BM Units – Registration of Balancing Mechanism (BM) Units |
Guidance Note |
|
BM Unit Type | Prefix | Overview |
Directly Connected | T_ | Primary BM Units directly connected to the Transmission System. |
Embedded | E_ | Primary BM Units embedded within a Distribution System. |
Interconnector | I_ | Primary BM Units related to an Interconnector. |
Supplier | 2_ | Primary BM Units covering Supply. These contain all of a particular Supplier’s Meters for a given Grid Supply Point (GSP) Group in either a Base or Additional Supplier Primary BM Unit. |
C_ | These Additional Supplier Primary BM Units are registered solely for the purpose of allocating Contracts for Difference (CfD) Assets. | |
Secondary | V_ | Secondary BM Units may be registered by a Virtual Lead Party to provide TERRE Balancing Services to the NETSO. |
Miscellaneous | M_ | Other types of Primary BM Units that don’t fit the above categories. This prefix does not apply to newly registered Primary BM Units. |
What is a Directly Connected Primary BM Unit? | Directly Connected Primary BM Units comprise of equipment directly connected to the Transmission System. They are usually Generation Units, relating to Power Stations or other Generating sites (e.g. wind farms) but can also be large demand sites. The equipment within each Primary BM Unit is independently controlled, and is metered separately. |
Do I need to do anything before registering one? | You normally need to Qualify as a Generator to register Generation Directly Connected Primary BM Units or as a Supplier to register Demand Primary BM Units. If the Primary BM Unit will be Exempt Export (see below for more details), you may also register the Primary BM Unit if you are a Qualified Supplier.
Visit the Market Entry page or BSCP65: Registration of Parties and Exit Procedures for more details.
Before you submit the Primary BM Unit registration form you must contact the NETSO , to discuss any obligations and sign the necessary contractual agreements. The NETSO1 will give you a NGC BM Unit Id. |
What forms do I need to fill in? | BSCP15/4.1 gives general details of the Primary BM Unit(s) you’re registering. You must send the BSCP15/4.1 form to the Central Registration Agent2 (CRA) at least 30 Working Days (standard Primary BM Unit) or at least 60 Working Days (non-standard Primary BM Unit) before the Effective From Date (EFD). A BM Unit can also be registered on the Self-Service Gateway (Elexon Kinnect Customer Solution).
BSCP15/4.13 requests a non-standard Primary BM Unit configuration. If your Primary BM Unit is non-standard, this must be submitted in addition to the BSCP15/4.1 form or the BM Unit can also be registered on the Self Service Gateway (Elexon Kinnect Customer Solution).
BSCP20/4.13 registers the Metering Systems related to your Primary BM Unit(s) and must be sent to the CRA2 at least 20 Working Days before the EFD.
BSCP20/4.3 registers the Meter Technical Details (MTDs) related to the Metering Systems of your Primary BM Unit(s), and is usually submitted by the Meter Operator Agent (MOA) to the CDCA2 at least 16 Working Days before the EFD. It can also be submitted by the Registrant of the Metering System.
BSCP75/4.2 details the Aggregation Rules for the Primary BM Unit(s) and must be sent to the CDCA at least 20 Working Days before the EFD4 .
BSCP02 details the Proving Test that your MOA must carry out on the Metering System. This must be completed at least 8 Working Days before the EFD.
You must provide an electrical single line diagram of the site showing:
|
What information do I provide on the BSCP15/4.1 form? | The NGC BM Unit ID is the ID provided by the NETSO (where the Final Physical Notification (FPN) flag is Y).
The Primary BM Unit ID has a prefix of ‘T_’ followed by the NGC BM Unit ID.
The Primary BM Unit Type is ‘T’ for Directly Connected and the Primary BM Unit Configuration depends on what type of Unit it is – please check the list at the bottom of the form.
You need to enter the Generation Capacity (GC) and Demand Capacity (DC) of each Primary BM Unit, as well as the Final Physical Notification (FPN) Flag. If you are using the Self-Service Gateway (Elexon Kinnect Customer Solution) you will need to enter the Maximum +ve QMij, and Maximum Negative QMij which will be doubled in the system to give the GC and the DC.
If the Primary BM Unit will be Exempt Export (see below for more details), you must put ‘Y’ in the relevant column, and complete a BSCP15/4.5 form. The Exempt Export information can also be registered on the Self-Service Gateway (Elexon Kinnect Customer Solution).
Finally, you need to state the proposed date on which the Primary BM Unit will become effective.
Further guidance on completing this form is given in the ‘completing the BSCP15/4.1’ section below. |
What other information is needed? | If you register the Primary BM Unit(s) as Exempt Export, refer to the Exempt Export section which covers additional processes that you need to follow. |
When do I need to submit these forms by? | You need to start the process at least 30 Working Days before your proposed Effective From Date if your Primary BM Unit is standard or at least 60 Working Days before your Effective From Date if your Primary BM Unit is non-standard. Forms can be submitted in any order, providing you meet the timescales above. Alternatively, this information (apart from the BSCP15/4.13 form) can be completed via the Self-Service Gateway (Elexon Kinnect Customer Solution). |
What is an Embedded Primary BM Unit? | Embedded Primary BM Units comprise of equipment that is connected to a Distribution Network. They are Generation Units relating to Power Stations or other generating sites (e.g. wind farms). They can include the imports relating to these sites, but large embedded demand sites without any generation cannot be registered as a Central Volume Allocation (CVA) Primary BM Unit. The equipment within each Primary BM Unit is independent of other Units, and is metered separately. |
Do I need to do anything before registering one? | You need to Qualify as a Generator to register Embedded Primary BM Units. If the Primary BM Unit will be Exempt Export (see below for more details), you may also Qualify as a Supplier to register the Primary BM Unit or elect another Generator or Supplier Party to register the Primary BM Units.
Visit the Market Entry page or BSCP65: Registration of Parties and Exit Procedures for more details.
Before you submit the Primary BM Unit registration form, and if you wish to participate in the Balancing Mechanism (i.e. (FPN) Flag is set to Yes) you must contact the NETSO5 , to discuss any obligations and sign the necessary contractual agreements. The NETSO will give you NGC BM Unit Id(s). |
What forms do I need to fill in? | BSCP15/4.1 gives general details of the Primary BM Unit(s) you’re registering. You must send the BSCP15/4.1 form to the Central Registration Agent6 (CRA) at least 30 Working Days (standard Primary BM Unit) or at least 60 Working Days (non-standard Primary BM Unit) before the Effective From Date (EFD). BM Units can also be registered on the Self-Service Gateway (Elexon Kinnect Customer Solution).
BSCP15/4.13 requests a non-standard Primary BM Unit configuration. BM Units can also be registered on the Self-Service Gateway (Elexon Kinnect Customer Solution).
BSCP20/4.17 registers the Metering Systems related to your Primary BM Unit(s) and must be sent to the CRA2at least 20 Working Days before the EFD.
BSCP20/4.3 registers the Meter Technical Details (MTDs) related to the Metering Systems of your Primary BM Unit(s), and is usually submitted by the Meter Operator Agent (MOA) to the CDCA2 at least 16 Working Days before the EFD. It can also be submitted by the Registrant of the Metering System.
BSCP75/4.2 details the Aggregation Rules for the Primary BM Unit(s) which must include reference to CVA Line Loss Factors and must be sent to the CDCA at least 20 Working Days before the EFD8 .
BSCP02 details the Proving Test that your MOA must carry out on the Metering System. This must be completed at least 8 Working Days before the EFD.
You must provide an electrical single line diagram of the site showing:
|
What information do I provide on the BSCP15/4.1 form? | The NGC BM Unit ID is provided by the NETSO (where FPN flag is Y).
The Primary BM Unit ID has a prefix of ‘E_’ followed by the NGC BM Unit ID.
The Primary BM Unit Type is ‘E’ for Embedded. The Primary BM Unit Configuration depends on what type of Unit it is - please check the list at the bottom of the form.
You need to enter the GC and DC of each Primary BM Unit, as well as the FPN Flag, and the GSP Group ID in which the Primary BM Unit is located. If you are using the Self-Service Gateway (Elexon Kinnect Customer Solution) you will need to enter the Maximum +ve QMij, and Maximum Negative QMij which will be doubled in the system to give the GC and the DC.
If the Primary BM Unit will be Exempt Export (see below for more details), you must put ‘Y’ in the relevant column, and complete a BSCP15/4.5 form.
Finally, you need to state the proposed date on which the Primary BM Unit will become effective.
Further guidance on completing this form is given in the ‘completing the BSCP15/4.1’ section below. |
What other information is needed? | Embedded Primary BM Units need CVA Line Loss Factors (LLFs) for use in their Aggregation Rules. The relevant Licensed Distribution System Operator (LDSO) is responsible for submitting them within the LLF timescales in BSCP128: Production, Submission, Audit and Approval of Line Loss Factors. Please ask the LDSO to submit CVA LLFs (as opposed to SVA LLFs) for the site and to cancel any SVA MPANs that they may have created for the site.
If you register the Primary BM Unit(s) as Exempt Export, refer to the Exempt Export section, which covers additional processes that you need to follow. |
When do I need to submit these forms by? | You need to start the process at least 30 Working Days before your proposed Effective From Date if your Primary BM Unit is standard or at least 60 Working Days before your Effective From Date if your Primary BM Unit is non-standard. Forms can be submitted in any order, providing you meet the timescales above. Alternatively, this information (apart from the BSCP15/4.13 form) can be completed via the Self-Service Gateway (Elexon Kinnect Customer Solution). |
only one Party is responsible for the Exports and/or Imports from or to the Plant and/or Apparatus registered in Central Meter Registration Service (CMRS) (another Party may be responsible for an Supplier Meter Registration Service (SMRS) registered connection as in point (d));
the Exports and/or Imports relating to the Primary BM Unit are capable of being controlled independently of any other Exports and/or Imports which do not relate to the Primary BM Unit;
the Metered Volumes from the Primary BM Units Plant and Apparatus are submitted separately from any Plant and Apparatus not part of the Primary BM Unit
the Primary BM Unit does not contain Plant and/or Apparatus whose Imports and Exports are measured by both CVA and SVA Metering Systems except where:
Plant and Apparatus with a Registered Capacity of less than or equal to the size of a Small Power Station may be aggregated up to the size of a Small Power Station9 (size applicable to both Imports and Exports) within a single Primary BM Unit. A Primary BM Unit comprised of Plant and Apparatus with a Registered Capacity of greater than the size of a Small Power station must be the smallest aggregation of the Plant and Apparatus for which the requirements mentioned in (a) to (c) would be met.
A description of the Plant and Apparatus, where it connects to the Total System and the location of the Metering Equipment with reference to the electrical single line diagram; and
The Plant and Apparatus that is to be included in each of the non-standard Primary BM Unit(s) and any other standard Primary BM Units at the boundary point(s) with reference to the electrical single line diagram; and
The clause(s) of BSC Section K 3.1.2 that the non-standard Primary BM Unit does not satisfy and why; and / or
The benefits of the non-standard Primary BM Unit configuration compared to a different configuration and / or the limitations of a different configuration; and / or
Any relevant costs associated with the non-standard Primary BM Unit configuration (as opposed to a standard Primary BM Unit configuration if appropriate), e.g. metering costs, BSC Costs.
where different Parties are responsible for the Import to and Export from the same Plant and Apparatus. In this scenario each Party must register a Primary BM Unit, one for the Import and one for the Export;
where all or part of the Import to the Plant and Apparatus is metered by Metering Systems registered in both CMRS and SMRS. This may be a single Metering System registered in both SMRS and CMRS at a single Boundary Point or separate Metering Systems at separate Boundary Points. The Primary BM Units may be registered by the same or different Parties; or
Power Park Modules which belong to a Switching Group.
Generating Unit;
Closed Cycle Generating Turbine (CCGT) Module;
Power Park Module (PPM);
Power Station Transformers (Station Transformers)
Directly Connected Demand at a single Boundary Point Combined Offshore BM Unit (COBMU) ;
Directly connected Demand at more than one Boundary Point provided that the total Imports are equal to or less than 50MW in England and Wales, 30MW in South Scotland and 10MW in North Scotland;
Supplier (Base or Additional) Primary BM Unit;
Interconnector Primary BM Unit
Any BM Units that were determined as part of the transitional arrangements for the implementation of the British Electricity Trading and Transmission Arrangements (BETTA)
An Offshore PPM or COBMU10 and its associated Low Voltage Assets
Combination of Generating Units connected to the Total system provided that the total Exports are equal to or less than 50MW in England and Wales, 30MW in South Scotland and 10MW in North Scotland
Electricity Storage Module provided that the total Exports are equal to or less than 50MW in England and Wales, 30MW in South Scotland and 10MW in North Scotland
Hybrid Plant – PPM or combination of Generating Units plus Storage Module provided that the total Exports are equal to or less than 50MW in England and Wales, 30MW in South Scotland and 10MW in North Scotland
Open Cycle Gas Turbines (OCGTs) (including CCGT conversions);
Two or more onshore PPMs controlled as a single entity;
Combination of Generating Units or Electricity Storage Module or hybrid Plant (generation plus storage) connected to the Total System, with total Exports greater than 50MW in England and Wales, 30MW in South Scotland and 10MW in North Scotland;
Directly Connected Premises at more than one Boundary Point with total Imports greater than 50MW in England and Wales, 30MW in South Scotland and 10MW in North Scotland;
Back-up assets for a CVA Primary BM Unit registered in SVA of more than 415V.
What is an Interconnector Primary BM Unit? | Interconnector Primary BM Units allow Parties to trade over a particular Interconnector, and always come in pairs. One of the Primary BM Units is for electricity entering the System over the Interconnector (Production), and the other is for electricity being taken off the System (Consumption). Each Interconnector has many pairs of these Primary BM Units, one pair for each Party who has registered to use it.
Interconnector Primary BM Units work differently to other Primary BM Units because the electricity is not metered for each Party’s Primary BM Units, but at the Interconnector Boundary. The Interconnector Administrator submits the deemed Primary BM Unit Metered Volume on the Party’s behalf. The difference between the Interconnector Metered Volume and the Primary BM Unit Metered Volumes (deemed to have been delivered) is attributed to the Interconnector Error Administrator. For more information about Interconnectors please refer to Interconnector Trading. |
Do I need to do anything before registering one? | You need to Qualify as an Interconnector User to register Interconnector Primary BM Units. Visit the Market Entry page or BSCP65: Registration of Parties and Exit Procedures for more details.
Before submitting the Primary BM Unit registration form, you must contact the NETSO11 , to discuss your obligations and sign the necessary contractual agreements. The NETSO will give you NGC BM Unit names. |
What forms do I need to fill in? | BSCP15/4.1 gives general details of the Primary BM Unit(s) you’re registering. This must be sent to the CRA 30 Working Days before the Effective From Date. BM Units can also be registered on the Self-Service Gateway (Elexon Kinnect Customer Solution). |
What information do I provide on the BSCP15/4.1 form? | The NGC BM Unit ID is the ID provided by the NETSO.
The Primary BM Unit ID has a prefix of ‘I_’ followed by the NGC BM Unit ID.
The Primary BM Unit Type is ‘I’ for Interconnector, and the Primary BM Unit Configuration will be ‘IC’ for Interconnector Unit.
For the Production Primary BM Unit (i.e. electricity flowing into the GB Transmission System), enter a positive GC, a zero DC and a ‘P’ for Production/Consumption (P/C) Flag. If you are using the Self-Service Gateway (Elexon Kinnect Customer Solution) you will need to enter the Maximum +ve QMij which will be doubled in the system to give the GCC.
For the Consumption Primary BM Unit (i.e. electricity flowing from the GB Transmission System), enter a zero GC, a negative DC and a ‘C’ for the Flag.
If you are using the Self-Service Gateway (Elexon Kinnect Customer Solution) you will need to enter the Maximum Negative QMij which will be doubled in the system to give the DC.
In both cases, the FPN Flag is ‘Y’.
Finally, enter the Interconnector ID for the Interconnector these Units are for (i.e. FRANCE, MOYLE, BRITNED, EWIC, NEMOLINK, ELECLINK, IFA2), and the date that the Primary BM Units will be effective from.
Further guidance on completing this form is given in the ‘completing the BSCP15/4.1’ section below. |
When do I need to submit these forms by? | You must submit the BSCP15/4.1 form at least 30 Working Days before your proposed Effective From Date. |
What is a Supplier Primary BM Unit? | Supplier Primary BM Units measure the amount of electricity supplied by Suppliers. Due to the high number of Supplier Meters that exist, individually identifying them all is unfeasible. Instead, all the Meters for a particular Supplier ID in a specific GSP Group are grouped into one Supplier Primary BM Unit.
When a Party signs up as a Supplier, they must register 14 ‘Base’ Supply Primary BM Units, one for each GSP Group, even if they do not plan to use them all. All their supply and SVA registered embedded generation in a particular GSP Group will by default be allocated to the relevant Base Primary BM Unit.
A Party can register ‘Additional’ Primary BM Units for particular sites, or grouping of Customers, within a GSP Group. |
Do I need to do anything before registering one? | You need to Qualify as a Supplier to register Supplier Primary BM Units. Visit the Market Entry page or BSCP65: Registration of Parties and Exit Procedures for more details.
Your Base Primary BM Units need to be registered as part of becoming a Supplier.
Additional Units can be registered at the same time as Base Primary BM Units or any time after.
The Effective Dates of Supplier Primary BM Units must be on or after the next eligible Market Domain Data (MDD) Go-Live Date. MDD Go-Live dates are published on the MDD Release Schedule.
Before you submit the Primary BM Unit registration form, and if you wish to participate in the Balancing Mechanism (i.e. (FPN) Flag is set to Yes) you must contact the NETSO12 , to discuss any obligations and sign the necessary contractual agreements. The NETSO will give you NGC BM Unit Id(s). |
What forms do I need to fill in? | BSCP509 F509/01 is the MDD Change request form and BSCP509 Appendix 1 form MDD Entity Id 61 gives the details of the Supplier, GSP Group and BM Unit Id mapping for inclusion in Market Domain Data (MDD). These must be sent to the MDD Coordinator13 by the fast track CR deadline for the Version of MDD you want the changes to be included in. Please see the MDD Release Schedule for a list of these dates. BSCP15/4.1 gives general details of the Primary BM Unit(s) that you are registering. This must be sent to the CRA at least 15 Working Days before the Effective From Date which must be on or after the next eligible MDD Go-Live Date. |
What information do I provide on the BSCP15/4.1 form? | The Base Primary BM Unit ID is 2__XPPPP000, where X is the relevant GSP Group letter, PPPP is your four-letter Supplier Market Participant Identifier (MPID), and 000 represents your Base Primary BM Unit. Additional Primary BM Units are numbered sequentially, i.e. 001, 002 etc, within each GSP Group.
If you are submitting FPNs, the NETSO will provide you with the NGC BM Unit ID.
The Primary BM Unit Type is ‘G’ if these are your Base Primary BM Units, and ‘S’ if you are registering Additional Primary BM Units. The Primary BM Unit Configuration is either ‘BB’ for a Base Unit or ‘AB’ for an Additional Unit.
You need to enter the Generation and Demand Capacities (GC and DC) of each Primary BM Unit as well as the FPN Flag. You need to state the date on which the Primary BM Unit will be effective from (this must be on or after the next eligible MDD Go-Live Date). If you are using the Self-Service Gateway (Elexon Kinnect Customer Solution) you will need to enter the Maximum +ve QMij, and Maximum Negative QMij which will be doubled in the system to give the GC and the DC. |
What other information is needed? | If you register the Primary BM Unit(s) as Exempt Export, refer to the Exempt Export section, which covers additional processes that you need to follow. Note that if a Supplier Primary BM Unit is registered as an Exempt Export BM Unit, it must satisfy the conditions for a standard Primary BM Unit or be approved by the Panel as a non-standard Primary BM Unit as set out in the section above, as if it were an embedded Primary BM Unit. |
When do I need to submit these forms by? | You must submit the BSCP15/4.1 form at least 15 Working Days before your proposed Effective From Date which must be on or after the next eligible MDD Go-Live Date. You must submit your MDD forms in line with the MDD Release Schedule. Alternatively, this information can be completed via the Self-Service Gateway (Elexon Kinnect Customer Solution). |
Is there anything else I need to do? | If you register an Additional Primary BM Unit, you need to allocate SVA MSIDs to that Additional Primary BM Unit using the process contained in BSCP503: Half Hourly Data Aggregation for SVA Metering Systems Registered in SMRS section 3.5, otherwise these Primary BM Units will remain in the Base Supplier Primary BM Unit.
If you wish to use an Additional Primary BM Unit for Balancing Services, you need to allocate SVA MSIDs to it using the process contained in BSCP602: SVA Metering System Balancing Services Register section 2.1 |
Are there any other options? | If you wish to register an Additional Primary BM Unit in every GSP Group you may wish to register an additional Market Participant Identifier (MPID) under your Trading Party Id instead14 . This would have the effect of creating another set of 14 Supplier Primary BM Units under the new MPID and which would carry no extra BSC Charges. Creating a set of 14 Additional BM Units, one in each GSP Group would cost £840 in BSC Charges (see the Schedule of Main and SVA Specified Charges). If registering an additional MPID you should consider the impact that splitting your portfolio may have on your reporting e.g. DTN, PARMs.
To register an additional MPID you need to submit forms BSCP65/05, BSCP15/4.1, BSCP509 F509/01 MDD Change request form and BSCP509 Appendix 1 form MDD Entity Ids 1, 45 and 61. The Process is described in BSCP65 Section 4.8 and BSCP15 Section 3.3 |
What is a Secondary BM Unit? | Secondary BM Units record the amount of Balancing Energy provided by Virtual Lead Parties to the NETSO as a Balancing Services Provider. |
Do I need to do anything before registering one? | You need to Qualify as a Virtual Lead Party to register Secondary BM Units. Visit the Market Entry page or BSCP65: Registration of Parties and Exit Procedures for more details.
Before submitting the Secondary BM Unit registration form, you must contact the NETSO15 , to discuss your obligations and sign the necessary contractual agreements. The NETSO will give you NGC BM Unit Id(s). |
What forms do I need to fill in? | BSCP15/4.14 gives general details of the Secondary BM Unit(s) you are registering. This must be sent to the CRA at least 15 Working Days before the Effective From Date. BM Units can also be registered on the Self-Service Gateway (Elexon Kinnect Customer Solution). |
What information do I provide on the BSCP15/4.14 form? | The Secondary BM Unit ID is V__XPPPP000, where X is the relevant GSP Group letter, PPPP is your four-letter Market Participant Identifier, and 00n where n are numbered sequentially, i.e. 001, 002 etc, within each GSP Group. The NETSO will provide you with the NGC BM Unit ID. You need to state the date on which the Secondary BM Unit will be effective from. |
When do I need to submit these forms by? | You must submit the BSCP15/4.14 form at least 15 Working Days before your proposed Effective From Date. |
Is there anything else I need to do? | You need to allocate SVA MSIDs to the Secondary BM Unit using the process contained in BSCP602: SVA Metering System Balancing Services Register section 2.1. |
What is an Exempt Export Primary BM Unit? | Some Generating Plants are ‘Exemptable’, which means that the Lead Party doesn’t need a Generation Licence. If the Lead Party of an Exemptable Generating Plant applies for and is granted exempt export status under the BSC, it can receive Embedded Benefits (if embedded) and declare its own P/C flag (embedded or directly connected). | |
What is the benefit of being Exempt Export? | For embedded Plant, depending on its the size, the benefits of being Exemptable apply to some or all of:
Further information can be found in the Embedded Generation and Embedded Benefits guidance.
For Exempt Export Primary BM Units, you declare your own P/C Flag, which is then fixed. You are able to change your P/C flag as required but it will always take the flag that you choose. | |
How can I nominate a Primary BM Unit as Exemptable? | Some generators meet the conditions of a Statutory Instrument exempting them from the requirement to hold a Generation Licence. There are class exemptions which apply to all generators that meet the conditions and individual exemptions for other generators. More information can be found on the Department of Business, Energy and Industrial Strategy website.
If you wish for your Primary BM Unit to be treated as exemptable under the BSC, you must apply for this status. You can do this with the initial Primary BM Unit Registration, or separately at a later date.
Note that a Primary BM Unit associated with SVA registered Metering and Exempt Export status can only contain the Exemptable Generating Plant for which it is being registered, it cannot contain additional generation or demand. A Base Primary BM Unit can have an Exempt Export status, if it contains a single Exemptable Generating Plant. A Party that wishes to flag a Base Primary BM Unit as Exempt Export Status needs to ensure that they do not allocate any other Generation or Demand to that Primary BM Unit.
Alternatively an Additional Supplier Primary BM Unit can be registered and flagged as Exempt Export Status to contain an Exemptable Generating Plant. Note that an Exemptable Generating Plant does not have to be included in an Exempt Export Primary BM Unit under the BSC; however exemptable benefits can only be applied to Exempt Export Primary BM Units. | |
What forms do I need to fill in? | For CVA Primary BM Units:
You must submit BSCP15/4.5A to apply for the Exempt Export status for a CVA-registered Primary BM Unit and to choose the P/C Flag to Elexon at least 20 Working Days before the required date. Alternatively, this information can be completed via the Self-Service Gateway (Elexon Kinnect Customer Solution). | For SVA Primary BM Units:
You must submit BSCP15/4.9A to apply for the Exempt Export status for an SVA-registered Primary BM Unit and to choose the P/C Flag to Elexon16 at least 20 Working Days before the required date. Alternatively, this information can be completed via the Self-Service Gateway (Elexon Kinnect Customer Solution). If registering an Additional Primary BM Unit, you will also need to allocate the Metering System associated with the Exemptable Generating Plant to the Additional Primary BM Unit via BSCP503. |
What other information is needed? | For CVA Primary BM Units:
We need to check whether the Primary BM Unit is eligible to be Exemptable. Once Elexon has verified this, we will confirm or reject your application. | For SVA Primary BM Units:
All you need to do is submit a BSCP15/4.9A form to us, and Elexon will confirm the status. |
How do I change the P/C Flag? | Exempt Export Primary BM Units must elect their own P/C Flag when they are first registered as exemptable using the BSCP15/4.5A (CVA) or BSCP15/4.9A (SVA) form. If the Lead Party wishes to change the P/C Flag of an Exempt Export Primary BM Unit, the Lead Party must send the CRA and Elexon a BSCP15/4.8 form stating whether they will have a Production or Consumption Flag. Alternatively, this information can be completed via the Self-Service Gateway (Elexon Kinnect Customer Solution). |
Transmission Loss Multipliers (TLMs);
Production/Consumption flag;
Certain BSC costs; and
Balancing Services Use of System (BSUoS) charges.
Primary BM Unit Registration Details | ||||||||||||
Primary BM Unit Id | Primary BM Unit Name (Max 30 Characters) | NG BM Unit ID | Primary BM Unit Type | Primary BM Unit Configuration | GSP Group Id | GC (MW) | DC (MW) | Inter-connector Primary BM Unit P/ C Flag | FPN Flag (Y/N) | Exempt Export (optional) | Inter-connector Id | EFD
|
T – Directly Connected Primary BM Unit, connected to the Transmission System;
E – Embedded Primary BM Unit, connected to a Distribution System;
I – Interconnector Primary BM Unit;
G – Base Supplier Primary BM Unit; or
S – Additional Supplier Primary BM Unit.
CCGT – Combined Cycle Gas Turbine registered in Central Meter Registration Service (CMRS);
PPM – a single Power Park Module registered in CMRS;
COBMU – a Combined Offshore BM Unit comprising 2 or more Offshore Power Park Modules registered in CMRS. This configuration must be agreed by the NETSO;
DC – Directly Connected Circuit at Customer (Supplied by BSC Party) Premises (there must be one Primary BM Unit for each circuit connected to the Transmission System);
DC+ – Directly Connected Circuit at Customer (Supplied by BSC Party) Premises through more than one Boundary Point. Total demand must be less than 50MW in England and Wales, 30 MW in South Scotland and 10 MW in North Scotland;
IC – Interconnector Primary BM Unit;
BB – Supplier Base Primary BM Unit. There will be 14 of these on the form, one for each GSP Group;
AB – Additional Primary BM Unit;
OPPM+ - Offshore PPM plus related Imports at separate Boundary Points;
COBMU+ - COBMU plus related Imports at separate Boundary Points;
MC – Meets criteria in BSC K3.1.2. If meets criteria is selected, you need to complete the table in the form to confirm you meet the five criteria for a Primary BM Unit detailed in Section K 3.1.2 of the BSC; or
NS – Non-standard Primary BM Unit. If non-standard Primary BM Unit is selected, you also need to submit a BSCP15/4.13 form.
FRANCE;
MOYLE;
BRITNED;
EWIC;
NEMOLINK
ELECLINK; or
IFA2
the location of the Metering Equipment, in particular the Settlement current and voltage transformers (CTs/VTs) and CT/VT ratios; and
any existing Boundary Points and/ or System Connection Points at or near the proposed Boundary Point(s); and
any back up SVA connection and interlocking arrangements.
Intellectual Property Rights, Copyright and Disclaimer
The copyright and other intellectual property rights in this document are vested in Elexon or appear with the consent of the copyright owner. These materials are made available for you for the purposes of your participation in the electricity industry. If you have an interest in the electricity industry, you may view, download, copy, distribute, modify, transmit, publish, sell or create derivative works (in whatever format) from this document or in other cases use for personal academic or other non-commercial purposes. All copyright and other proprietary notices contained in the document must be retained on any copy you make.
All other rights of the copyright owner not expressly dealt with above are reserved.
No representation, warranty or guarantee is made that the information in this document is accurate or complete. While care is taken in the collection and provision of this information, Elexon Limited shall not be liable for any errors, omissions, misstatements or mistakes in any information or damages resulting from the use of this information or action taken in reliance on it. |
3 A Metering System ID (MSID) for your BM Unit can be reserved by contacting the CRA.
4 The Aggregation Rules guidance explains how to write your Aggregation Rules.
6 neta@imserv.com
7 A Metering System ID (MSID) for your BM Unit can be reserved by contacting the CRA. If you are registering both Export and Import relating to the site, then you will need to check with the LDSO if they intend to apply a separate CVA Line Loss Factors (LLFs) to the Export and to the Import – if so, then you will need two MSIDs (one for Export, one for Import).
8 The Aggregation Rules guidance explains how to write your Aggregation Rules.
9 Small Power Station is defined in the Grid Code as a Power Station with a Registered Capacity of less than 50MW in England and Wales, less than 30MW in South Scotland and less than 10MW in North Scotland and Offshore.
10 The NETSO must agree that two or more Power Park Modules can be combined into a Combined Offshore BM Unit.
14 Note that if you have a contact with the NETSO to participate in the Balancing Market with these BM Unit, it may require you to register Additional BM Units as opposed to an additional MPID.
17 A Metering System ID (MSID) for your BM Unit can be reserved by contacting the CRA.