Schedule of Main and SVA Specified Charges

v 21.0
Effective From Date:
Status:LIVE
Other versions
Download

Schedule of Main and SVA Specified Charges

Guidance Note

Schedule of Main and SVA Specified Charges

This schedule sets out the amounts/rates of the Main and SVA Specified BSC Charges, as defined in Annex D-3 of the BSC. These charges are determined each year by the BSC Panel in accordance with Annex D-3 1.2(b).

This document provides information on the original charges, set at NETA Go-Live, and the current values for the 2024/25 BSC Year.

Base Monthly Charge (Annex D-3 3.1(a))

Every Party, with the exception of Virtual Lead Parties (VLPs) and Asset Metering Virtual Lead Parties (AMVLPs) that do not hold Energy Accounts, must pay a flat monthly charge.

Original Charge

2024/25 Charge

£250

£250

CVA Metering System Charge (D-3 3.1(b))

Parties have to pay a charge per Registered CVA Metering System (including those at a Systems Connection Point) for which it has been the Registrant at any point in the month.

Original Charge

2024/25 Charge

£50

£50

CVA BM Unit Charge (D-3 3.1(c))

A charge is made against every CVA BM Unit for which the Party is the Lead Party for all or part of the month. If the BM Unit is a Production BM Unit at an Export Exempt site where there are also one or more Consumption BM Units, then no charge is made. If there are Production BM Units at an Export Exempt site, where there are no Consumption BM Units, then one charge is made for all BM Units at that site.

Original Charge

2024/25 Charge

£100

£0

Notified Volume Charge (D-3 3.1(f))

A charge is also payable against a Party’s Gross Contract Volume (which is defined in D-3.3.2).

Original Charge

2024/25 Charge

£0.0005/MWh

£0.0005 /MWh

Base BM Unit Charge (D-3 3.1(g))

A Supplier must pay a charge for its Base BM Units for each Supplier ID that it uses in the month. This refers to the BM Units automatically allocated under Section K3.3.1(a).

Original Charge

2024/25 Charge

£100

£0

Additional BM Unit Charge (D-3 3.1(i))

If a Supplier has any additional BM Units to those described above for which it is the Lead Party, then it must also pay a charge for those.

Original Charge

2024/25 Charge

£100

£60

Base VLP or AMVLP Monthly Charge (D-3 3.1(j))

Every VLP or AMVLP, who is not also a Trading Party, must pay a flat monthly charge.

Original Charge

2024/25 Charge

£125

£125

Secondary BM Unit Monthly Charge (D-3 3.1(k))

A VLP,AMVLP or VTP must pay a charge for each Secondary BM Unit for which the Party is Lead Party, for all or any part of that month.

Original Charge

2024/25 Charge

£60

£60

SVA Metering System Charge (D-3 4)

In addition to the Main Specified Charges detailed above, Suppliers also have to pay a charge per SVA Metering System that it is the Registrant for during the month.

Original Charge

2024/25 Charge

£0.35

£0.01318

MHHS Implementation Management (D-3 3.1(l))

This charge is payable by each Supplier for each Supplier Volume Allocation (SVA) Metering System for which a Supplier is Registrant on the first day of that month.

Original Charge

2024/25 Charge

£ 0.03847

£ 0.06049

Need more information?

For other information please contact Elexon Support via Elexon Service link

Intellectual Property Rights, Copyright and Disclaimer

The copyright and other intellectual property rights in this document are vested in Elexon or appear with the consent of the copyright owner. These materials are made available for you for the purposes of your participation in the electricity industry. If you have an interest in the electricity industry, you may view, download, copy, distribute, modify, transmit, publish, sell or create derivative works (in whatever format) from this document or in other cases use for personal academic or other non-commercial purposes. All copyright and other proprietary notices contained in the document must be retained on any copy you make.

All other rights of the copyright owner not expressly dealt with above are reserved.

No representation, warranty or guarantee is made that the information in this document is accurate or complete. While care is taken in the collection and provision of this information, Elexon Limited shall not be liable for any errors, omissions, misstatements or mistakes in any information or damages resulting from the use of this information or action taken in reliance on it.