HomeRulebook HomeBalancing and Settlement CodeGuidance NotesThe Efr and Efr Escalation ProcessThe Efr and Efr Escalation Process V 6 0
CONTENTS
- What this document covers
- What this document does not cover
- What is EFR?
- When is EFR applied?
- Settlement Performance EFR Plans
- BSC Audit Issue EFR Plans
- Other EFR Plans
- What should I do if I am being considered for EFR?
- What should I do when EFR has been turned on?
- What are the timescales for agreeing a plan?
- What should I include in my EFR Plan?
- Fig. 1: Agreeing an EFR plan
- How will my EFR Plan be monitored, and how do I exit EFR?
- Exiting EFR
- Fig 2: Monitoring and closing an EFR plan
- When is an EFR plan escalated?
- Escalation to the PAB
- How should I Prepare for a PAB Escalation?
- What will happen during and after a PAB Escalation?
- Fig. 3: PAB Escalation
- Escalation to the BSC Panel
- Fig. 4: Panel Escalation
- Do you need more information?
EFR and EFR Escalation Process V6.0
Effective From Date:05/07/2024
Status:SUPERSEDED
Other versions
Download