Compliance Testing and Protocol Approval of Settlement Meters and Outstations |
Guidance Note |
Elexon has produced this guidance note to assist those seeking to deploy new
Meters and/or
Outstations or
Asset Meters for use in Half Hourly (HH)
Settlement in the
Great Britain (GB) market. Elexon has primarily aimed this guidance at
Meter/
Outstation/
Asset Meter manufacturers seeking compliance testing approval and protocol approval, who may not be familiar with the
Balancing and Settlement Code (BSC) and its
Code Subsidiary Documents.
Half Hourly Data Collectors (HHDCs) , the
Central Data Collection Agent (
CDCA), and
Asset Metering
Half Hourly Data Collectors (AMHHDCs) will also find this guidance useful when seeking protocol approval for
Outstations they wish to collect HH data from, for use in
Settlement.
The BSC Metering Requirements
The BSC sets out the rules for trading in the wholesale
electricity market and
Settlement of
Secondary BM Units using metering behind the site
Boundary Point (referred to as
Asset Metering).
Section L: Metering requires
Meters and
Outstations, and
Asset Meters used for
Settlement purposes to comply with relevant
Settlement metering
Codes of Practice (CoPs).
For Boundary Point metering, the current suite of CoPs covers Settlement Metering Equipment requirements for circuits at domestic premises all the way up to large sites with circuits that have a rated capacity of over 100MVA (CoP1), e.g. Generating Plant. CoP4 covers the calibration, testing and commissioning of Settlement Metering Equipment and as such is not relevant to this guidance.
For the Asset Metering, CoP11 covers Settlement Metering EquipmentError! Bookmark not defined. requirements for circuits for the metering of Balancing Services Assets.
A single Meter or Outstation may be compliant with a number of CoPs, or in the case of an Asset Meter may be compliant with a number of Asset Metering Types in CoP11, but the relevant CoP, and if applicable Asset Metering Type, for a circuit is the one that is in force at the time the Registrant/Supplier/Asset Metering Virtual Lead Party (AMVLP) responsible for the Metering System or Asset Metering System, comprising that Metering Equipment, first registers it for Settlement purposes.
There are three market sectors within the BSC: the Non Half Hourly (NHH) market, the HH market and the Asset Meter market. The BSC requires HH Meter readings for Settlement. A process called Profiling converts NHH Meter readings to HH Meter readings.
There is no formal process under the BSC for approving
Meters for
Settlement purposes in this sector as the onus is on the
Supplier to ensure compliance with a particular NHH
Settlement CoP. Elexon has produced some guidance on ‘
Smart Metering and Compliance with the BSC’.
As
Settlement Meter readings are required on a HH basis for this sector the relevant CoPs specify additional features such as
Outstations that, among other things, store
Meter readings for later transmission to a HHDC or the
CDCA.
Meters can be combined (integral) with an
Outstation or separate but both must comply with a relevant CoP. A
Meter type that meets the Smart
Metering Equipment Technical Specification (SMETS) is exempt from CoP10 compliance testing and protocol approval. Elexon has produced some guidance on ‘
Smart Metering and BSC Codes of Practice
Asset Meter readings are required on a HH basis for later transmission to an AMHHDC or HHDC. The Asset Meter can store data in a HH basis or use a separate device receiving an output from the Asset Meter that coverts to HH data. Both methods must comply with CoP11.
CoP11 specifies the requirements and Asset Meters are split into three categories:
1) An Asset Meter approved for use in Code of Practice 1, 2, 3, 5 and 10 that is a Half Hourly Integral Outstation Meter;
2) An Asset Meter whose primary purpose is the measurement of Active Power and/or Active Energy that is not an approved Half Hourly Integral Outstation Meter under 1) above; and
3) An Asset Meter whose primary purpose is not the measurement of Active Power and/or Active Energy and is not a Half Hourly Integral Outstation Meter. These Embedded Metering Devices are embedded within equipment used for purposes other than the measurement of Active Power and/or Active Energy, such as an EV charging unit or a small scale domestic battery storage unit.
Only Asset Meters in categories 2) and 3) need to complete compliance testing as an Asset Meter. A Meter used as an Asset Meter in category 1) must have completed compliance testing as a HH Settlement Meter.
Compliance Testing and Protocol Approval
When a manufacturer introduces a new Meter or Outstation, or Asset Meter into the market it needs to consider two Settlement aspects. The first is compliance with the requirements of a CoP and the second is approval of the communications protocol that the Outstation or Asset Meter uses. A manufacturer needs to complete compliance testing of its Meter or Outstation or Asset Meter, and at least one Data Collector (DC) needs to undergo protocol approval (for an Outstation or Asset Meter), before Registrants/Suppliers/AMVLPs can use the Meter or Outstation or Asset Meter in Settlement.
Compliance testing confirms whether a Meter or Asset Meter performs to the required accuracy and external influences do not affect it. In respect of Outstations, compliance testing confirms that the functionality is in accordance with the relevant CoP. In respect of Asset Meters compliance testing confirms that the functionality is in accordance with the relevant Asset Metering Type as specified in CoP11.
The process for compliance testing is set out in
BSC Procedure (
BSCP)
601.
BSCP601 details the necessary tests that the compliance testing body needs to perform
,. If the testing is successful, Elexon will issue a certificate of compliance to the applicant, on behalf of the BSC
Panel, against the relevant issue of a CoP. Note that the
Meter/
Outstation/
Asset Meter must pass
all the relevant tests. Therefore, before testing can begin Elexon and the manufacturer must agree the test schedule to ensure that it is relevant to the product in question. Failure to do so could result in test failures.
Elexon also recommends that, for
Codes of Practice One, Two, Three, Five and Ten, a manufacturer satisfy itself that the
Meter or
Outstation would meet all the requirements set out in the relevant CoP, and the relevant tests for that CoP in
BSCP601, prior to applying for compliance testing approval.
Elexon also recommends that, for
Codes of Practice Eleven, a manufacturer satisfy itself that the
Asset Meter would meet all the requirements set out in the relevant
Asset Metring Type in CoP11, and the relevant tests for that
Asset Metering Type in
BSCP601, prior to applying for compliance testing approval.
Laboratories with recognised relevant accreditations, issued by the
United Kingdom Accreditation Service or other international equivalent bodies, may perform compliance testing providing Elexon has confirmed their suitability before the commencement of any testing. Manufacturers are free to nominate a test laboratory during the application process. It is the responsibility of the manufacturer to identify an appropriate test laboratory, fund testing and provide Elexon with an appropriate test report.
Certificates reference particular Meter/Outstation/Asset Meter products, with specific firmware versions, and the specific CoP Issues with which they comply. A change to any of these particulars after an approval is given will mean that existing certificates no longer apply to the changed product or new CoP Issue. The following are reasons why these items could change:
Elexon updates the CoPs from time to time and releases new version of the CoPs. Elexon will release a new version and Issue if the change is material to a Meter or Outstation or Asset Meter. If this is the case, further testing may be required in order to confirm the Meter/Outstation/Asset Meter is compliant with the new Issue of the CoP(s). Where Elexon makes a non-material change, only the version number of the CoP will increase. Version only updates have no impact on existing approvals. For example, if Elexon updates CoP5 Issue 3 version 6 to CoP5 Issue 3 version 7, the difference will not be relevant to existing approvals. A change to the current transformer requirements would be a typical example;
Meter/Outstation/Asset Meter manufacturers are responsible for advising Elexon of any changes to firmware. Where such changes are relevant to an existing approval it may be necessary for further testing to re-confirm compliance; and
Certificates contain product type references, which rarely change. If however, the manufacturer needs to change the type reference, which a CoP approval covers, then the manufacturer should discuss this with Elexon.
Each HH CoP requires the BSC
Panel (who have delegated responsibility to its Committees the
Imbalance Settlement Group (ISG) and/or the
Supplier Volume Allocation Group (SVG)) to approve the communication protocol used by an
Outstation or
Asset Meter before the
Registrant/
Supplier/AMVLP can use the
Outstation or
Asset Meter for
Settlement purposes. The process for protocol approval is set out in
BSCP601.
In order for BSC
Panel to approve a protocol, it must undergo testing with at least one HHDC or the
CDCA, or at least one AMHHDC
15. Testing will verify that the HHDC or the
CDCA, or the AMHHDC can properly communicate with, and retrieve data from, the
Outstation or
Asset Meter. There are a number of HHDCs, AMHHDCs, and the
CDCA, therefore each DC intending to collect data from a new
Meter/
Outstation/
Asset Meter would require a separate protocol approval. Please see the
Qualified Person Workbook (spreadsheet) on the
BSC Signatories and Authorised Persons page of the Elexon website for a list of HHDCs and AMHHDCs. You can contact the
CDCA at
neta@imserv.com.
In order to carry out protocol testing the relevant HHDC, AMHHDC, or the CDCA requires sample Outstations or Asset Meters . The testing involves setting up the sample Outstations or Asset Meters on a test bench; simulating certain events (e.g. Outstation clock trimming, phase failure(s), reverse running (where fitted), battery failure (where fitted), etc.) and comparing the metered data collected using the manufacturer’s software with the metered data collected by the DC’s data collection software.
Normally, individual DCs apply for protocol approval, although a manufacturer can do this if it chooses to. The HHDC, AMHHDC, or the CDCA will agree a test schedule with Elexon and, when the HHDC, AMHHDC, or CDCA is ready, Elexon will witness their tests. If the Outstation or Asset Meter passes all the tests then Elexon will issue a protocol certificate, to the applicant, on behalf of the BSC Panel. The purpose of this certificate is to verify that the HHDC, AMHHDC, or the CDCA has properly implemented the manufacturer’s protocol into its data collection system.
As with compliance certificates, protocol certificates reference particular products, firmware and data collection systems.
What if a Meter, Asset Meter, or Outstation Fails Compliance or Protocol Testing?
There are a number of options in the event of a failed test.
For compliance testing, the manufacturer can amend the product to correct the defect and further testing may be necessary to verify this. Alternatively, the manufacturer may seek a
Metering Dispensation via a BSC
Party. Under certain circumstances a
Metering Dispensation may be approved, by the relevant BSC
Panel Committee, to allow
Registrants/
Suppliers/AMVLPs to use the product where it is not fully compliant with a CoP.
BSCP32 sets out the
Metering Dispensation application process.
For failed protocol testing, the DC will need to work with the manufacturer and the developer of their data collection software protocols to correct the defect and further testing may be necessary to verify this.
Notification of Approvals to Industry
Once a Meter/Outstation/Asset Meter has passed compliance testing and at least one HHDC, or at least one AMHHDC, or the CDCA has successfully passed protocol approval, Elexon will issue the certificates to the applicant(s). Elexon will then:
All costs associated with compliance testing and protocol approvals are the responsibility of those seeking compliance and/or approval. Elexon will not normally charge for its services but retains the right to recover any reasonable costs in so doing.
The following is a non-exhaustive summary of responsibilities:
Manufacturers are responsible for:
applying for compliance testing (and if the manufacturer chooses to, protocol approval);
reviewing and agreeing test schedules;
agreeing with Elexon which test facility to use;
arranging testing at a suitable test laboratory and delivery of product samples;
providing Elexon with test results; and
arranging for protocol testing with a DC.
Elexon is responsible for:
acknowledging receipt of applications;
agreeing test schedules;
agreeing test laboratories;
witnessing protocol tests;
reviewing test results;
providing certificates; and
notifying new approvals to industry.
applying for protocol approval;
arranging testing with the manufacturer;
receiving test samples and developing or implementing new protocols;
developing and agreeing test schedules with Elexon; and
agreeing test witnessing dates with Elexon.
Meters Used for Billing Purposes
The legislation is Schedule 7 of the Electricity Act 1989 and supporting regulations. Schedule 7 of the Electricity Act requires all meters used for billing to be of an approved pattern or construction and installed in an approved manner.
Applicants for compliance testing approval of a
Meter type (usually the
Meter manufacturer) need to indicate, on the compliance testing application form (
BSCP601/03), the ‘Type approval’ status of the submitted
Meter type(s), i.e. whether the
Meter type is:
Where the relevant body (i.e. Notified Body for MID, UK Approved Body for MIR, or BEIS) has issued a MID/MIR type approval and/or GB approval certificate for a meter type, please provide a copy of the certificate(s) with the application for compliance testing approval (
BSCP601/03). If the MID/MIR and/or GB approval is being conducted in parallel with or following compliance testing approval, please provide a copy of the certificate(s) once the MID/MIR and/or GB approval certificate(s) have been issued. In this case, Elexon will not issue a compliance testing approval certificate until the applicant provides this evidence. This is to avoid giving the impression to the applicant that once Elexon issues a compliance testing approval certificate (and at least one protocol approval certificate) for a
Meter type,
Registrants/
Suppliers can use the
Meter type in the GB market.
Asset Meters shall not be used for billing purposes.
Intellectual Property Rights, Copyright and Disclaimer The copyright and other intellectual property rights in this document are vested in Elexon or appear with the consent of the copyright owner. These materials are made available for you for the purposes of your participation in the electricity industry. If you have an interest in the electricity industry, you may view, download, copy, distribute, modify, transmit, publish, sell or create derivative works (in whatever format) from this document or in other cases use for personal academic or other non-commercial purposes. All copyright and other proprietary notices contained in the document must be retained on any copy you make. All other rights of the copyright owner not expressly dealt with above are reserved. No representation, warranty or guarantee is made that the information in this document is accurate or complete. While care is taken in the collection and provision of this information, Elexon Limited shall not be liable for any errors, omissions, misstatements or mistakes in any information or damages resulting from the use of this information or action taken in reliance on it. |