BSC Codes of Practice and Smart Meters

v 8.0
Effective From Date:
Status:LIVE
Other versions
Download

BSC Codes of Practice and Smart Meters

Guidance Note

Compliance with BSC Codes of Practice and Smart Metering

In June 2013 Elexon raised Issue 48 ‘SMETS & Codes of Practice (CoPs)’. The Issue 48 workgroup compared the requirements in BSC Code of Practice 8, 9 and 10 with those in version 2.0 of the Smart Metering Equipment Technical Specifications (SMETS v2.0). The workgroup noted that the SMETS v2.0 refers to compliance with ‘the wider statutory and regulatory framework applying to devices installed for the purpose of energy supply to premises’. The workgroup concluded that SMETS v2.0 Meters would need to meet any additional requirements of the BSC CoPs, where relevant.

Although the Issue 48 workgroup carried out the gap analysis with reference to SMETS2 meters, the group’s conclusions apply equally to version 1.2 of the Smart Metering Equipment Technical Specifications (SMETS v1.2) and should also apply to subsequent versions.

This guidance sets out the requirements in the BSC CoPs that Suppliers will need to comply with, over and above those in the SMETS. In Feb 2017 CP14661 was implemented to clarify that SMETS compliant Meters exceed the requirements of CoP10 and that BSC approval of such meters is not required.

Non Half Hourly Metering Systems

Non Half Hourly (NHH) Meters should comply with CoP82, CoP93 or CoP104. All refer to the requirements in Schedule 7 of the Electricity Act 1989 in relation to the accuracy of data. SMETS Meters must also comply with these requirements and those of the Measuring Instruments (Active Electrical Energy Meters) Regulations 2006. The analysis carried out by the Issue 48 workgroup showed that SMETS Meters meet the requirements of CoP9 for NHH whole current import/export metering (compliance with CoP8 will no longer be relevant as SMETS Meters will record both import and export). The SMETS do not cover Current Transformer operated Meters, so these will need to comply with the relevant additional requirements in CoP9 or CoP10.

Half Hourly Metering Systems

In general, Meters that comply with the SMETS will also comply with the main requirements of CoP10. In some cases, the SMETS requirements exceed those of CoP10, for example the data storage requirements. SMETS Meters will not meet the ‘Security Regime Requirements’ in Section 5.6 of CoP10 (i.e. the use of three levels of password to control access). However, the Smart Metering Key Infrastructure (SMKI) will provide a higher level of security. The BSC CoPs set out minimum requirements. By exceeding the security requirements in CoP10, a SMETS Meter would be compliant with CoP10.

To use SMETS Meters for Half Hourly (HH) Settlement, Suppliers will need to ensure that they meet the additional requirements listed in Table A to achieve CoP10 compliance.

Table A

CoP10 Reference

Requirement

Comment

5.1 - 5.3

Current Transformers

The SMETS do not cover Current Transformer metering. The CoP10 requirements will apply.

5.4.1

Displays

Although the SMETS Meter records Import kvarh and Export kvarh, there is no requirement to display these.

Other display capabilities that the SMETS do not include are Maximum Demand (MD) kVA, Cumulative MD and number of MD resets. However, these are optional requirements, ‘as specified by the Registrant’. It is unlikely that Suppliers will require these features for the significant majority of domestic and small non-domestic sub-100kW Metering Systems.

5.5

Protocol Approval

Meters that are SMETS compliant do not require approval under BSCP601 ‘Metering Protocol Approval and Compliance Testing’.

5.5

Time Synchronisation

The responsibility will move from the HHDC to the Supplier/DCC and is part of the protocol approval process.

5.5

Separately fused supply for modems

There are requirements in the SMETS about the supply to Communications Hubs.

5.5.1

Data Storage

There are no SMETS equivalents to the requirements that –

  • ‘the resolution of the Active Energy transferred into the demand registers shall be within ±0.1% (at full load) of the amount of Active Energy measured by the associated Meter’;

  • energy measured in a Demand Period but not stored in that Demand Period should be carried forward to the next Demand Period;

  • the clock and calendar can function for 20 days without an external supply.

5.5.2

Time Keeping

There are no SMETS requirements to maintain time keeping accuracy allowing for failures to communicate of 20 days.

5.5.3

Monitoring / Alarms

There are no SMETS requirements for –

  • battery monitoring

  • Demand Periods truncated or extended by a time synchronisation;

  • Metering equipment functionality errors.

Need more information?

For more information please contact the BSC Service Desk or call 0370 010 6950.

Intellectual Property Rights, Copyright and Disclaimer

The copyright and other intellectual property rights in this document are vested in Elexon or appear with the consent of the copyright owner. These materials are made available for you for the purposes of your participation in the electricity industry. If you have an interest in the electricity industry, you may view, download, copy, distribute, modify, transmit, publish, sell or create derivative works (in whatever format) from this document or in other cases use for personal academic or other non-commercial purposes. All copyright and other proprietary notices contained in the document must be retained on any copy you make.

All other rights of the copyright owner not expressly dealt with above are reserved.

No representation, warranty or guarantee is made that the information in this document is accurate or complete. While care is taken in the collection and provision of this information, Elexon Limited shall not be liable for any errors, omissions, misstatements or mistakes in any information or damages resulting from the use of this information or action taken in reliance on it.

1 Removing SMETS compliant Meters from the scope of BSCP601

2 Code of Practice 8: Code of Practice for the Metering of Import Active Energy via Low Voltage Circuits for Non-Half Hourly Settlement Purposes

3 Code of Practice 9: Code of Practice 9: The Metering of Import and Export Active Energy via Low Voltage Circuits for Non-Half Hourly Settlement Purposes

4 Code of Practice 10: Metering of Energy via Low Voltage Circuits for Settlement Purposes