Advanced Search

Calculation of Residual Cashflow Reallocation Cashflow V4.0

Effective From Date:
Status:LIVE
Download

Calculation of Residual Cashflow Reallocation Cashflow

Guidance Note

Calculation of Residual Cashflow Reallocation Cashflow

For all Settlement Periods, the Total Residual Cashflow (TRC) is calculated as being the sum of all energy imbalance charges across all parties and accounts. This value represents the total amount of money to be redistributed (or collected) via the Residual Cashflow Reallocation Cashflow (RCRC).

Each party will be allocated a Residual Cashflow Reallocation Proportion (RCRP) of the TRC for both of its accounts (Production and Consumption). These proportions will sum to one across the whole market. RCRP is calculated based on the Trading Parties’ proportion of the market credited energy in a particular Settlement Period with the exception of interconnector Balancing Mechanism (BM) Units which are excluded from the calculation. The calculation of RCRP is defined in Section T of the Balancing and Settlement Code.

Credited energy is calculated using the metered energy from Trading Units. The Trading Unit will be determined as a Delivering Trading Unit if the sum of the metered volumes in that Settlement Period is greater than zero.

Please note, that according to this definition, BMUs may flip between being delivering and offtaking from one Settlement Period to another, therefore care must be taken in aggregating the credited energy, ensuring that the correct signs are applied according to the status of the Trading Unit.

Credited energy won’t always have a positive effect on RCRP, for example, negative credited energy (relating to consumption) on a BMU in a delivering Trading Unit will have the effect of reducing that account’s RCRP. To calculate the RCRC for any account, it is necessary to multiply the TRC (£/MWh) figure by the RCRP.

Notes on the RCRC Data

The RCRC is calculated using the Total Residual Cashflow and the RCRP values from the SAA I014 flow. It is also available on the Elexon Portal.

Need more information?

For more information please contact the BSC Service Desk at bscservicedesk@cgi.com or call 0370 010 6950.

Also see:

Intellectual Property Rights, Copyright and Disclaimer

The copyright and other intellectual property rights in this document are vested in Elexon or appear with the consent of the copyright owner. These materials are made available for you for the purposes of your participation in the electricity industry. If you have an interest in the electricity industry, you may view, download, copy, distribute, modify, transmit, publish, sell or create derivative works (in whatever format) from this document or in other cases use for personal academic or other non-commercial purposes. All copyright and other proprietary notices contained in the document must be retained on any copy you make.

All other rights of the copyright owner not expressly dealt with above are reserved.

No representation, warranty or guarantee is made that the information in this document is accurate or complete. While care is taken in the collection and provision of this information, Elexon Limited shall not be liable for any errors, omissions, misstatements or mistakes in any information or damages resulting from the use of this information or action taken in reliance on it.