CODE OF PRACTICE THREE CODE OF PRACTICE FOR THE METERING OF CIRCUITS WITH A RATED CAPACITY NOT EXCEEDING 10MVA FOR SETTLEMENT PURPOSES. Issue 5 Version 3.00 DATE Code Effective Date |
CODE OF PRACTICE FOR THE METERING OF CIRCUITS WITH A RATED CAPACITY NOT EXCEEDING 10MVA FOR SETTLEMENT PURPOSES.
For and on behalf of the Panel.
ISSUE | DATE | VERSION | CHANGES | AUTHOR | APPROVED |
Draft | 18/3/93 | 0.03 | Recommended to PEC | MSC | |
1 | 15/4/93 | 1.00 | Endorsed by PEC | COP WG | |
| 19/4/95 | 1.01 | Draft | COPWG | |
| 14/6/95 | 1.02 | Draft | COPWG | |
| 22/6/95 | 1.03 | Draft for MDC | COP WG | |
| 27/7/95 | 1.04 | Draft following comments by MDC | COP WG | Approved by MDC 7/9/95 |
2 | 8/9/95 | 2.00 | Implementation date agreed by MDC | COP WG | |
3 | 1/5/97 | 2.03 | Amendments for 100kW Take-on | 1998 Programme | Approved by MDC 1/5/97 |
| 1/9/97 | 2.05 | Amended following review by Expert Group and internally. | 1998 Programme (C A Team) | |
| 25/3/98 | 2.06 | Draft for MDC | CoPSRP | |
| 20/4/98 | 2.07 | Post MDC revisions and CoPSRP on 17/4/98 | CoPSRP | |
4 | 1998 Operational Date | 2.05 | Amended following review by Expert Group and internally. | 1998 Programme (CA Team) | |
5 | 1/9/98 | 3.00 | Harmonisation of Codes of Practice | COPSRP | Approved by MDC 4/6/98 |
5 | Code Effective Date | 3.00 | Re-badging of Code of Practice Three for the implementation of the Balancing and Settlement Code | BSCCo | Panel 16/11/00 (Paper 07/003) |
CODE OF PRACTICE FOR THE METERING OF CIRCUITS WITH A RATED CAPACITY NOT EXCEEDING 10MVA FOR SETTLEMENT PURPOSES.
This Code of Practice defines the minimum requirements for the Metering Equipment required for the measurement and recording of electricity transfers at Defined Metering Points where the rated circuit capacity does not exceed 10MVA.
For the purpose of this Code of Practice the rated circuit capacity in MVA shall be determined by the lowest rated primary plant (e.g. transformer rating, line rating, etc) of the circuit. The Metering Equipment provision and accuracy requirements shall anticipate any future up-rating consistent with the installed primary plant. The primary plant maximum continuous ratings shall be used in this assessment.
BSCCo shall retain copies of, inter alia, the Code of Practice together with copies of all documents referred to in them, in accordance with the provisions of the Balancing and Settlement Code (the Code).
This Code of Practice states the practices that shall be employed, and the facilities that shall be provided for the measurement and recording of the quantities required for Settlement purposes on each circuit where the rated capacity does not exceed 10MVA.
It derives force from the Code, and in particular the metering provisions (Section L), to which reference should be made. It should also be read in conjunction with the BSC Procedures.
This Code of Practice does not contain the calibration, testing and commissioning requirements for Metering Equipment used for Settlement purposes. These requirements are detailed in Code of Practice Four - "Code of Practice for Calibration, Testing and Commissioning Requirements for Metering Equipment for Settlement Purposes".
Metering Dispensations from the requirements of this Code of Practice may be sought in accordance with the Code and the BSC Procedure BSCP32.
In the event of an inconsistency between the provisions of this Code of Practice and the Code, the provisions of the Code shall prevail.
The following documents are referred to in the text:-
BS EN 61036 | AC Static Watthour Meters for Active Energy (Classes 1 and 2) |
BS EN 60521 | Specification for Class 0.5, 1 and 2 Single-Phase and Polyphase, Single Rate and Multi-Rate Watt-Hour Meters |
BS EN 61268 | Alternating Current Static Var-Hour Meters for Reactive Energy (Classes 2 and 3) |
BS 5685 Part 4 | Specification for Class 3 Var-Hour Meters |
IEC Standard 44-3 | Instrument Transformers - Combined Transformers |
IEC Standard 185 | Current Transformers |
IEC Standard 186 | Voltage Transformers |
BS EN 61107 | Data Exchange for Meter Reading, Tariff and Load Control. Direct Local Exchange. |
Balancing and Settlement Code | Section X; Annex X-1 and Section L and BSC Procedures |
Code of Practice Four | Code of Practice for Calibration, Testing and Commissioning Requirements for Metering Equipment for Settlement Purposes |
BSC Procedures | See BSC Procedures |
Electricity Act 1989 | Schedule 7 as amended by Schedule 1 to the Competition and Services (Utilities) Act 1992. |
Meter Operator Code of Practice Agreement | Agreement between Meter Operators and Distribution Businesses governing arrangements for safety and technical competence. |
Standard Frequency and Time Signal Emission | International Telecommunication Union - RTF.460(ISBN92-61-05311-4) |
3. DEFINITIONS AND INTERPRETATIONS
Save as otherwise expressly provided herein, words and expressions used in this Code of Practice shall have the meanings attributed to them in the Code and are included for the purpose of clarification.
Note: * indicates definitions in the Code.
Note: † indicates definitions which supplement or complement those in the Code.
Note: ‡ indicates definitions specific to this Code of Practice.
Active Energy means the electrical energy produced, flowing or supplied by an electric circuit during a time interval, being the integral with respect to time of the instantaneous Active Power, measured in units of watt-hours or standard multiples thereof;
Active Power means the product of voltage and the in-phase component of alternating current measured in units of watts and standard multiples thereof, that is:
3.3 Actual Metering Point ‡
Actual Metering Point means the physical location at which electricity is metered.
Apparent Energy means the integral with respect to time of the Apparent Power.
Apparent Power means the product of voltage and current measured in units of volt-amperes and standard multiples thereof, that is:-
CTN means the Electricity Supply Industry (ESI) corporate telephone network.
CVA Customer means any customer, receiving electricity directly from the Transmission System, irrespective of from whom it is supplied.
De-Energised means the temporary removal of the supply at a Defined Metering Point (e.g. the main circuit connections to the Public Distribution System Operators network are still made) such that all or part of the Metering Equipment is considered to be temporarily "inactive" for the purposes of Settlement. e.g. unoccupied premises where the incoming switchgear has been opened or the cut-out fuse(s) removed.
3.9 Defined Metering Point ‡
Defined Metering Point means the physical location at which the overall accuracy requirements as stated in this Code of Practice are to be met. The Defined Metering Points are identified in Appendix A and relate to Boundary Points and System Connection Points.
Demand Period means the period over which Active Energy, Reactive Energy or Apparent Energy are integrated to produce stored energy values. For Settlement purposes, unless the context requires otherwise, each Demand Period shall be of 30 minutes duration, one of which shall finish at 24:00 hours.
Demand Values means, expressed in kW, kvar or kVA, twice the value of kWh, kvarh or kVAh recorded during any Demand Period. The Demand Values are half hour demands and these are identified by the time of the end of the Demand Period.
electricity means Active Energy and Reactive Energy.
Export means, for the purposes of this Code of Practice, an electricity flow as indicated in Figure 1 of Appendix B.
Import means, for the purposes of this Code of Practice, an electricity flow as indicated in Figure 1 of Appendix B.
3.15 Interrogation Unit ‡
Interrogation Unit means a Hand Held Unit "HHU" (also known as Local Interrogation Unit LIU") or portable computer which can enter Metering Equipment parameters and extract information from the Metering Equipment and store this for later retrieval.
Maximum Demand expressed in kW or kVA means twice the greatest number of kWh or kVAh recorded during any Demand Period.
Meter means a device for measuring Active Energy and/or Reactive Energy.
3.18 Metering Equipment *
Metering Equipment means Meters, measurement transformers (voltage, current or combination units), metering protection equipment including alarms, circuitry, associated Communications Equipment and Outstation and wiring.
Meter Register means a device, normally associated with a Meter, from which it is possible to obtain a reading of the amount of Active Energy, or the amount of Reactive Energy that has been supplied by a circuit.
Metering System means particular commissioned Metering Equipment, as defined in Section X; Annex X-1 of the Balancing and Settlement Code.
Outstation means equipment which receives and stores data from a Meter(s) for the purpose, inter-alia, of transfer of that metering data to the Central Data Collector Agent (CDCA) or Data Collector as the case may be, and which may perform some processing before such transfer and may be in one or more separate units or may be integral with the Meter.
Outstation System means one or more Outstations linked to a single communication line.
Password means a string of characters of length no less than six characters and no more than twelve characters, where each character is a case insensitive alpha character (A to Z) or a digit (0 to 9) or the underscore character (_). Passwords must have a minimum of 2,000,000,000 combinations, for example six characters if composed of any alphanumeric characters or eight characters if composed only of hexadecimal characters (0 to F).
PSTN means the public switched telephone network.
3.25 Rated Measuring Current ‡
Rated Measuring Current means the rated primary current of the current transformers in primary plant used for the purposes of measurement.
Reactive Energy means the integral with respect to time of the Reactive Power.
Reactive Power means the product of voltage and current and the sine of the phase angle between them, measured in units of voltamperes reactive and standard multiples thereof.
Registrant means in relation to a Metering System, the person for the time being registered in CMRS or (as the case may be) SMRS in respect of that Metering System pursuant to Section K of the Balancing and Settlement Code.
3.29 Settlement Instation ‡
Settlement Instation means a computer based system which collects or receives data on a routine basis from selected Outstation by the Central Data Collector or (as the case may be) a relevant Data Collector.
means a person to whom electrical power is provided, whether or not that person is the provider of that electrical power; and where that electrical power is measured by a SVA Metering System.
UTC means Co-ordinated Universal Time which bears the same meaning as in the document Standard Frequency and Time Signal Emission, International Telecommunication Union - RTF.460(ISBN92-61-05311-4) (colloquially referred to as Rugby Time).
4.1 Measured Quantities and Demand Values
4.1.1 Measured Quantities
For each separate circuit the following energy measurements are required for Settlement purposes:-
For each Demand Period for each circuit the following Demand Values shall be provided:-
* Import and/or Export metering need only be installed where a Party requires this measurement to meet system or plant conditions.
Where Import and Export metering is installed gross Import and gross Export Active Energy shall be recorded separately for Settlements.
For multiple circuit connections between Parties the configuration of the Metering Equipment shall be agreed in advance with the Panel.
4.2 Accuracy Requirements
The overall accuracy of the energy measurements at or referred to the Defined Metering Point shall at all times be within the limits of error as shown:-
CONDITION | LIMIT OF ERRORS AT STATED SYSTEM POWER FACTOR |
Current expressed as a percentage of Rated Measuring Current | Power Factor | Limits of Error |
120% to 10% inclusive Below 10% to 5% 120% to 10% inclusive | 1 1 0.5 lag and 0.8 lead | ± 1.5% ± 2.0% ± 2.5% |
CONDITION | LIMIT OF ERRORS AT STATED SYSTEM POWER FACTOR |
Current expressed as a percentage of Rated Measuring Current | Power Factor | Limits of Error |
120% to 10% inclusive 120% to 20% inclusive | Zero 0.866 lag and 0.866 lead | ± 4.0% ± 5.0% |
These limits of error for both (i) and (ii) above shall apply at the Reference Conditions defined in the appropriate Meter specification.
Evidence to verify that these overall accuracy requirements are met shall be available for inspection by either the Panel or the Technical Assurance Agent.
4.2.2 Compensation for Measurement Transformer Error
To achieve the overall accuracy requirements it may be necessary to compensate Meters for the errors of the measurement transformers and the associated leads to the Meters. Values of the compensation shall be recorded and evidence to justify the compensation criteria, including wherever possible test certificates, shall be available for inspection by either the Panel or the Technical Assurance Agent.
4.2.3 Compensation for Power Transformer and Line Losses
Where the Actual Metering Point and the Defined Metering Point do not coincide a Metering Dispensation shall be applied for and, where necessary, compensation for power transformer and/or line losses shall be provided to meet the overall accuracy at the Defined Metering Point.
The compensation may be achieved in the Metering Equipment and in this event the applied values shall be recorded. Supporting evidence to justify the compensation criteria shall be available for inspection by either the Panel or the Technical Assurance Agent.
Alternatively, the compensation may be applied in the software of the relevant data aggregation system used for Settlement purposes. In this event the factors shall be passed to the appropriate agency and evidence to justify the compensation criteria shall be made available for inspection by either the Panel or the Technical Assurance Agent.
5. METERING EQUIPMENT CRITERIA
Although for clarity this Code of Practice identifies separate items of equipment, nothing in it prevents such items being combined to perform the same task provided the requirements of this Code of Practice are met.
Metering Equipment other than outdoor measurement transformers, shall be accommodated in a clean and dry environment.
For each circuit, other than one which is permanently disconnected, the voltage supply to any Meters, Displays and Outstations shall be connected such that it is normally energised to facilitate reading of the Meter Register(s) and Local and Remote Interrogation of the Outstation. (see Appendix E).
Where an Outstation is storing data for more than one circuit and the Outstation power supply is from these circuits then a voltage selection relay scheme using each circuit involved shall be provided.
5.1 Measurement Transformers
The terms "current transformer" and "voltage transformer" used below in 5.1.1 and 5.1.2 do not preclude the use of other measuring techniques with a performance equal to that specified for such measurement transformers.
For each circuit current transformers (CT) and voltage transformers (VT) shall meet the requirements set out in clauses 5.1.1 and 5.1.2.
Additionally, where a combined unit measurement transformer (VT & CT) is provided the 'Tests for Accuracy' as covered in clause 8 of IEC Standard 44-3 covering mutual influence effects shall be met.
5.1.1 Current Transformers
One set of current transformers in accordance with IEC Standard 185 and with a minimum standard of accuracy to Class 0.5 shall be provided per circuit. Preferably the current transformers shall be dedicated for Settlement purposes, but the CTs may be used for other purposes provided the overall accuracy requirements in clause 4.2.1 are met and evidence of the value of the additional burden is available for inspection by either the Panel or the Technical Assurance Agent.
The additional burden shall not be modified without prior notification to the Panel, and evidence of the value of the modified additional burden shall be available for inspection by either the Panel or the Technical Assurance Agent.
CT test certificates showing errors at the overall working burden or at burdens which enable the working burden errors to be calculated shall be available for inspection by either the Panel or the Technical Assurance Agent.
The total burden on each current transformer shall not exceed the rated burden of such CT.
5.1.2 Voltage Transformers
A single voltage transformer secondary winding in accordance with IEC Standard 186 and with a minimum standard of accuracy to Class 1 shall be provided for the main and check metering of a circuit. The voltage transformer secondary winding may be used for other purposes provided the overall accuracy requirements in clause 4.2.1 are met and evidence of the value of the additional burden is available for inspection by either the Panel or the Technical Assurance Agent.
The additional burden shall not be modified without prior notification to the Panel, and evidence of the value of the modified additional burden shall be available for inspection by either the Panel or the Technical Assurance Agent.
A VT test certificate(s) showing errors at the overall working burden(s) or at burdens which enable the working burden errors to be calculated shall be available for inspection by either the Panel or the Technical Assurance Agent.
The total burden on each secondary winding of a VT shall not exceed the rated burden of such secondary winding.
The VT supplies shall be fused as close as practicable to the VT, with a set of isolating links, suitably identified, provided locally to the Metering Equipment.
5.1.3 Measurement Transformers Installed on Existing Circuits
Where circuits, other than those newly installed, are to be metered to this Code of Practice and where the installed measurement transformers do not comply with the class accuracies specified in clauses 5.1.1 & 5.1.2, then such measurement transformers may be used providing the following requirements and those in clause 4.2.1 are met:-
5.2 Fusing and Testing Facilities
Testing facilities shall be provided close by the Meters of each circuit, which enables such Meters to be routinely tested and/or changed safely with the circuit energised. (see Appendix C)
Separate fusing shall be provided locally for:-
Local fusing shall discriminate with the source fusing.
A typical arrangement is illustrated in Appendix C.
Where Current Transformers are used on low voltage installations, the voltage supply to the Metering Equipment shall be fused as close as practicable to the point of that supply with a set of isolating links, suitably identified, provided locally to the Metering Equipment. If that point of supply is close to the Metering Equipment, then the isolating links may be omitted.
The Meters may be either static or induction disc types.
For each circuit main and check Active Energy Meters shall be supplied. These Meters shall meet the requirements of either BS EN 61036 Class 1 or BS EN 60521 Class 1.
Active Energy Meters provided for the metering of supplies to customers shall be in accordance with Schedule 7 of the Electricity Act 1989.
For each circuit, only main Reactive Energy Meter(s) need be supplied. The Reactive Energy Meters shall meet the requirements of either BS EN 61268 Class 3 or BS 5685 Part 4.
Active Energy Meters shall be configured such that the number of measuring elements is equal to or one less than the number of primary system conductors. These include the neutral conductor, and/or the earth conductor where system configurations enable the flow of zero sequence energy.
All Meters supplied via measurement transformers shall be set to the actual primary and secondary ratings of the measurement transformers and the ratios displayed as follows:-
All Meters shall include a non-volatile Meter Register of cumulative energy for each measured quantity (see 4.1.1). The Meter Register(s) shall not roll-over more than once within the normal Meter reading cycle.
Meters which provide data to separate Outstations shall for this purpose provide an output per measured quantity (see 4.1.1).
For Meters using electronic displays due account shall be taken of the obligations of the Central Data Collector Agent (CDCA) or other Data Collectors to obtain Meter readings, even when the circuit is de-energised.
All Meters shall be labelled or otherwise be readily identifiable with respect to their associated circuit(s), and in accordance with Appendix B.
5.4 Displays and Facilities for Registrant or Supplier Information
The Metering Equipment shall display the following primary information (not necessarily simultaneously):-
The Metering Equipment shall be capable of enabling the display of the following information, as specified by the Registrant:-
MD shall be resettable at midnight of the last day of a charging period and for part chargeable period demands. If a manual reset button is provided then this shall be sealable.
The Metering Equipment shall be capable of providing the following information locally to the Customer or Registrant for Stage 1 Metering Equipment; or to the Customer or Supplier for Stage 2 Metering Equipment, configured to their requirements taking account of the measured quantities (see clause 4.1.1):-
An Outstation System shall be provided which transfers data to and receives data from a Settlement Instation.
Where a single separate Outstation is provided for storing data for more than one circuit, the Maximum Aggregated Capacity shall be 100 MVA.
Where more than one separate Outstation is provided, the main and check Meter data shall be stored in different Outstations.
The Outstation data shall be to a format and protocol approved by the Panel.
The Outstation shall facilitate the metering data to be read by instations other than the Settlement Instation provided the requirements of clause 7 of this Code of Practice are satisfied.
For the purpose of transferring stored metering data from the Outstation to the Settlement Instation, a unique Outstation identification code shall be provided.
Normally, metering data will be collected by the Settlement Instations by a daily interrogation, but repeat collections of metering data shall be possible throughout the Outstation data storage period.
If not integral, the Outstation System supply shall either be from a secure supply or from a measurement VT, with separate fusing for each Outstation.
Where a separate modem associated with the Outstation System is used, then it shall be provided with a separately fused supply either from a secure supply or from a measurement VT (see clause 5). Alternatively, line or battery powered modem types may be used.
Data storage facilities for metering data shall be provided as follows:-
a) the completion of each Demand Period shall be at a time which is within ± 20 seconds of UTC; and
b) the duration of each Demand Period shall be within ± 0.1%, except where time synchronisation has occurred in a Demand Period.
5.5.3 Monitoring Facilities
Monitoring facilities shall be provided for each of the following conditions and shall be reported, as separate alarm indications, tagged to the relevant Demand Period(s), via on-line communications and the local Interrogation Unit:-
In addition to (ii), detected errors in Metering Equipment functionality should be recorded as an event alarm with date and time.
Any alarm indications shall not be cancelled or deleted by the interrogation process and shall be retained with the data until overwritten. The alarm shall reset automatically when the abnormal condition has been cleared.
Outstation(s) shall provide both local and remote interrogation facilities, from separate ports.
To prevent unauthorised access to the data in the Metering Equipment a security scheme, as defined below and in Appendix D, and shall be incorporated for both local and remote access. Separate security levels shall be provided for the following activities:-
Read only of the following metering data, which shall be transferable on request during the interrogation process:-
Outstation ID;
Demand Values as defined in clause 4.1.2 for main and check Meters;
cumulative measured quantities as defined in clause 4.1.1 for main and check Meters;
Maximum Demand (MD) for kW or kVA per programmable charging period i.e. monthly, statistical review period;
multi-rate cumulative Active Energy as specified by Registrant;
the measurement transformer ratios, where appropriate (see clause 5.3);
the measurement transformer error correction factor and/or system loss factor, where this is a constant factor applied to the entire dynamic range of the Meter and the Meter is combined with the display and/or Outstation;
alarm indications; and
Outstation time and date.
(ii) Level 2 - Password for:-
corrections to the time and/or date; and
resetting of the MD.
(iii) Level 3 - Password for:-
the Displays and Facilities as defined in clause 5.4;
the measurement transformer ratios, as appropriate (see clause 5.3);
the measurement transformer error correction and/or system loss factor where this is a constant factor applied to the entire dynamic range of the Meter and the Meter is combined with the display and/or Outstation; and
the passwords for levels 1, 2 and 3.
In addition, it shall be possible to read additional information within the Metering Equipment to enable the programmed information to be confirmed.
(iv) Level 4 - Password or removal of Metering Equipment cover(s) necessitating the breaking of a seal for:-
calibration of the Metering Equipment;
setting the measurement transformer ratios, as appropriate;
programming the measurement transformer error correction factor and/or system loss factor where this is other than a single factor; and
programming the level 3 password and the level 4 password, if appropriate.
In addition to the functions specified for each level it shall be feasible to undertake the functions at the preceding level(s). e.g. at level 3 it shall also be possible to carry out the functions specified at levels 1 and 2. This need not apply at level 4 when access is obtained via removing the cover.
Different Passwords shall be utilised for each level, which shall only be circulated in accordance with the relevant BSC Procedure.
5.6.1 Local Interrogation
An interrogation port shall be provided for each Outstation which preferably shall be an opto port to BS EN 61107, and with a serial protocol such as BS EN 61107.
5.6.2 Remote Interrogation
Remote interrogation facilities shall be provided with error checking of the communications between the Outstation System and the Settlement Instation.
It shall not be possible to disconnect the remote communications connection to/from the Outstation without the breaking of an appropriate seal (see clause 5.7).
Interrogation of an Outstation shall be possible using one of the following media:
In addition any further media may be used as approved by the Panel.
The actual media employed shall be in accordance with the requirements of the CDCA for CVA Metering Systems and the Supplier for SVA Metering Systems..
The data shall be to a format and protocol approved by the Panel.
All SVA Metering Equipment shall be sealed in accordance with Appendix 8 and 9 of the Meter Operator Code of Practice Agreement.
All CVA Metering Equipment shall be sealed using Settlement Seals and in accordance with BSC Procedure BSCP06.
The operator may interrogate the Metering Equipment using an Interrogation Unit (IU). The IU may be used for programming, commissioning, maintenance/fault finding and when necessary the retrieval of stored metering data. The data retrieved by the IU shall be compatible with the Settlement Instation.
The IU shall have a built-in security system, such as a password, so that the IU becomes inoperative and non-interrogatable if it is lost, stolen, etc. The password can be applied at power-on of the device and/or on entry to the IU software application.
Additional features may be incorporated within or associated with the Metering Equipment provided but these shall not interfere with or endanger the operation of the Settlement process.
Access to metering data shall be in accordance with the provisions of the Code and the BSC Procedures referred to therein. Such access must not interfere with or endanger the security of the data or the collection process for Settlement purposes.
Access to stored metering data in Outstations shall also be the right of the Registrant and any party who has the permission of the Registrant.
APPENDIX A DEFINED METERING POINTS
For transfers of electricity between the following parties the Defined Metering Point (DMP) shall be at one of the following locations:-
1. For transfers between the Transmission Company and a single Public Distribution System Operator where no other Party(s) are connected to the busbar, the DMP shall be at the lower voltage side of the supergrid connected transformer.
2. For transfers between the Transmission Company and a single Public Distribution System Operator where other Party(s) are connected to the busbar, the DMP shall be at the circuit connections to that Public Distribution System Operator.
3. For transfers between the Transmission Company and more than one Public Distribution System Operator connected to the same busbar, the DMP shall be at the circuit connections of each Public Distribution System Operator to such busbar.
4. For transfers between Public Distribution System Operators not including a connection to the Transmission System, the DMP shall be at the point of connection of the two Public Distribution System Operators.
5. For transfers between the Transmission Company and Generating Plant, the DMP shall be at the high voltage side of the generator transformers and station transformer(s).
6. For transfers between Public Distribution System Operators and Generating Plant, the DMP shall be at the point(s) of connection of the generating station to the Public Distribution System Operator.
7. For transfers between the Distribution System of a Public Distribution System Operator and a Customer, the DMP shall be at the point of connection to the Distribution System of the Public Distribution System Operator.
8. For transfers between the Transmission Company and a Customer, the DMP shall be at the point of connection to the Transmission Company.
9. For transfers between the Transmission Company and an Interconnector User the DMP shall be as follows:-
(i) For the Scottish links, the busbar side of the busbar disconnectors at:-
(a) Harker 400 kV Substation
(b) Harker 275 kV Substation
(c) Harker 132 kV Substation
(d) Stella 275 kV Substation
(e) Stella 400 kV Substation
(ii) For the EdF link the busbar side of the busbar disconnectors at the Sellindge 400 kV Substation.
APPENDIX B LABELLING OF METERS FOR IMPORT AND EXPORT
A standard method of labelling Meters, test blocks, etc is necessary and based on the definitions for Import and Export the required labelling shall be as follows.
Meters or Meter Registers shall be labelled "Import" or "Export" according to Figure 1.
Within the context of this code the relationship between Active Energy and Reactive Energy can best be established by means of the power factor. The following table gives the relationship:-
Flow of Active Energy | Power Factor | Flow of Reactive Energy |
Import Import Import Export Export Export | Lagging Leading Unity Lagging Leading Unity | Import Export Zero Export Import Zero |
Meters or Meter Registers for registering Import Reactive Energy should be labelled "Import" and those for registering Export Reactive Energy should be labelled "Export".
APPENDIX C TYPICAL TESTING FACILITIES AND FUSING ARRANGEMENTS
The Passwords specified in clause 5.6 shall be subject to the following additional requirements:-
1. The communications protocol employed shall ensure that the Password offered determines the level of access to the data within the Metering Equipment.
2. A counter logging the number of illegal attempts (i.e. Password comparison failures) to access Metering Equipment via the local and remote ports shall be incorporated into the log-on process. This counter shall reset to zero at every hour change (i.e. 0100, 0200, etc.).
3. If the counter reaches 7, then access is prohibited at all levels until the counter resets at the next hour change.
APPENDIX E OPTIONS FOR ENSURING METERS AND DISPLAYS CAN BE READ AND REMOTELY INTERROGATED
This Appendix sets out the options for complying with the requirements set out in clause 5 for certain types of supply where the voltage supply to the Metering Equipment would not normally be maintained for significant periods. e.g. those used for standby and those where the customer's restricted period load is controlled by the main incoming switchgear.
1. Connection of Metering Equipment to the Live Side of the Supply
For new supplies the most practical solution would be to arrange for the Metering Equipment to be connected to the incoming side of the main switchgear so that it is normally energised even when the switchgear is open.
2. Install Separate Meters and Displays/Outstations
Installation of separate Meters and Displays/Outstations would enable the latter to be connected to a normally energised supply. This would facilitate Local and Remote Interrogation and reading on a routine basis. The Meters would need to be provided with a permanent Meter Register to meet the requirements of clause 5.3.
3. Combined Meters, Displays and Outstations with Separate Auxiliary Supply Facilities
Integrated products could be utilised which have separate input terminals to energise the data storage and display functions which could be connected to a normally energised supply, whilst the voltage supply to the Meter is from the relevant circuit.
4. Combined Meters, Displays and Outstations Supplied via a Voltage Relay Selection Scheme
With this option the integrated equipment would be connected to an appropriate single phase voltage supply via a voltage relay selection scheme such that whilst this circuit was de-energised it would receive it's voltage supply only, from the adjacent circuit. However, when this circuit was energised it would be fed with both voltage and current from the measured circuit. This arrangement is shown in Figure 2 overleaf and is only suitable for use with CT operated Metering Systems.
APPENDIX F GENERIC DISPENSATIONS
The issue of this Code of Practice does not revoke the following Dispensations and they are valid against this issue of the Code of Practice:
DISPENSATION NUMBER | DESCRIPTION OF DISPENSATION (FORM D4) | DISPENSATION FROM ISSUE |
157 | Agreed that Code of Practice G Metering Equipment installed prior to 1st April 1993, but not Registered with the SSA until some later date, could remain on circuit provided that there was no material change to that Metering Equipment. | Issue 1 |