Advanced Search

P339 Implementation Guide

v 2.0
Download

P339 Implementation Guide

Guidance Note

Who should read this implementation guide?

The implementation guide will be of interest to Distribution Network Operators (DNOs), Independent Distribution Network Operators (IDNOs), Half Hourly Data Aggregators (HHDAs) and Suppliers.

What is P339?

Consumption values are categorised for the purposes of volume allocation and reporting (including performance reporting) by a Consumption Component Class (CCC).

Each CCC has a two digit identifier (CCC Id) and is defined by a combination of attributes.

Some of these attributes are associated with individual Metering Systems:

    • Half Hourly or Non Half Hourly

    • Metered or unmetered

    • Import or export

    • 100 kW maximum demand or below 100 kW (for Half Hourly Metering Systems).

In these cases, the Metering System is allocated to an appropriate Measurement Class.

Other attributes of a CCC depend whether values are Consumption or Line Loss values, and actuals or estimates (as notified by the Half Hourly Data Aggregator (HHDA) or Non Half Hourly Data Aggregator (NHHDA)).

P300: Introduction of new Measurement Classes to support Half Hourly DCUSA Tariff Changes, which was implemented in the November 2015 Release, sub-divided Measurement Class E (sub-100kW Half Hourly) into three Measurement Classes E, F and G depending on the type of metering (whole current or Current Transformer metered) and whether the customer premise is domestic or non-domestic. These Measurement Classes share six CCCs for Active Import (AI) and do not currently have any CCCs for Active Export (AE). This means it is not possible to separate AI and AE for these Measurement Classes or to report at Measurement Class level. It is also not possible to provide export data for aggregated Distribution Use of System (DUoS) billing.

P339: Introduction of new Consumption Component Classes for Measurement Classes E-G Introduces new CCCs for Half Hourly Metering Systems with less than 100kW maximum demand to differentiate between:

    • Active Import and Active Export; and

    • Measurement Classes E, F and G.

The CCCs previously associated with Measurement Classes E, F and G collectively ((i.e. 23, 25, 26, 28, 30 and 31) will be associated exclusively with Measurement Class E.

What are Measurement Classes E, F and G?

The below 100kW Measurement Classes are defined as follows:

    • E - Half Hourly Metering Equipment at below 100kW Premises with current transformer;

    • F - Half Hourly Metering Equipment at below 100kW Premises with current transformer or whole current, and at Domestic Premises;

    • G - Half Hourly Metering Equipment at below 100kW Premises with whole current and not at Domestic Premises.

What Measurement Classes should Suppliers use for Export Metering Systems?

Measurement Classes are defined in terms of the premises at which the Metering Equipment is installed. So an Export Metering System should be allocated to the same Measurement Class as the import Metering System at the same premises.

What are the new (and amended) CCC Ids?

The new (and amended) CCC Ids are set out in the table below. All the CCC Ids listed below relate to Half Hourly metered energy.

CCC Id / Measurement Class

E

F

G

HH Active Import Consumption (Actuals)

23

42

54

Active Import Metering System Specific Line Losses (Actuals)

25

43

55

Active Import Metering System Non-Specific Line Loss (Actuals)

26

44

56

Active Import Consumption (Estimates)

28

45

57

Active Import Metering System Specific Line Losses (Estimates)

30

46

58

Active Import Metering System Non-Specific Line Loss (Estimates)

31

47

59

Active Export Consumption (Actuals)

36

48

60

Active Export Metering System Specific Line Losses (Actuals)

37

49

61

Active Export Metering System Non-Specific Line Loss (Actuals)

38

50

62

Active Export Consumption (Estimates)

39

51

63

Active Export Metering System Specific Line Losses (Estimates)

40

52

64

Active Export Metering System Non-Specific Line Loss (Estimates)

41

53

65

When will the new (and amended) CCC Ids be introduced?

Elexon will raise a Market Domain Data (MDD) Change Request by 2 February 2017 for inclusion in MDD Version 253, with a publish date of 8 March 2017 and a go-live date of 15 March 2017. Associated GSP Group Correction Factor Scaling Weights will be introduced at the same time.

Please note that, although the CCC Ids will be live from 15 March 2017, they should not be used until the implementation date of 1 April 2017. If HHDAs intend to deploy P339 software ahead of the implementation date, we would recommend incorporating date-specific logic to ensure that aggregation files are not rejected.

What changes do HHDAs need to make?

HHDAs will allocate HH Import or Export volumes to the relevant CCC Id in the Aggregated Half Hour Data File (D0040) or BM Unit Aggregated Half Hour Data File (D0298) data flows sent to the Supplier Volume Allocation Agent (SVAA). The allocation of energy will depend on the Measurement Quantity (i.e. whether Active Import or Active Export) and the Metering System’s Measurement Class, as notified by the Supplier Meter Registration Service (SMRS)).

In line with the changes to the D0040 and D0298 introduced by P300:

    • the top sections of the flows (the ‘SUP’ group and its nested sub-groups) will contain data for all CCC Ids; and

    • the bottom sections of the flows (the ‘37J’ group in the D0298, ‘24J’ group in the D0040, and their nested sub-groups ) will contain data for CCC Ids associated with Measurement Classes F and G (whether Active Import or Active Export).

The data for CCC Ids associated with Measurement Classes F and G will thus be aggregated twice – once for the purposes of the Settlement calculations and, separately, for the purposes producing the Aggregated DUoS Report (D0030).

What is the effective date of the new CCC Ids?

CCC Ids do not have an effective date. HHDAs should use the new CCC Ids for all aggregation runs performed on or after the implementation date. So, for example, all runs scheduled for Monday 3 April 2017 (the P339 implementation date is Saturday 1 April 2017) should use the new CCC Ids, even though the Settlement Dates of these runs will pre-date the implementation date.

Suppliers also need to be aware that Reconciliation Runs from 1 April 2017 in respect of dates earlier than 1 April 2017 will contain the new CCC Ids.

What happens if the HHDAs carries out an aggregation run in advance of the scheduled date in the Settlement Calendar?

If an HHDA uses the new CCC Ids before the SVAA has implemented the amended P339 software (expected to be on Thursday 30 March 2017), this will cause an error.

CCC Ids 23, 25, 26, 28, 30 and 31 will be associated with Measurement Class E going forward, but were previously associated with Measurement Classes E, F or G. If the HHDA submits data for a Measurement Class G Metering System using CCC Ids 23-31 (i.e. before implementing its P339 changes), the SVAA will process this as if it were allocated to Measurement Class E. This won’t impact the Settlement calculations as Measurement Classes E, F and G are all processed in the same way. It won’t impact the D0030 report, because the SVAA will continue to accept all CCC Ids associated with Measurement Classes E, F and G, and will use the Line Loss Factor Class Id to differentiate between the volumes for Measurement Classes F and G.

What happens if the HHDA is unable to implement its P339 changes ahead of the 3 April runs?

As described above, the SVAA will continue to process CCC Ids 23-31 for the purposes of the D0030. This will ensure that DUoS billing is correct in the event that:

    • D0040/D0298 flows received by the SVAA on or soon after the implementation date were produced before HHDAs implemented their P339 changes; or

    • HHDAs are late in implementing their P339 changes; or

    • HHDA data is defaulted to a pre-1 April 2017 Run Type.

It also has the advantage that HHDAs do not need to implement any date-specific logic as part of their P339 changes. However, it means that the onus is on HHDAs to ensure that Measurement Class E data is not included in the bottom sections of the D0298/D0040 flows (i.e. the ‘37J’ group in the D0298, ‘24J’ group in the D0040 and their nested sub-groups). This is in accordance with the existing Data Transfer Catalogue (DTC) rules.

What do DNOs/IDNOs need to set up and when?

DNOs and IDNOs will need to send the SVAA a revised ‘Mapping Data for HH Aggregated Metering Systems’ (P0239) flow. Elexon will receive and check these flows on behalf of the SVAA. Please email the mapping data to jon.spence@Elexon.co.uk.

The revised P0239 file will need to include a new ‘dummy SSC’ for export and a mapping of this SSC to an appropriate export Line Loss Factor Class (LLFC). For the year from 1 April 2017, the export SSC will be single-rate i.e. have a single Time Pattern Regime (TPR). If DCUSA Change Proposal DCP268 ‘DUoS Charging Using HH settlement data’ is approved, multi-rate SSCs may need to be introduced for future years.

Additionally, if a host DNO is introducing new red-amber-green periods from April 2017, these will need to be included as new dummy SSCs in the P0239, along with new LLFC mappings, ‘dummy TPR’s and ‘clock intervals’.

The recommended timetable for providing this data is shown below.

Who

What

When

DNO

Submit revised P0239 mapping file to Elexon

By 10/02/2017

Elexon

Notify IDNOs of new DNO ‘dummy SSCs’

By 17/02/2017

IDNO

Submit revised P0239 mapping file to new LLFs (D0265) for any LLFCs requested in MDD version 230

By 17/03/2017

Elexon

Publish revised mapping details on Elexon website

By 31/03/2017

What is the format of the mapping file (P0239)?

complex image of process

Please note:

    • if IDNOs use the same SSC, Measurement Requirements and Clock Intervals as DNOs, they will only need to provide the LLF Group;

    • The file should be in standard Data Transfer Catalogue (DTC) format – i.e. a pipe-delimited format;

    • You can find definitions of the data items in the Data Transfer Catalogue;

    • The File Type should be ‘P0239001’;

    • LLFCs mapped to the Export SSC should have a MS Specific LLFC Indicator of ‘C’ = ‘General LLF Class Export (i.e. those associated with the LV Generation HH or Aggregate HH DUoS tariff);

    • Old LLFCs can be mapped to new Import SSCs, if revised red-amber-green periods have been defined;

    • Old LLF/SSC mappings should be retained for use in Reconciliation runs;

    • Effective From Settlement Date {LLFSSC} for any new mappings should be set to ‘20170401’;

    • The new Export SSC should have an Effective From Settlement Date {SSC} of ‘20170401’;

    • Where Red, Amber, Green periods have been revised;

        • The end-dated SSC should be retained, along with its associated TPRs and Clock Intervals (for use in Reconciliation Runs);

        • The old SSC should have an Effective To Settlement Date {SSC} of ‘20170331’

        • a new SSC should be set up with an Effective from Settlement Date {SSC}

    • Values for ‘Day of the Week Id’ are – 1=Monday, 2=Tuesday, 3=Wednesday, 4=Thursday, 5=Friday, 6=Saturday, 7=Sunday

    • midnight (start of day) is always expressed as 000000 and midnight (end of day) as 240000;

more than one LLFC can be mapped to the same SSC; but

    • an LLFC must not be mapped to more than one SSC (at any point in time);

    • Record Count is inclusive of the Header and Footer records.

An example P0239 data flow is shown in Appendix A.

What codes should DSOs use for the ‘dummy SSCs’ and TPRs

The SSCs and associated TPRs and Clock Intervals will not be registered in MDD. In order to ensure that ‘dummy’ SSCs and TPRs are kept distinct from ‘real’ SSCs and TPRs, we recommend that DNOs and IDNOs adopt the following numbering convention in their mapping files.

The SSCs set up in November 2015 were of the form 9SCn where 9 is a constant and SC = the Distributor Short Code for the host DNO for the relevant GSP Group. The final integer was set to 1.

If the host DNO is using different Red, Amber, Green periods from 1 April 2017, we recommend incrementing the final digit of the SSC to 2.

TPRs are of the form 9SCn1, 9SCn2 and 9SCn3, where 1, 2 and 3 represent Red, Amber and Green respectively.

For the new export SSCs, there will be a single TPR from 1 April 2017, noting that this could change if DCUSA Change Proposal DCP268 is approved. As all DNOs will be using a single rate SSC, we recommend using a standard dummy SSC Id for export of 9991 with a TPR of 99911.

GSP Group Id

GSP Group

Nov 15 SSC

TPRs

Export SSC

TPR

April 17 SSC (if required)

TPRs

_A

Eastern

9101

91011 red

91012 amber

91013 green

9991

99911

9102

91021 red

91022 amber

91023 green

_B

East Midlands

9111

91111

91112

91113

9991

99911

9112

91121

91122

91123

_C

London

9121

91211

91212

91213

9991

99911

9122

91221

91222

91223

_D

Merseyside and North Wales

9131

91311

91312

91313

9991

99911

9132

91321

91322

91323

_E

Midlands

9141

91411

91412

91413

9991

99911

9142

91421

91422

91423

_F

Northern

9151

91511

91512

91513

9991

99911

9152

91521

91522

91523

_G

North Western

9161

91611

91612

91613

9991

99911

9162

91621

91622

91623

_H

Southern

9201

92011

92012

92013

9991

99911

9202

92021

92022

92023

_J

South Eastern

9191

91911

91912

91913

9991

99911

9192

91921

91922

91923

_K

South Wales

9211

92111

92112

92113

9991

99911

9212

92121

92122

92123

_L

South Western

9221

92211

92212

92213

9991

99911

9222

92221

92222

92223

_M

Yorkshire

9231

92311

92312

92313

9991

99911

9232

92321

92322

92323

_N

South Scotland

9181

91811

91812

91813

9991

99911

9182

91821

91822

91823

_P

North Scotland

9171

91711

91712

91713

9991

99911

9172

91721

91722

91723

Who should I contact if I have any further questions?

Please contact Kevin Spencer (kevin.spencer@Elexon.co.uk / 020 7380 4115) or Jon Spence (jon.spence@Elexon.co.uk / 020 7380 4313), or

For more information please contact the BSC Service Desk or call 0370 010 6950.

Intellectual Property Rights, Copyright and Disclaimer

The copyright and other intellectual property rights in this document are vested in Elexon or appear with the consent of the copyright owner. These materials are made available for you for the purposes of your participation in the electricity industry. If you have an interest in the electricity industry, you may view, download, copy, distribute, modify, transmit, publish, sell or create derivative works (in whatever format) from this document or in other cases use for personal academic or other non-commercial purposes. All copyright and other proprietary notices contained in the document must be retained on any copy you make.

All other rights of the copyright owner not expressly dealt with above are reserved.

No representation, warranty or guarantee is made that the information in this document is accurate or complete. While care is taken in the collection and provision of this information, Elexon Limited shall not be liable for any errors, omissions, misstatements or mistakes in any information or damages resulting from the use of this information or action taken in reliance on it.