season of the preceding year, in accordance with paragraph 4.3 above.
Production Primary BM Units based upon Hydro technologies migrating from SMRS to CMRS will be assigned a generic WDCALF/NWDCALF value until three months’ metered data is available. The generic WDCALF/NWDCALF value is based upon the historical average WDCALF/NWDCALF of existing Hydro Primary BM Units in CMRS. This value is currently set to 0.2938. Further changes to this generic value will only be made by the ISG or the Panel. After three months metered data becomes available, the WDCALF/NWDCALF value for the next BSC Season will be calculated from metered data for the previous three months. After twelve months the WDCALF/NWDCALF value will be calculated from the net metered Production of the Primary BM Unit in the equivalent BSC Season of the preceding year, in accordance with paragraph 4.3 above.
Production Primary BM Units based upon Combined Cycle Gas Turbine (CCGT) technology migrating from SMRS to CMRS will be assigned a generic WDCALF/NWDCALF value until three months’ metered data is available. The generic WDCALF/NWDCALF value is based upon the historical average WDCALF/NWDCALF of existing CCGT Primary BM Units in CMRS. This value is currently set to 0.5411. Further changes to this generic value will only be made by the ISG or the Panel. After three months metered data becomes available, at which point the WDCALF/NWDCALF value for the next BSC Season will be calculated from metered data for the previous three months. After twelve months the WDCALF/NWDCALF value will be calculated from the net metered Production of the Primary BM Unit in the equivalent BSC Season of the preceding year, in accordance with paragraph 4.3 above.
For new Consumption Primary BM Units a generic WDCALF/NWDCALF value will be assigned until three months metered data is available. This generic WDCALF/NWDCALF value is based upon the historical average of all other Consumption Primary BM Units in CMRS. This value is currently set to 0.3622. Further changes to this generic value will only be made by the ISG or the Panel. After three months metered data becomes available, the WDCALF/NWDCALF value for the next BSC Season will be calculated from metered data for the previous three months. After twelve months the WDCALF/NWDCALF value will be calculated from the net metered Consumption of the Primary BM Unit in the equivalent BSC Season of the previous year, in accordance with paragraph 4.4 above.
For new Rail Demand Primary BM Units a generic WDCALF/NWDCALF value will be assigned until three months’ metered data is available. This generic WDCALF/NWDCALF value is based upon the historic average of all other Rail Demand Primary BM Units in CMRS. This value is currently set to 0.2047. Further changes to this generic value will only be made by the ISG or the Panel. After three months metered data becomes available, at which point the WDCALF/NWDCALF value for the next BSC Season will be calculated from metered data for the previous three months. After twelve months the WDCALF/NWDCALF value will be calculated from the net metered Consumption of the Primary BM Unit in the equivalent BSC Season of the previous year, in accordance with paragraph 4.4 above.
Fuel Type | WDCALF/NWDCALF |
Wind | 0.2900 |
Biofuel | 0.6230 |
Hydro | 0.2938 |
Pumped Storage | -0.0378 |
OCGT | 0.0087 |
CCGT | 0.5411 |
CVA Consumption | 0.3622 |
Rail Demand | 0.2047 |
Station Load | 0.0664 |
CALF values are calculated and published to BSC Parties around 3 months ahead of the BSC Season (e.g. Spring 2017) that they are intended to be used. The calculations are done using Primary BM Unit Metered Volume data for that BSC Season, but in the previous year (e.g. Spring 2016), and this is called the Reference Season.
The CALF values are calculated in one of two ways, depending on whether the average Primary BM Unit Metered Volume in the Reference Season was greater than or less than zero. This is because Supplier Primary BM Units can contain a mix of generation and consumption sites, which could result in a positive (net generation) or negative (net consumption) value of Primary BM Unit Metered Volume.
Where the average Primary BM Unit Metered Volume was less than zero then WDCALF and NWDCALF are calculated as:
Where the average Primary BM Unit Metered Volume was greater than zero then WDCALF and NWDCALF are calculated as:
Where the average Primary BM Unit Metered Volume was equal to zero then WDCALF and NWDCALF will be calculated as zero.
The result of this approach is that a positive (or zero) WDCALF and NWDCALF values will be calculated for all SMRS-registered Primary BM Units. In the case of Exempt Export Primary BM Units (whose average metered volume across a BSC Season will typically be greater than zero) the Lead Party must elect whether its P/C Status is “P” or “C”. If the Primary BM Unit is “C” status, then a WDBMCAIC and NWDBMCAIC will be calculated. Where the Primary BM Unit’s average Primary BM Unit Metered Volume is greater than zero and the declared DC is non-zero, then a negative WDBMCAIC and NWDBMCAIC will be calculated. This will not give an accurate reflection of the Primary BM Unit’s behaviour in the Energy Indebtedness calculation. This is a known and pre-existing issue with the CALF methodology (the problem is described in the context of CMRS-registered Primary BM Units in Section 11 of this guidance)1. Potential workarounds are frustrated by the fact that the applicable P or C Status may not be known at the time of calculating WDCALF and NWDCALF values2, and in any event this may be varied at any time at the option of the Lead Party. It is possible for such Primary BM Units to have Credit Qualifying status, if the Primary BM Unit fulfils the criteria laid out in paragraph 10.2. Their Primary BM Unit FPNs would be used in the CEI part of the credit calculation, thereby more accurately reflecting that Primary BM Unit’s activity. It is suggested that where Parties adopt a Production or Consumption status at variance with their actual behaviour, there will typically be other benefits associated to this decision that outweigh the consequences for the Energy Indebtedness calculation.
Where Supplier Primary BM Units have Embedded Generation, the above is unlikely to give an accurate reflection of the Primary BM Unit’s behaviour in the Energy Indebtedness calculation. This is because the total Consumption within the Base Trading Unit is likely to be greater than the total Embedded Generation and, because the P/C Status of a Base Primary BM Unit is normally ‘C’ (Consumption)3, BSC Systems will calculate a WDBMCAIC and NWDBMCAIC for the Primary BM Unit using WDCALF, NWDCALF and DC thus ignoring the Generation element.
There are two options to more accurately reflect Embedded Generation. A workaround referred to as ‘alternative CALF’ and the SECALF solution. Modification P310, effective from 25 June 2015, introduces the SECALF calculation.
A SECALF will be applied where the Supplier Primary BM Unit has a positive GC and zero DC (hereafter referred to as SECALF-qualifying). In this scenario the BMCAEC will be used instead of the BMCAIC in the CEI calculation, hence reflecting generation.
Like WDCALF and NWDCALF, SECALF is calculated using Primary BM Unit Metered Volume data for that Reference Season, however only for days where the Primary BM Unit was SECALF-qualifying.
Where the average Primary BM Unit Metered Volume for SECALF-qualifying days was less than zero then SECALF is calculated as:
Where the average Primary BM Unit Metered Volume for SECALF-qualifying days was greater than zero then SECALF is calculated as:
Where the average Primary BM Unit Metered Volume for SECALF-qualifying days was equal to zero then SECALF will be calculated as zero.
A manual workaround is used for Supplier Primary BM Units with both Embedded Generation and demand. A Party can submit a request for the WDCALF and NWDCALF values to be calculated using the methodology defined below. An application is made using the form in Appendix 7, at least one month prior to the start of the Season.
On receipt of the application for a Supplier Primary BM Unit, the WDCALF and NWDDCALF values will be determined as follows:
Initially two GC/DC Factors will be calculated; one for Working Days and one for Non-Working Days. For the Reference Season which is being used to derive values for the current BSC Season, these factors are derived to express the weighting of the Generation and Demand Capacities on the Working Day Net Average Metered Volume and Non-Working Day Net Average Metered Volume using the following formula:
Then the CALF Value is calculated using the following formula
Then continuing with the above example If SDC and SGC were -10 and+30, the method of determining WDCALF or NWDCALF would give an estimated average flow of (0.25x30 + (1 - 0.25)-10) / -10 = 0.
Alternatively, Suppliers having Primary BM Units with both demand and generation can decide to register Additional Primary BM Units to split the two and benefit from Modification P310. Registering Additional Primary BM Units only containing generation will allow the BSC Systems to consider a Supplier’s generation in the Credit Cover Percentage calculation by applying a SECALF value to the Generation Capacity (GC) declared. This may consequently reduce the amount of Credit Cover needed by the Party. Registering Additional Primary BM Units can be done by completing the BSCP15 ‘Primary BM Unit Registration’ form, and the Market Domain Data (MDD) Entity 61 “BM Unit for Supplier in GSP Group” form.
For the methodology described in paragraph 5.17, changes, in particular those relating to a Demand Capacity for the Primary BM Unit, could have the effect of incorrectly improving a BSC Party’s Credit Position. Therefore, on receipt of a change in the Demand or Generation Capacity of a Primary BM Unit, the CALF value will be recalculated using the same formula: e.g.
Note that, for Supplier Primary BM Units, if changes to GC/DC are required; the DC value can only be lowered twice during a BSC Season, however, both GC and DC can be increased (in absolute value) as many times as required by the party.
In the case of SVA Exempt Export Primary BM Units (whose average metered volume across a BSC Season will also typically be greater than zero) the Lead Party must elect whether its P/C Status is Production or Consumption. See Section 3.
If the Primary BM Unit is “C” status, then a WDBMCAIC and NWDBMCAIC will be calculated and if similar circumstances exist to those described in Section 5.9 above this will not give an accurate reflection of the Primary BM Unit’s behaviour in the Energy Indebtedness calculation. Where the Primary BM Unit has a positive GC and zero DC, a WDBMCAEC and NWDBMCAEC will be applied, using a SECALF value along with the GC (see Section 5.11). If the Primary BM Unit has both generation and demand and the average net Metered Volume for the equivalent BSC Season the previous year was greater than zero, the Party can submit a request for the WDCALF and NWDCALF values to be calculated using the methodology defined in this sub-Section, by completing the application in Appendix 7, one month prior to the start of the Season.
Initially a GC/DC Factor will be calculated. For the Reference Season which is being used to derive values for the current BSC Season, this factor is derived to express the weighting of the Generation and Demand Capacities on the Net Average Metered Volume using the following formulas:
Then the WDCALF and NWDCALF values are calculated using the following formulas:
For the methodology described in Section 5.9 changes, in particular those relating to a Demand Capacity for the Primary BM Unit, could have the effect of incorrectly improving a BSC Party’s Credit Position.
Therefore, on receipt of a change in the Demand or Generation Capacity of a Primary BM Unit, the WDCALF and NWDCALF values will be recalculated using the same formula: e.g.
Where the Primary BM Unit had zero metered volume in the equivalent BSC Season of the previous year, or non-zero metered volumes were not first submitted in respect of the Primary BM Unit until after the start of that Season, a generic WDCALF and NWDCALF value will be assigned. This will be calculated as the average of all WDCALF and NWDCALF values assigned to Primary BM Units in the relevant GSP Group.
Changes in a Supplier’s customer portfolio in a given GSP Group between the period used for the calculation and the present may affect the WDCALF and NWDCALF characteristics of the relevant Primary BM Unit(s). The impact will depend on the mix of Metering Systems registered before and after the portfolio change. Analysis indicates that, for most Primary BM Units, the typical year-on-year variation between the proportion of the Primary BM Unit’s metered volume that is HH metered, as opposed to NHH, is less than 20%. As a crude control, therefore, where the absolute difference between the percentage HH: NHH contributions to Primary BM Unit metered volume is more than 20% between the BSC Season used to calculate WDCALF and NWDCALF and the most recent 30-day period for which data is available, then a generic WDCALF and NWDCALF values will be applied, calculated as described in paragraph 5.9.
The generic WDCALF and NWDCALF value may not be appropriate for Supplier Primary BM Units with embedded generation. In this case the Supplier has the option to raise a CALF Appeal by following the process detailed in Section 12. If the Supplier did not submit a CALF Appeal, but has good reason for not doing so – for example acquiring embedded generation after the CALF Appeal deadline – then it can request that Elexon calculates an interim WDCALF and NWDCALF values. Elexon will only calculate an interim WDCALF and NWDCALF value upon receipt of substantial evidence from the Lead Party of the Primary BM Unit’s expected maximum and average generation and demand for the BSC Season. Elexon will report details of any such calculation to the ISG. If a lack of reference data means that a generic WDCALF and NWDCALF value would again be assigned for the following BSC Season, then the Lead Party must submit a CALF Appeal in accordance with Section 12.
As with WDCALF and NWDCALF, there are instances where a SECALF value cannot be calculated for a BSC Season.
BSC Season | Generic SECALF |
Spring 2024 | 0.2100 |
Summer 2024 | 0.2400 |
Autumn 2024 | 0.2200 |
Winter 2024 | 0.2500 |
Spring 2025 | 0.2100 |
Summer 2025 | 0.2200 |
Where a Supplier Primary BM Unit would receive a SECALF per Section 5.11, it will be assigned a generic SECALF instead if one or more of the following are true:
The Supplier Primary BM Unit had an average metered volume of less than or equal to zero, over the equivalent BSC Season of the previous year
Non-zero metered volumes were not first submitted in respect of the Supplier Primary BM Unit until after the start of that Season
The Supplier Primary BM Unit was not SECALF qualifying in that Season
Suppliers have the option to appeal a generic SECALF value under the process detailed in Section 12.
Generic SECALF values are reviewed annually at the start of May. Elexon will recalculate the four generic SECALF values as follows:
All SECALF qualifying Primary BM Units in each of the previous four Seasons will be identified.
The SECALF for each Primary BM Unit will be calculated as follows:
Where the average Primary BM Unit Metered Volume for SECALF-qualifying days was less than zero then SECALF is calculated as:
Where the average Primary BM Unit Metered Volume for SECALF-qualifying days was greater than zero then SECALF is calculated as:
Where the average Primary BM Unit Metered Volume for SECALF-qualifying days was equal to zero then SECALF will be calculated as zero.
For each Season the average of all non-zero SECALFs will be taken to give the SECALF for each Season
Where a recalculated generic SECALF has a difference from the current generic SECALF of greater than or equal to 0.02, Elexon will present this to ISG. ISG will consider the new generic SECALF value for approval and if granted, Elexon will use the new set of generic SECALF values from the next publication onwards.
Due to the calendar timings, the next BSC Season to use the generic SECALFs after approval will be Autumn of that year. Therefore Spring and Summer values for the current and following year will be published.
BSC Section M1.5A specifies two Annual Holiday Periods “for purposes associated with the Credit Assessment Load Factor”. One Annual Holiday Period covers the Christmas – New Year period and the other covers the Easter holiday period. These are defined formulaically in the Code to consist of consecutive whole Settlement Days as follows:
Thursday | Good Friday (Bank Holiday) | Saturday | Sunday | Easter Monday (Bank Holiday) | Tuesday |
24 December (Christmas Eve) falls on: | Commencement Day: | Conclusion Day: |
Sunday | 23 December | 2 January |
Monday | 22 December | 2 January |
Tuesday | 21 December | 2 January |
Wednesday | 24 December | 4 January |
Thursday | 24 December | 3 January |
Friday | 24 December | 4 January |
Saturday | 24 December | 3 January |
Lead Parties of SMRS-registered Primary BM Units and CMRS-registered Consumption Primary BM Units are permitted to elect, in place of the base Seasonal WDCALF and NWDCALF values and for some or all of their SMRS-registered Primary BM Units and CMRS-registered Consumption Primary BM Units, to be assigned two separate WDCALF and NWDCALF values for each of the two BSC Seasons in which Annual Holiday Periods occur:
One ‘Holiday’ WDCALF and NWDCALF value to apply to Settlement Periods within an Annual Holiday Period (HOL) and;
One ‘normal’ WDCALF and NWDCALF value to apply to all other Settlement Periods in the BSC Season in which the Annual Holiday Period falls (XHOL).
Where separate WDCALF and NWDCALF values are calculated for Settlement Periods falling, respectively, within and outside of the Annual Holiday Period, these periods will be referred to as HOL and XHOL respectively, and the associated WDCALF and NWDCALF values, HOL-WDCALF, HOL-NWDCALF, XHOL-WDCALF and XHOL-NWDCALF.
Parties will be asked to submit a HOL-Ratio for each of their Primary BM Units for which they require a WDHOL, NWDHOL, and XHOL-WDCALF and XHOL-NWDCALF to be applied. The HOL-Ratio is defined to be the value which represents, in the good faith assessment of the Lead Party and in respect of the forthcoming BSC Season to which it is to be applied, the following quotient:
WDBMCAEC/NWDBMCAEC (calculated as WDCALF*GC/NWDCALF*GC) for non-Interconnector, non-Credit Qualifying, Primary BM Units with a Production P/C Status and an individual Primary BM Unit Relevant Capacity which is greater than zero; and
WDBMCAIC/NWDBMCAIC (calculated as WDCALF*DC/NWDCALF*DC) for non-Interconnector, non-Credit Qualifying, Primary BM Units with a Consumption P/C Status, or with a Production P/C Status but an individual Primary BM Unit Relevant Capacity which is less than or equal to zero.
The Primary BM Unit is obligated to submit FPNs under the Grid Code or has elected to participate in the Balancing Mechanism; and
The Primary BM Unit is not an Interconnector Primary BM Unit; and
The Primary BM Unit meets one or more of the following additional criteria:
It is a Production Primary BM Unit; or
It is an Exempt Export Primary BM Unit (regardless of whether its P/C Status is Production or Consumption).
Primary BM Unit ID | GC | DC | Type | Average Net Generation or Demand (MWh) | Maximum Generation or Demand (MWh) | Individual CALF |
Primary BM Unit 1 | 400 | 0 | Production | 150 | 170 | 0.8824 |
Primary BM Unit 2 | 400 | 0 | Production | 150 | 190 | 0.7895 |
Primary BM Unit 3 | 0 | -50 | Consumption | -35 | -45 | 0.7777 |
Primary BM Unit ID | Ratio of Maximum Generation | Amount of Demand to be netted | Netted Average Generation | CALF Value |
Primary BM Unit 1 | =170/360 = 0.4722 | =0.4722 x (-35) = (-16.527) | = 150 + (-16.555) = 133.445 | =133.445/170 = 0.7850 |
Primary BM Unit 2 | =190/360 = 0.5277 | = 0.5277 x (-35) = (-18.470) | =150 + (-20.020) =129.980 | =129.980/190 = 0.6841 |
Primary BM Unit 3 | - | - | - | 0 |
Commissioning Season | WDCALF/NWDCALF |
1 | 0.0936 |
2 | 0.3581 |
3 | 0.6500 |
4 | 0.6500 |
5 | 0.6500 |
6 | 0.7866 |
Submit the attached form (fully completed) to BSCCo via Elexon Support at least three weeks before the date of the last ISG meeting to occur before the start of the BSC Season (a timetable of ISG meetings is published on the BSC Website at: Imbalance Settlement Group (ISG)
Ensure that the person submitting the form (or a suitable alternative contact) can respond to any Elexon requests for clarification/elaboration in the period before the ISG meeting.
If it was due to an unexpected plant failure or otherwise planned after the start of the BSC Season in which it occurred;
To the extent that a Primary BM Unit operated at a lower average load during the outage than was planned; or
If the outage is an unplanned extension of a planned outage.
The equivalent BSC Season in the previous year; and
If applicable, another BSC Season or other historic period recommended by the Party as the basis of revising WDCALF, NWDCALF or SECALF values in part 2.
CDCA data for a particular BSC Season; or
A detailed production schedule/ forecast for the BSC Season being appealed.
WDCALF, NWDCALF or SECALF Appeal Reference (To be assigned by Elexon) |
|
BSC Season for which WDCALF, NWDCALF or SECALF values are being appealed |
|
Contact 1: | Contact 2: (if applicable) | ||
Name |
| Name |
|
Phone |
| Phone |
|
|
|
Lead Party name: |
| ||
Trading Unit name (state N/A if Sole Trading Unit or Base Trading Unit): |
| ||
Primary BM Unit IDs: | GC (MW) | DC (MW) | Reason for appealing assigned WDCALF, NWDCALF or SECALF values: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
[add more rows if necessary; copy table for other Trading Units as required] |
Primary BM Unit IDs | Outage First Date | Outage Last Date | Average % Volume during Outage |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
[add more rows if necessary] |
BSC Season Dates: |
|
Primary BM Unit IDs | Outage First Date | Outage Last Date | Average % Volume during Outage |
Planned outages | |||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
[add more rows if necessary] | |||
Unplanned outages | |||
|
|
|
|
|
|
|
|
|
|
|
|
[add more rows if necessary] |
BSC Season/ Reference Period Dates: |
|
Primary BM Unit IDs | Outage First Date | Outage Last Date | Average % Volume during Outage |
Planned outages | |||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
[add more rows if necessary] | |||
Unplanned outages | |||
|
|
|
|
|
|
|
|
|
|
|
|
[add more rows if necessary] |
Primary BM Unit ID | Proposed WDCALF, NWDCALF or SECALF value | Detailed basis of proposed calculation | Base data appended? | Approve provision of base data to ISG? | Planned Outages factored? | TU calculation applied? |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
[add more rows if required] |
Primary BM Unit ID | Proposed WDCALF, NWDCALF or SECALF value | Detailed basis of proposed calculation | Base data appended? | Approve provision of base data to ISG? | Planned Outages factored? | TU calculation applied? |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
[add more rows if required] |
Primary BM Unit ID | Proposed WDCALF, NWDCALF or SECALF value | Detailed basis of proposed calculation | Base data appended? | Approve provision of base data to ISG? | Planned Outages factored? | TU calculation applied? |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
[add more rows if required] |
BSC Season appealed | Primary BM Units appealed |
|
|
|
|
[add more rows if required] |
|
WDCALF, NWDCALF or SECALF Appeal Reference |
|
Name |
|
Phone Number |
|
Event | Details |
BSC Season being appealed |
|
Date of Publication of WDCALF, NWDCALF or SECALF Values on Elexon Portal |
|
Date of Notice of intention to appeal logged via Elexon Support. |
|
Date Completed Form received from Party |
|
Trading Unit Name: |
| ||||
Primary BM Unit ID | Currently assigned WDCALF, NWDCALF or SECALF Value | P/C Status based on planned submission | GC (MW) to be submitted for Season being appealed | DC (MW) to be submitted for Season being appealed | |
Primary BM Units being appealed | |||||
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
[Add more rows if required] | |||||
Trading Unit Name: |
| ||||
Primary BM Units being appealed |
| ||||
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
[Add more rows if required] |
Primary BM Unit ID | Code | Notes |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
[insert more rows if required] |
(Primary BM Unit ID) | ||||||||||
BSC Season and Year | Appeal Code | WDCALF, NWDCALF or SECALF | Metered Volume | GC | Trading Unit Name | |||||
Initially Assigned | Requested | After Appeal | Achieved | Average | Maximum | |||||
(Latest Year’s Data) |
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| |
(Previous Appeals) |
| |||||||||
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| |
[add more rows as necessary] |
Primary BM Unit ID | Proposed WDCALF, NWDCALF or SECALF value | Detailed basis of proposed calculation | Assumed Average volume or equivalent, where applicable (MWh) | Assumed Maximum volume or equivalent, where applicable (MWh) | Base data appended? | Planned Outages in appealed BSC Season accounted for? |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
[add more rows if required] |
Primary BM Unit ID | Proposed WDCALF, NWDCALF or SECALF value | Detailed basis of proposed calculation | Assumed Average volume or equivalent, where applicable (MWh) | Assumed Maximum volume or equivalent, where applicable (MWh) | Base data appended? | Outages in appealed BSC Season accounted for? |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
[add more rows if required] |
Primary BM Unit ID | Proposed WDCALF, NWDCALF or SECALF value | Detailed basis of proposed calculation | Assumed Average volume or equivalent, where applicable (MWh)) | Assumed Maximum volume or equivalent, where applicable (MWh) | Base data appended? | Outages in appealed BSC Season accounted for? |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
[add more rows if required] |
|
Primary BM Unit ID | Proposal 1 | Proposal 2 | Proposal 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
[insert additional rows if required] |
Party Details | |||
BSC Party ID |
| ||
Authorised Signatory Name |
| ||
Signature |
| ||
Contact Telephone Number |
| ||
Contact Email Address |
| ||
Secondary Contact Name |
| ||
Secondary Contact Telephone Number |
| ||
Secondary Contact Email Address |
| ||
BSC Season Details | |||
Spring | |
| |
Summer | | Tick/Select Season Requested | |
Autumn | | ||
Winter | |
| |
|
|
| |
|
|
|
Primary BM Unit Details | ||||
Primary BM Unit ID | Generation Capacity (MW)5 | Demand Capacity (MW) | Current P/C Status of Primary BM Unit6 | Trading Unit ID |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
BMCAEC | Balancing Mechanism Credit Assessment Export Capability |
BMCAIC | Balancing Mechanism Credit Assessment Import Capability |
QABC | Account Bilateral Contract Volume |
CALF | Credit Assessment Load Factor |
CAP | Credit Assessment Price |
CAQCE | Credit Assessment Credited Energy Volume |
CCP | Credit Cover |
CCPPj | Credit Cover Percentage |
CEIPj | Credit Assessment Energy Indebtedness |
CMRS | Central Meter Registration Service |
CQ | Credit Qualifying |
CRA | Central Registration Agent |
DC | Demand Capacity |
ECCP | Energy Credit Cover |
EIPj | Energy Indebtedness |
FPN | Final Physical Notification |
GC | Generation Capacity |
GSP | Grid Supply Point |
HH | Half Hourly |
MW | Megawatts |
MWh | Megawatt hours |
NHH | Non Half Hourly |
NWDBMCAEC | Non-Working Day Balancing Mechanism Credit Assessment Export Capability |
NWDBMCAIC | Non-Working Day Balancing Mechanism Credit Assessment Import Capability |
NWDCALF | Non-Working Day Credit Assessment Load Factor |
Primary BM Unit | Primary Balancing Mechanism Unit |
QMij | Primary BM Unit Metered Volume |
SECALF | Supplier Export Credit Assessment Load Factor |
SMRS | Supplier Meter Registration Service |
SPD | Settlement Period Duration |
WDBMCAEC | Working Day Balancing Mechanism Credit Assessment Export Capability |
WDBMCAIC | Working Day Balancing Mechanism Credit Assessment Import Capability |
WDCALF | Working Day Credit Assessment Load Factor |
Version |
| Date | Reason for review | Approver |
2.0 |
| 03/10/02 | Document incorporating ISG comments | ISG |
3.0 |
| 30/12/02 | Document incorporating ISG agreed clarification of Exemptable Generating Plant methodologies | ISG |
4.0 |
| 31/01/03 | Document incorporating ISG comments | ISG |
5.0 |
| 22/04/03 | Document incorporating ISG comments | ISG |
6.0 |
| 01/11/03 | Issued for use | ISG |
7.0 |
| 16/12/03 | Issued for use | ISG |
8.0 |
| 31/03/04 | Document incorporating new Appeals pro formas for ISG comment | ISG |
9.0 |
| 02/11/04 | Issued for use | ISG |
10.0 |
| 05/04/05 | Issued for use | ISG |
11.0 |
| 24/05/06 | Issued for use | ISG |
12.0 |
| 01/08/06 | Issued for use | ISG |
13.0 |
| 30/04/07 | Issued for use | ISG |
14.0 |
| 13/02/08 | Issued for use | ISG |
15.0 |
| 24/02/09 | To incorporate changes as per implications of P215 on CALF guidance | ISG |
16.0 |
| 18/12/12 | Transferred to new template, rebadged & hyperlinks updated. Updated to reflect changes in P/C Status rules following implementation of P268 and P269. Clarifications and style changes made for improved readability. Changes to calculation for Supplier Primary BM Units with embedded generation. | ISG140/04 |
17.0 |
| 07/11/13 | Rebranding of BSC Service Desk from Logica to CGI |
|
18.0 |
| 25/06/15 | Updated to reflect introduction of SECALF and generic SECALF for P310 | ISG169/01 |
19.0 |
| 25/02/16 | Updated generic SECALF process | ISG178/01 |
20.0 |
| 01/06/16 | Updated to generic SECALF Values | ISG181/02 |
21.0 |
| 24/01/16 | Updated to reflected P326 changes; and further clarification regarding the Appeals calculations | ISG190/01 ISG191/09 |
22.0 |
| 01/06/17 | New Generic SECALF Values | ISG194/04 |
23.0 |
| 06/06/18 | New Generic SECALF Values and changes to BSC Service Desk Telephone Number | ISG205/01 |
24.0 |
| 28/02/19 | Updated to reflect changes following implementation of P344 | ISG214/06 |
25.0 |
| 21/05/19 | New Generic SECALF Values | ISG217/01 |
26.0 |
| 27/02/20 | Updated to reflect changes following implementation of P394 | ISG225/02 |
27.0 |
| 11/05/20 | Annual Review of SECALF Values | ISG229/01 |
28.0 |
| 04/05/21 | Annual Review of SECALF Values | ISG241/01 |
29.0 |
| 01/02/22 | Updated to allow T_ Consumption BM Units to raise Holiday CALF appeals | ISG250/01 |
30.0 |
| 03/05/22 | Annual Review of SECALF Values | ISG253/06 |
31.0 |
| 06/04/23 | Annual Review of SECALF Values | ISG265/01 |
32.0 |
| 07/05/24 | Annual Review of generic SECALF values and change BSC Service Desk to Elexon Support and BEIS to DESNZ | ISG277/04 |
Intellectual Property Rights, Copyright and Disclaimer
The copyright and other intellectual property rights in this document are vested in Elexon or appear with the consent of the copyright owner. These materials are made available for you for the purposes of your participation in the electricity industry. If you have an interest in the electricity industry, you may view, download, copy, distribute, modify, transmit, publish, sell or create derivative works (in whatever format) from this document or in other cases use for personal academic or other non-commercial purposes. All copyright and other proprietary notices contained in the document must be retained on any copy you make.
All other rights of the copyright owner not expressly dealt with above are reserved.
No representation, warranty or guarantee is made that the information in this document is accurate or complete. While care is taken in the collection and provision of this information, Elexon Limited shall not be liable for any errors, omissions, misstatements or mistakes in any information or damages resulting from the use of this information or action taken in reliance on it. |
1 BSCCo will keep this issue under review and, should a suitable solution be identified, this will be presented to the ISG at a future date. Should ISG members or other interested Parties wish to recommend solutions, they are invited to contact the ISG secretary.
2 Under BSC Section K3.5.5 the P/C Status notified will become effective in the timescales set out in BSCP15. For new Primary BM Unit registrations, this will be 28 days (the length of the registration process). For existing Primary BM Units, this will be two Working Days (or sooner if requested by the Lead Party and agreed by the Central Registration Agent/Elexon).
3 If a Base Primary BM Unit is flagged as an Exempt Export BM Unit then the Supplier can choose the P/C Flag.
4 P394 removed the ability for a BM Unit to be assigned Credit Qualifying Status by the Panel.
5 Generation and Demand Capacities must be provided in MW and not MWh
6 P/C Status of the BM Unit is the Production or Consumption Status of the BM Unit