Compliance testing and protocol approval of settlement Meters and outstations |
Guidance Note |
|
An Asset Meter approved for use in Code of Practice 1, 2, 3, 5 and 10 that is a Half Hourly Integral Outstation Meter;
An Asset Meter whose primary purpose is the measurement of Active Power and/or Active Energy that is not an approved Half Hourly Integral Outstation Meter under 1) above; and
An Asset Meter whose primary purpose is not the measurement of Active Power and/or Active Energy and is not a Half Hourly Integral Outstation Meter. These Embedded Metering Devices are embedded within equipment used for purposes other than the measurement of Active Power and/or Active Energy, such as an EV charging unit or a small scale domestic battery storage unit.
Elexon updates the CoPs from time to time and releases new version of the CoPs. Elexon will release a new version and Issue if the change is material to a Meter or Outstation or Asset Meter. If this is the case, further testing may be required in order to confirm the Meter/Outstation/Asset Meter is compliant with the new Issue of the CoP(s). Where Elexon makes a non-material change, only the version number of the CoP will increase. Version only updates have no impact on existing approvals. For example, if Elexon updates CoP5 Issue 3 version 6 to CoP5 Issue 3 version 7, the difference will not be relevant to existing approvals. A change to the current transformer requirements would be a typical example;
Meter/Outstation/Asset Meter manufacturers are responsible for advising Elexon of any changes to firmware. Where such changes are relevant to an existing approval it may be necessary for further testing to re-confirm compliance; and
Certificates contain product type references, which rarely change. If however, the manufacturer needs to change the type reference, which a CoP approval covers, then the manufacturer should discuss this with Elexon.
update the CoP Compliance and Protocol Approval spreadsheet;
take a paper to the relevant BSC Panel Committees to notify them of the approvals; and
publish a Newscast article to notify industry more generally.
applying for compliance testing (and if the manufacturer chooses to, protocol approval);
reviewing and agreeing test schedules;
agreeing with Elexon which test facility to use;
arranging testing at a suitable test laboratory and delivery of product samples;
providing Elexon with test results; and
arranging for protocol testing with a DC.
acknowledging receipt of applications;
agreeing test schedules;
agreeing test laboratories;
witnessing protocol tests;
reviewing test results;
providing certificates; and
notifying new approvals to industry.
applying for protocol approval;
arranging testing with the manufacturer;
receiving test samples and developing or implementing new protocols;
developing and agreeing test schedules with Elexon; and
agreeing test witnessing dates with Elexon.
Measuring Instruments Directive (MID)22 or Measurements Instruments Regulations (MIR)23 type approved by a Notified Body (MID) or UK Approved Body (MIR) (for use in the below 100kW market) or undergoing MID/MIR type approval; and/or
Approved by BEIS under national legislation (GB approved24) (for use in the above 100kW market) or undergoing GB approval.
Intellectual Property Rights, Copyright and Disclaimer The copyright and other intellectual property rights in this document are vested in Elexon or appear with the consent of the copyright owner. These materials are made available for you for the purposes of your participation in the electricity industry. If you have an interest in the electricity industry, you may view, download, copy, distribute, modify, transmit, publish, sell or create derivative works (in whatever format) from this document or in other cases use for personal academic or other non-commercial purposes. All copyright and other proprietary notices contained in the document must be retained on any copy you make. All other rights of the copyright owner not expressly dealt with above are reserved. No representation, warranty or guarantee is made that the information in this document is accurate or complete. While care is taken in the collection and provision of this information, Elexon Limited shall not be liable for any errors, omissions, misstatements or mistakes in any information or damages resulting from the use of this information or action taken in reliance on it. |
1 The BSC defines a Meter as a device for measuring Active Energy or Reactive Energy.
2 The BSC defines an Outstation as equipment which receives and stores data from a Meter(s) for the purpose, inter alia, of transfer of that metering data to the CDCA or a Data Collector, as the case may be, and which may perform some processing before such transfer and may be one or more separate units or may be integral with the Meter.
3 The BSC defines an Asset Meter as a device for measuring Active Power or Active Energy.
4 The BSC defines Metering Equipment as Meters, Asset Meters, measurement transformers (voltage, current or combination units), metering protection equipment including alarms, circuitry, associated Communications Equipment and Outstations and wiring.
5 ‘Code of Practice for the metering of circuits with a rated circuit capacity exceeding 100MVA for Settlement purposes’.
6 ‘Code of Practice for the calibration, testing and commissioning requirements of Metering Equipment for Settlement purposes’.
7 Remember that Meters provided by Meter manufacturers to their customers, for use in Settlement, will need to be calibrated (an ‘initial’ calibration) in accordance with CoP4.
8 e.g. Electromagnetic compatibility and immunity to electromagnetic high frequency fields.
9 ‘Metering Protocol Approval and Compliance Testing’
10 Section 3.4 ‘Compliance Testing of Metering Equipment for Codes of Practice One, Two, Three, Five and Ten’ or Section 3.6 ‘Compliance Testing of Asset Metering Equipment for Code of Practice Eleven’, as applicable.
11 In the event of any inconsistency between the requirements tested for as set out in BSCP601 and the requirements of the relevant CoP, the provisions of the relevant CoP shall prevail.
12 e.g. ISO/IEC 17025 covering the measurement of Active and Reactive Power/Energy.
13 On 28 June 2007, Change Proposal CP1174 modified BSCP601 to allow Elexon (as the BSC Company (BSCCo) to issue compliance and protocol approval certificates to applicants on behalf of the BSC Panel, where all tests pass, and notify the BSC Panel (i.e. the ISG and the SVG) that they have been issued. Elexon notifies the BSC Panel in the form of a BSC Panel Committee paper.
14 For Metering Equipment that will be registered in the Supplier Meter Registration Service (SMRS) of a Licensed Distribution System Operator (LDSO) against a Metering System ID (MSID) (also known as a Metering Point Administration Number (MPAN) under the Retail Energy Code).
15 For Metering Equipment that will be registered in the Asset Meter Registration Service (AMRS) against an Asset Metring System ID (AMSID).
16 For Metering Equipment that will be registered in the Central Meter Registration Service (CMRS) against an MSID. Typically Metering Equipment associated with Transmission System connected generators/customers, some Distribution System connected generators, Transmission System connections to Distribution Systems (Grid Supply Points (GSPs)), Distribution System connections to other Distribution Systems (Distribution Systems Connection Points (DSCPs)) and Transmission or Distribution System connections to External Systems (e.g. France, Netherlands, Ireland, etc.).
17 The manufacturer usually provides these.
18 BSCP601 provides an example test schedule in section 3.3 ‘Specification for the Testing of Metering Equipment Protocols’. 3.3.2.2 for Protocol Testing of Metering Equipment for Codes of Practice One, Two, Three, Five, Six, Seven and Ten or 3.3.3.2 for Protocol Testing of Asset Metering Equipment for Code of Practice Eleven.
19 ‘Metering Dispensations’.
20 Excluding Asset Meters as these are used for Balancing Services purposes and not used for billing purposes.
21 ‘Protocol Approval and Compliance Testing’. You can find a word copy of the application form on the BSCP601 landing page.
22 From 1st January 2021, meters are approved under the Measuring Instruments Regulations (MIR), as amended by the Product Safety & Metrology etc. (Amendment etc.) Regulations (EU Exit) (SI 2019/696). There was an initial two year transition period up to 31 December 2022 which has been extended to 31 December 2024.
23 MIR is identical to the MID and SI 2016/1153 implements the MID.
24 GB approved meters will be listed on Schedule 4 of the Meters (Certification) Regulations, (SI 1998/1566)