Change of CVA Primary BM Unit Lead Party (CoPBLP) process
Transfer of Supplier ID process.
What is a CoPBLP? | A CoPBLP is the procedure used to transfer one or more Primary BM Units with Central Volume Allocation (CVA) Metering from one registered BSC Party (the existing Lead Party) to another (the new Lead Party). The CoPBLP will not result in any change to Meter Technical Details (BSCP20/4.3), Meter Operator Agent (MOA), Aggregation Rules (BSCP75), Trading Unit (BSCP31), or Primary BM Unit data (BSCP15 – except the change of Lead Party). If the new Lead Party wishes to change any of this data, additional processes will need to be carried out which could impact the timescales for the transfer.
|
As a new Lead Party do I need to do anything before undertaking a CoPBLP? | You need to Qualify as a Generator to register Directly Connected Generation or Demand Primary BM Units, or as a Supplier to register Directly Connected Demand Primary BM Units. If the Primary BM Unit is Licence Exempt Export, you may also register the Primary BM Unit if you are a Qualified Supplier Visit the Market Entry page or BSCP65: Registration of Parties and Exit Procedures for more details. If the Primary BM Unit has a Final Physical Notification Flag (FPN) of ‘Yes’, then before you submit the COPBLP form the existing and new Lead Parties must contact the National Electricity Transmission System Operator (NETSO), to discuss any obligations (in particular, if there is a change of Control Point, or a change of Trading Agent, which may extend the timescales), initiate the Change of NGC BM Unit Lead Party process and sign the necessary contractual agreements.
|
What forms do I need to fill in? | The existing Lead Party must submit a BSCP15/4.11 Part A form. The new Lead Party must submit a BSCP15/4.11 Part B form. Alternatively, this information can be completed via the Self Service Gateway (Elexon Kinnect Customer Solution). The ‘Effective From’ Date on the BSCP15/4.11 Part B must be the day after the ‘Effective To’ Date on the BSCP15/4.11 Part A.
The existing and new Lead Parties must agree the transfer date between themselves. The CoPBLP will take place at midnight on the Effective From Date. This date can be a weekend or Bank Holiday.
|
What information do I provide on the BSCP15/4.11 form? | The new Lead Party should obtain the Primary BM Unit details required to complete the form from the existing Lead Party. If the Primary BM Unit is Exempt Export, the new Lead Party can choose the P/C Flag which does not have to be the same as the existing P/C flag.
|
What other information is needed? | If the Primary BM Unit(s) are currently part of a Trading unit, this process will transfer the Trading Unit to the new Lead Party. If the new Lead Party wishes to change the configuration of the Trading Unit then BSCP31 ‘Trading Units’ may need to be followed. If the Primary BM Unit(s) currently have a Metering Dispensation, this process will transfer the Metering Dispensation associated with the corresponding MSIDs to the new Lead Party. If there are any changes in the Metering which affects the Metering Dispensation, processes in BSCP32 ‘Metering Dispensations’ may need to be followed. The CoPBLP procedure will invalidate any Metering Volume Reallocation Notices (MVRNs) submitted by the existing Lead Party for the transferred Primary BM Unit(s). If the new Lead Party wishes to submit a new MVRN for the Primary BM Unit(s) after they become responsible for it, a valid Metering Volume Reallocation Notices Agent (MVRNA) Authorisation needs to be set up. See below for more information. You may need to review the impact that the CoPBLP may have on your Credit Cover. You may need to review your reporting requirements, including where you have given other parties permission to see your reports.
|
When do I need to submit these forms by? | Both the BSCP15/4.11 Part A and Part B need to be received at least 5 Working Days before the Transfer (subject to satisfying the NETSO’s requirements if the FPN is ‘Yes’). Alternatively, this information can be completed via the Self-Service Gateway (Elexon Kinnect Customer Solution). |
What is a Transfer of Supplier ID? | A Transfer of Supplier ID is the procedure which transfers all the Primary BM Units associated with a Supplier ID from one Supplier (the Supplier ID Transferor) to another Supplier (Supplier ID Transferee). The number of Supplier IDs obtained through the Transfer of Supplier ID process (change of SVA Primary BM Unit Lead Party) is unlimited. All Primary BM Units associated with the Supplier ID are linked and will be transferred together. Note that if the Lead Party of the Primary BM Units also had a Virtual Lead Party participation capacity, the Secondary BM Units are not transferred during a Transfer of Supplier Id and would remain with the original Virtual Lead Party.
|
As the Supplier ID Transferee do I need to do anything before undertaking a Transfer of Supplier ID? | You need to be qualified as a Supplier and you should have a Supply Licence or should be able to assure Elexon that you are exempt from that requirement. Visit the Market Entry page or BSCP65: Registration of Parties and Exit Procedures for more details. If any of the Primary BM Units under the Supplier ID to be transferred have a Final Physical Notification Flag (FPN) of ‘Yes’, before you submit the Transfer of Supplier ID forms, the existing and new Lead Parties must contact the NETSO, to discuss any obligations (in particular, if there is a change of Control Point, or a change of Trading Agent, which may extend the timescales), initiate the Change of NGC BM Unit Lead Party process and sign the necessary contractual agreements.
|
What forms do I need to fill in? | The Supplier ID Transferor must complete a BSCP15/4.6 Part A form. If the Supplier ID being transferred is the Supplier ID Transferor’s last Supplier ID (i.e. they will no longer be a Supplier), they must also complete a BSCP65/01 form to de-register as a Supplier. Alternatively, this information can be completed via the Self-Service Gateway (Elexon Kinnect Customer Solution). The Supplier ID Transferee must complete a BSCP15/4.6 Part B form. The ‘Effective From’ Date on the BSCP15/4.6 Part B must be the same day as the ‘Effective From Date’ on the BSCP15/4.6 Part A. The Supplier ID Transferor and the Supplier ID Transferee must agree the transfer date between themselves. The Supplier ID Transfer will take place at midnight on the Effective From Date. This date can be a weekend or Bank Holiday. As a result of the Supplier ID Transfer, Party address details in Market Domain Data (MDD) may need to be changed. This is achieved by completing a MDD Change Request Form in BSCP509 along with Entity Forms 1 and 45 and submitting it to the mddc@Elexon.co.uk. Note that Elexon will inform all BSC Parties and the Authority of the transfer details in accordance with Section S1.4 of the BSC.
|
What information do I provide on the BSCP15/4.6 form? | The new Lead Party should obtain the Primary BM Unit details required to complete the form from the existing Lead Party.
|
What other information is needed? | If any of the SVA MSIDs currently have a Metering Dispensation, this process will transfer the Metering Dispensation associated with the corresponding SVA MSIDs to the new Lead Party. If there are any changes in the Metering which affect the Metering Dispensation, processes in BSCP32 ‘Metering Dispensations’ may need to be followed. The Transfer of Supplier ID procedure will invalidate any MVRN submitted by the existing Lead Party for the transferred Primary BM Unit(s). If the new Lead Party wishes to submit a new MVRN for the Primary BM Unit(s) after they become responsible for it, a valid MVRNA Authorisation needs to be set up. See below for more information. You may need to review the impact that the Transfer of Supplier ID may have on your Credit Cover. You may need to review your reporting requirements, including where you have given other parties permission to see your reports.
|
When do I need to submit these forms by? | If Elexon receives notice before midday on a Working Day a Supplier ID transfer can take effect the following day. If the request is after midday on a Working Day the transfer will take place on the second day following. This is the minimum lead-time for the process (subject to satisfying the NETSO’s requirements if the FPN is ‘Yes’). |
Name | Description | Telephone | |
Participant Management Team Elexon | The CoPBLP and Supplier ID Transfer process and BSCP15 | 020 7380 4376 | |
Dispensation Team Elexon | Metering Dispensations (BSCP32) and Trading Units (BSCP31) | 020 7380 4033 | |
Participant Management Team Elexon | Market Entry, BSCP65 and BSCP71 | 020 7380 4322 | |
NETSO Helpdesk | NETSO Registration issues/queries (including EDT and EDL) | 0800 085 4806 | |
IMServ | IMServ: CRA and ECVAA | 0870 833 5602 |
BSCP15 | BM Unit Registration |
BSCP20 | Registration Metering Systems for Central Volume Allocation |
BSCP31 | Registration of Trading Units |
BSCP32 | Metering Dispensations |
BSCP38 | Authorisations |
BSCP65 | Registration of Parties and Exit Procedures |
BSCP71 | ECVNA and MVRNA Registration, Authorisation and Termination |
BSCP509 | Changes to Market Domain Data |
Intellectual Property Rights, Copyright and Disclaimer
The copyright and other intellectual property rights in this document are vested in Elexon or appear with the consent of the copyright owner. These materials are made available for you for the purposes of your participation in the electricity industry. If you have an interest in the electricity industry, you may view, download, copy, distribute, modify, transmit, publish, sell or create derivative works (in whatever format) from this document or in other cases use for personal academic or other non-commercial purposes. All copyright and other proprietary notices contained in the document must be retained on any copy you make.
All other rights of the copyright owner not expressly dealt with above are reserved.
No representation, warranty or guarantee is made that the information in this document is accurate or complete. While care is taken in the collection and provision of this information, Elexon Limited shall not be liable for any errors, omissions, misstatements or mistakes in any information or damages resulting from the use of this information or action taken in reliance on it. |