Balancing and Settlement Code
Code Subsidiary Document
Limit On SVA Connection For SMRS Registered Primary BM Units Where Plant And/Or Apparatus is Registered in another (CVA) Primary BM Unit
Effective Date: 27 June 2019
|
Version | Implementation Date | Description of Change | Mods/ Panel/ Committee Refs |
1.0 | 27 June 2019 | P364 Self-Governance | Panel 291/12 |
Intellectual Property Rights, Copyright and Disclaimer The copyright and other intellectual property rights in this document are vested in ELEXON or appear with the consent of the copyright owner. These materials are made available for you for the purposes of your participation in the electricity industry. If you have an interest in the electricity industry, you may view, download, copy, distribute, modify, transmit, publish, sell or create derivative works (in whatever format) from this document or in other cases use for personal academic or other non-commercial purposes. All copyright and other proprietary notices contained in the document must be retained on any copy you make. All other rights of the copyright owner not expressly dealt with above are reserved. No representation, warranty or guarantee is made that the information in this document is accurate or complete. While care is taken in the collection and provision of this information, ELEXON Limited shall not be liable for any errors, omissions, misstatements or mistakes in any information or damages resulting from the use of this information or action taken in reliance on it. |
A Power Station will have its own internal electricity consumption e.g. to boil the kettle in the control room. This is normally powered by the Power Station itself however, could be used at times where the Power Station itself is not producing power and the normal connection is open but the staff still wants to make tea; and
An onshore wind turbine’s hazard warning light is normally powered by the turbine Power Park Module itself but, if the Power Park Module is not operating and the normal connection is open; an auxiliary supply is required to keep the light on to prevent aircraft from crashing into it.
It is the ISG’s decision whether to review or change the limit, but BSCCo, BSC Parties or the NETSO can request them to do so;
Any change to the limit must not make BSC parties meeting the previous limit non-compliant with the BSC;
The ISG may request assistance from BSCCo e.g. in analysing whether a change is needed;
The ISG can agree a change to the limit based on recommendations by BSCCo or NETSO. It does not need to consult with BSC Parties to introduce a change but may choose to do so; and
This document is owned by BSCCo. Changes to this document will be drafted by BSCCo following ISG agreeing a change to the limit.
1 The other caveats are:
there is no Export through the SVA Metering System;
instantaneous through flow of electricity between the SVA and CVA Metering Systems is not possible; and
instantaneous through flow of electricity between the Transmission System and the Distribution System or between two different Distribution Systems is not possible.
2 ‘auxiliary supply’ and ‘back-up supply’ are used alternately as colloquialisms but are taken to be the same thing in this context