Balancing and Settlement Code
BSC PROCEDURE
OVERVIEW OF TRADING ARRANGEMENTS
BSCP01
Date:
|
Version | Date | Description of Changes | Changes Included | Mods/ Panel/ Committee Refs |
1.0 | 08/08/2000 | Go Active version | n/a | n/a |
2.0 | 30/11/00 | Work Outstanding at Go Active, resolution of inconsistencies, inclusion of consultation comments. | 242,191,216 | 08/009 |
3.0 | 13/8/02 | Change Proposals and Code Modifications for BSC Systems Release 2 | CP563, CP572, CP630; P18A, P49 | ISG/1 |
4.0 | 30/9/02 | Code Modification P2 | P2 | ISG16/166 SVG17/208 |
5.0 | 27/08/02 | Phase 2A (Dec 02) Release – Draft | CP629, CP639 | ISG15/151 ISG11/093 |
6.0 | 25/02/03 | February 03 Release | P71, P78 | ISG 24/265 SVG24/311 |
7.0 | 24/06/03 | June 03 Release | CP736 | ISG17/177 |
8.0 | 04/11/03 | November 03 Release | P107, P82 | 59/009 54/006 |
9.0 | 30/06/04 | CVA Programme June 04 Release | CP945 CP854, CP971 P82 Removal | ISG40/003 |
10.0 | 03/11/04 | CVA Programme Nov 04 Release | CP1032 | TDC58/03 |
11.0 | 23/02/05 | CVA Programme Feb 05 Release | CP1091 BETTA 6.3 P140 |
|
12.0 | 26/06/08 | June 08 Release | CP1223 | SVG84/02 ISG84/01 TDC109/01 PAB84/11 |
13.0 | 05/11/09 | November 09 Release | P217 | Panel 142/06 |
14.0 | 03/11/11 | November 11 Release | P253 | ISG127/02 SVG127/13 |
15.0 | 25/06/15 | June 15 Release | CP1426 | ISG166/06, SVG169/05 |
16.0 | 29/06/17 | June 17 Release | P350 | ISG194/02 SVG196/03 |
17.0 | 02/11/17 | November 17 Release | P342 Alternative | ISG198/04 SVG200/03 |
18.0 | 29/03/19 | 29 March 19 Standalone Release | P369 | P285/12 |
19.0 | 11/12/19 | 11 December 2019 Standalone Release | CP1517 | ISG220/01, SVG223/03 |
20.0 | 27/02/2020 | 27 February 2020 Release | P394 Self-Governance | P297/07 |
21.0 | 01/04/2020 | 1 April 2020 Standalone Release | P354, P388 | ISG227/04, SVG 229/07 |
22.0 | 01/09/2021 | 1 September 2021 Non-Standard Release | P420 | P316/05 |
Intellectual Property Rights, Copyright and Disclaimer The copyright and other intellectual property rights in this document are vested in Elexon or appear with the consent of the copyright owner. These materials are made available for you for the purposes of your participation in the electricity industry. If you have an interest in the electricity industry, you may view, download, copy, distribute, modify, transmit, publish, sell or create derivative works (in whatever format) from this document or in other cases use for personal academic or other non-commercial purposes. All copyright and other proprietary notices contained in the document must be retained on any copy you make. All other rights of the copyright owner not expressly dealt with above are reserved. No representation, warranty or guarantee is made that the information in this document is accurate or complete. While care is taken in the collection and provision of this information, Elexon Limited shall not be liable for any errors, omissions, misstatements or mistakes in any information or damages resulting from the use of this information or action taken in reliance on it. |
BSCP03 | Data estimation and substitution for CVA |
BSCP04 | BM Unit Metered Volumes for Interconnector Users |
BSCP11 | Trading Disputes |
BSCP65 | Registration of BSC Parties and Exit Procedures |
BSCP68 | Transfer of Registration of metering systems between CMRS and SMRS |
BSCP71 | Submission of ECVNs and MVRNs |
BSCP301 | Clearing, Invoicing and Payment |
BSCP501 | Supplier Meter Registration Service |
BSCP502 | Half Hourly Data Collection for Metering Systems Registered in SMRS |
BSCP503 | Half Hourly Data Aggregation for Metering Systems Registered in SMRS |
BSCP504 | Non Half Hourly Data Collection for Metering Systems Registered in SMRS |
BSCP505 | Non Half Hourly Data Aggregation for Metering Systems Registered in SMRS |
BSCP508 | Supplier Volume Allocation Agent |
BSCP602 | SVA Metering System Register |
Ref | Task | Responsibility | Time-scale |
1 | Send to ECVAA Energy Contract Volume Notifications | ECVNA | To be received by ECVAA before the Submission Deadline |
2 | Send to ECVAA: Meter Volume Reallocation Notifications | MVRNA | To be received by ECVAA before the Submission Deadline |
3 | Send the following information (for each BM Unit in respect of which the Lead Party is obliged to submit a FPN or has chosen to submit a FPN) to the NETSO: Final Physical Notification Data Bid / Offer Data (Required only if trading in Balancing Mechanism) Dynamic Data | Lead Parties | To be received by the NETSO before Gate Closure |
4 | Send to BMRA: Market Index Data | Market Index Data Providers | Target by end of Settlement Period |
5 | Accept Bids and Offers as required to meet forecast and actual system conditions. Acceptances which are taken to resolve transmission constraints are SO-Flagged. | NETSO | Not later than 15 minutes following the issue of an Acceptance; or In the case of an Emergency Instruction, as soon as reasonably practicable. |
6 | Energy Transfer and Metering | Lead Parties | Settlement Period |
7 | Send the following information to BMRA (for information / storage) for each BM Unit in respect of which the Lead Party is obliged to submit a FPN or has chosen to submit a FPN to the NETSO: Maximum Export Limit Maximum Import Limit Final Physical Notification Data Dynamic Data Bid Offer Data (for those BM Units for which such data has been provided) Acceptance Data System related Data BM Unit Applicable Balancing Services Volume Data Replacement Reserve Data | NETSO | Target Times:
Not later than 5 minutes following receipt
Not later than 15 minutes following Gate closure for each Settlement Period
Not later than 1200 hrs each day |
8 | Send Final Physical Notification Data to ECVAA. Calculate Indicative System Buy Price and Indicative System Sell Price and publish relevant data | BMRA | Upon receipt from the NETSO.
15 + CADL minutes after end of Settlement Period. |
9 | Send the following information to SAA to enable Settlement: Final Physical Notification Data Balancing Services Adjustment Data Bid Offer Data Acceptance Data Any Dynamic Data received by the NETSO during the Settlement Day BM Unit Applicable Balancing Services Volume Data | BMRA | The next day following the Settlement Day for Balancing Services Adjustment Data, and by 15 minutes following the end of the Settlement Day for the other items.
Within 2 Business Days following the relevant Settlement Period for BM Unit Applicable Balancing Services Volume Data |
10 | Interrogate Metering Systems registered by Parties with the CRA and collect consumption data. Send to relevant Parties: Raw Meter Data together with any validation criteria | CDCA | Send out by Settlement Day +1 (1300hrs) |
11 | Send to SVAA: Tele-switch data | Tele-switch Agent | By +1 WD (by 1000hrs) |
12 | Obtain the following data from relevant authorised providers: Daily temperature parameters by GSP Group Sunset times by GSP Group (annually) Perform Profile Production Run Send Profile Reports to Suppliers and NHHDCs | SVAA | By +1 WD (by 1000hrs)
By +1 WD (by 1700hrs) |
13 | Send to SAA: BM Unit Metered Volumes for the BM Units of each Interconnector User for each Interconnector | IA | By +1 WD |
14 | Send to SAA: Market Index Data | Market Index Data Providers | By +1 WD |
15 | Send to SVAA MSID Pair Delivered Volumes for procured balancing services | VLP | By +1 WD (by 1700hrs) |
16 | Suppliers raise query on Daily Profile Production Reports if necessary and log with Dispute Administrator | Supplier | By +3 WD (by 1000hrs) |
17 | Resolve Daily Profile Production query | SVAA | By +4 WD (by 1300hrs) |
18 | Amend Profile variables ready to re-run Daily Profile Production, if necessary | SVAA | By +4 WD (by 1500hrs) |
19 | If re-run of Daily Profile Production required then carry this out and send revised Daily Profile Production Reports to relevant Suppliers | SVAA | By +4 WD (by 1730hrs) |
20 | Collate information for use in the Interim Information Run Send to SAA: Meter Volume Reallocation Notification, by BM Unit for each Settlement Period Account Bilateral Contract Volumes for each Settlement Period by BSC Party | ECVAA | In accordance with SAA Settlement Calendar |
21 | Carry out CDCA Aggregation for Interim Information Volume Allocation Run using the latest available data, i.e. valid actual meter data and/or agreed estimated meter data (for all missing or invalid readings) and the latest available approved Line Loss Factors, Aggregation Rules, Registration Data and Meter Technical Details. Send to SAA: BM Unit Metered Volumes for each BM Unit GSP Group Take Interconnector Metered Volumes Send to SVAA: GSP Group Take
Send to BSC Parties: GSP Group Take
Send to Lead Party and NETSO BM Unit Aggregation Report | CDCA | By + 4 WD (0900hrs) |
22 | Ensure Agents send to SVAA: Half Hourly Aggregation Files from HHDAs Half Hourly Metering System Metered Volumes from HHDAs Supplier Purchase Matrices from NHHDAs | Suppliers | By +4 WD (0900hrs) |
23 | Carry out Interim Information Volume Allocation Run Calculate the Supplier Volume Allocations for each BM Unit | SVAA | By +4 WD (from 0900hrs) |
24 | Send to SAA: BM Unit Metered volumes for Supplier BM Units Secondary BM Units Demand Volumes Secondary BM Unit Delivered Volumes | SVAA | For receipt by + 5 WD (0900hrs) |
25 | Send Interim Information Volume Allocation Run Reports to relevant Suppliers | SVAA | By +5 WD |
36 | Carry out Interim Information Settlement Run using data from CDCA, ECVAA, SVAA, NETSO and MIDPs and send relevant reports to Parties. Issue IIR Credits/Debits Report to ECVAA. | SAA | By + 5 WD or later if delayed in accordance with the Code |
27 | Implement SVAA resolution on profile query or request arbitration from Disputes Administrator | Supplier | By + 5 WD (by 1600hrs) |
28 | Communicate outcome of arbitration to affected Suppliers and SVAA | Dispute Administrator | By +7 WD (by 1000hrs) |
29 | If arbitration against SVAA, amend profile variables ready to re-run Daily Profile Production | SVAA | By +7 WD (by 1430hrs) |
30 | Implement results from arbitration and send revised profiles to affected Suppliers | SVAA | By +7 WD (by 1800hrs) |
31 | Send MSID Pair Delivered Volumes to SVAA | NETSO | By +11 WD2 |
32 | Estimate volumes for missing or disputed data in accordance with the Code. Carry out CDCA Aggregation for Initial Volume Allocation Run using the latest available data i.e. valid actual meter readings and/or any agreed estimates and the latest available approved Line Loss Factors, Aggregation Rules, Registration Data and Meter Technical Details. Send to Parties: GSP Group Take
Send to Lead Party and NETSO BM Unit Aggregation Report
Send to SVAA: GSP Group Take
Send to SAA: CDCA Aggregation File | CDCA | For receipt by +14 WD |
33 | Ensure Agents send to SVAA: Half Hourly Aggregation Files from HHDAs Half Hourly Metering System Metered Volumes from HHDAs Supplier Purchase Matrices from NHHDAs | Suppliers | By +14 WD |
34 | Carry out Initial Volume Allocation Run Calculate the Supplier Volume Allocations for each BM Unit | SVAA | By +15 WD (from 0900hrs) |
35 | Send to SAA: BM Unit Metered volumes for Supplier BM Units Secondary BM Units Demand Volumes Secondary BM Unit Delivered Volumes Supplier BM Unit Non BMU ABSVD Volume3 | SVAA | For receipt by + 16 WD (0900hrs) |
36 | Send: Relevant Reports to NETSO DUoS Report to Distribution Businesses Initial Volume Allocation Run Reports to Suppliers | SVAA |
By + 16 WD (before 1230hrs)
) )By + 17 WD ) |
37 | Carry out Initial Settlement Run using latest files from NETSO, ECVAA, CDCA and SVAA and MIDPs; and send relevant reports to BSC Parties.
Send Settlement Report to FAA | SAA | By +16 WD (subject to SAA Settlement Calendar) or later if delayed in accordance with the Code
For receipt by + 17 WD (0900hrs) (subject to Payment Calendar) |
38 | Receive Settlement Report from SAA Calculate Payments | FAA | By +17–18 WD (subject to Payment Calendar) |
39 | Send Advice Notes to Payment Parties | FAA | By +17–18 WD (subject to Payment Calendar) |
40 | Funds transfers between Parties’ Banks | FAA | By +20–21 WD (subject to Payment Calendar) |
Ref | Task | Responsibility | Time-scale (*) |
1 | Ensure Agents send to SVAA: Revised Half Hourly Aggregation Files from HHDAs Half Hourly Metering System Metered Volumes from HHDAs Revised Supplier Purchase Matrices from NHHDAs | Suppliers | By T – 6 WD Note: Dependent on SVAA Calendar |
2 | Estimate volumes for missing or disputed data in accordance with the Code. Re-run Aggregation Process using the latest available data i.e. valid actual meter data and/or any agreed estimates and the latest approved Line Loss Factors, Aggregation Rules, Registration Data and Meter Technical Details applicable for the relevant Settlement Day. Send to Parties: CDCA Aggregation Reports Send to SVAA: GSP Group Take Send to SAA: CDCA Aggregation File | CDCA | By T – 6 WD Note: Dependent on SAA Settlement Calendar |
3 | Carry out Reconciliation Volume Allocation Run Calculate the Supplier Volume Allocation for each BM Unit. | SVAA | By T – 5 WD
Note: Dependent on SVAA Calendar |
4 | Send to SAA BM Unit Metered Volumes for Supplier BM Units Secondary BM Units Demand Volumes Secondary BM Unit Delivered Volumes Supplier BM Unit Non BMU ABSVD Volume | SVAA | For receipt by T – 4 WD (0900hrs) Note: Dependent on SVAA Calendar |
5 | Send: Relevant Reports to NETSO Updated DUoS Report to Distribution Businesses Reconciliation Volume Allocation Run Reports to Suppliers | SVAA |
By T – 4 WD (before 1230hrs) ) ) By T – 3 WD ) |
6 * | Carry out Reconciliation Settlement Run using latest available files from NETSO, ECVAA, CDCA and SVAA and MIDP Send to FAA Reconciliation Settlement Report Send to BSC Parties: Reports on financial position | SAA | By T – 4 WD
For receipt by T – 3 (0900hrs) |
7 | Receive Reconciliation Settlement Report from SAA (Notification Date) Calculate Payments | FAA | By T – 3 WD |
8 | Send to Parties Advice Notes | FAA | By T – 3 WD |
9 | Authorise the financial transfers between Parties’ Banks (Payment Date) | FAA | By T |
10 | Send MSID Pair Delivered Volumes to SVAA | NETSO | No later than SD + 45 calendar days5 |
1 Where an upheld Trading Dispute is to be processed after the Final Reconciliation Settlement Run has been performed then a Post-Final Settlement Run or Extra-Settlement Determination may be required as described in BSCP11.
2 Where such data is available to the NETSO
3 Relating to the MSID Pair Delivered Volumes received by the SVAA
4 Note that that Post-Final Settlement or Volume Allocation Runs may be requested after 28 months, but only for the purposes of the Rectification of Past Notification Error
5 Where such data has not been supplied already under Section 4.1.31