CONTENTS

  • SCOPE
  • 1. REFERENCES
  • 2. DEFINITIONS AND INTERPRETATIONS
    • 2.1 Active Energy
    • 2.2 Active Power
    • 2.3 Actual Metering Point
    • 2.4 Apparent Energy
    • 2.5 Apparent Power
    • 2.6 CTN
    • 2.7 CVA Customer
    • 2.8 Defined Metering Point
    • 2.9 Demand Period
    • 2.10 Demand Values
    • 2.11 Electricity
    • 2.12 Export
    • 2.13 Import
    • 2.14 Interrogation Unit
    • 2.1 Maximum Aggregated Capacity
    • 2.16 Meter
    • 2.17 Metering Equipment
    • 2.18 Meter Register
    • 2.19 Outstation
    • 2.20 Outstation System
    • 2.21 PARh Meter
    • 2.22 PSTN
    • 2.23 Rated Measuring Current
    • 2.24 Reactive Energy
    • 2.25 Reactive Power
    • 2.2 Registrant
    • 2.27 Settlement Instation
    • 2.28 SVA Customer
    • 2.29 UTC
  • 3. MEASUREMENT CRITERIA
    • 3.1 Measured Quantities and Demand Values
      • 3.1.1 Measured Quantities
      • 3.1.2 Demand Values
    • 3.2 Accuracy Requirements
      • 3.2.1 Overall Accuracy
      • 3.2.2 Compensation for Measurement Transformer Error
      • 3.2.3 Compensation for Power Transformer and Line Losses
  • 4. METERING EQUIPMENT CRITERIA
    • 4.1 Measurement Transformers
      • 4.1.1 Current Transformers
      • 4.1.2 Voltage Transformers
      • 4.1.3 Monitoring of Voltage Transformers
      • 4.1.4 Measurement Transformers Installed on Existing Circuits
    • 4.2 Testing Facilities
    • 4.3 Meters
    • 4.4 Displays and Facilities for Registrant or Supplier Information
      • 4.4.1 Displays
      • 4.4.2 Facilities
    • 4.5 Outstation
    • 4.5.1 Data Storage
      • 4.5.2 Time Keeping
      • 4.5.3 Monitoring Facilities
    • 4.6 Communications
      • 4.6.1 Local Interrogation
      • 4.6.2 Remote Interrogation
    • 4.7 Sealing
  • 5. ASSOCIATED FACILITIES
    • 5.1 Interrogation Unit
    • 5.2 Additional Features
  • 6. ACCESS TO DATA
    • APPENDIX A DEFINED METERING POINTS
    • APPENDIX B LABELLING OF METERS FOR IMPORT AND EXPORT
    • APPENDIX C Non-Settlement Facilities for Registrant or Supplier Information

Code of Practice 2: The Metering of Circuits with a Rated Capacity not Exceeding 100 MVA for Settlement Purposes V2.0