Balancing and Settlement Code
BSC PROCEDURE
Metering Protocol Approval and Compliance Testing
BSCP601
Date:
|
Intellectual Property Rights, Copyright and Disclaimer The copyright and other intellectual property rights in this document are vested in Elexon or appear with the consent of the copyright owner. These materials are made available for you for the purposes of your participation in the electricity industry. If you have an interest in the electricity industry, you may view, download, copy, distribute, modify, transmit, publish, sell or create derivative works (in whatever format) from this document or in other cases use for personal academic or other non-commercial purposes. All copyright and other proprietary notices contained in the document must be retained on any copy you make. All other rights of the copyright owner not expressly dealt with above are reserved. No representation, warranty or guarantee is made that the information in this document is accurate or complete. While care is taken in the collection and provision of this information, Elexon Limited shall not be liable for any errors, omissions, misstatements or mistakes in any information or damages resulting from the use of this information or action taken in reliance on it. |
Version | Date | Description of Changes | CRs Included | Mods Panel Ref |
0.1 | 20/01/01 | Re-Badged for NETA | NCR313 |
|
1.0 | 27/03/01 | Approved by Panel 22/02/01 | P/13/008 |
|
2.0 | 05/08/02 | Changes to incorporate CP764 | CP764 | SVG/18/226 ISG/18/187 |
3.0 | 01/08/03 | Updated for Modification P62 | P62 | SVG/29/390 |
4.0 | 29/06/04 | Updated for CP983 | CP983 | SVG/39/003 ISG/40/002 |
5.0 | 23/02/05 | SVA February 2005 Release and BETTA 6.3 | P159, CP993, CP1091 and BETTA 6.3 and CP1067 | SVG/47/004 |
6.0 | 03/11/05 | SVA November 2005 Release | CP1099 and CP1139 | SVG/56/004 |
7.0 | 28/06/07 | June 2007 Release | CP1174 P197 | ISG/72/04 SVG/72/04 |
8.0 | 23/08/07 | August 2007 Release | P197 | P/115/04 |
9.0 | 28/02/08 | February 2008 Release Update of protocol and incorporation of appendices | CP1202, CP1203
CP1166 v.3.0 | ISG79/02 SVG79/02 SVG80/03 |
10.0 | 06/11/08 | November 2008 Release | CP1232 | ISG88/01 SVG88/02 |
11.0 | 26/02/09 | February 2009 Release | CP1261 | ISG93/02 SVG93/02 |
12.0 | 25/06/09 | June 2009 Release | CP1264 | ISG94/01 SVG94/02 |
|
|
| CP1273 | ISG97/01 SVG97/01 |
13.0 | 05/11/09 | November 2009 Release | CP1275 v2.0 | ISG100/01 SVG99/02 |
14.0 | 25/02/10 | February 2010 Release | CP1296 | ISG102/01 SVG102/01 |
|
|
| CP1297 | ISG102/01 SVG102/01 |
15.0 | 24/06/10 | June 2010 Release | CP1318 | ISG107/01 SVG107/01 |
16.0 | 04/11/10 | November 10 Release | CP1315 | SVG109/01 |
17.0 | 23/02/12 | February 2012 Release | P266 | ISG130/08 SVG130/01 |
18.0 | 25/02/16 | February 2016 Release | CP1450 | SVG178/04 |
19.0 | 23/02/17 | February 2017 Release | CP1466 | P261/09 |
|
|
| CP1472 | SVG191/05 ISG190/03 |
20.0 | 27/06/19 | June 2019 Release | CP1508 | SVG213/04 |
|
|
| CP1513 | SVG216/04 ISG214/01 |
21.0 | 01/09/21 | September 2021 Release | P420 | P316/05 |
22.0 | 24/02/22 | February 2022 Standard Release | CP1551 | SVG250/03 ISG248/06 |
23.0 | 30/06/22 | June 2022 Standard Release | P375, P433, CP1527 | P309/06, P322/05, SVG233/02, ISG231/01 |
each or any Metering Equipment and Asset Metering Equipment (including in relation to any safety matters) in respect of any item of Metering Equipment and Asset Metering Equipment which is not tested whether or not such item is of the same type, model or version as an item which is tested;
the processing of any application for certification or for Compliance Approval, Protocol Approval or any other approval (“approval”) in relation to Metering Equipment and Asset Metering Equipment;
the grant, failure or refusal to grant any such certification or approval; and/or
any testing, method of testing or analysis of the results of testing of Metering Equipment and Asset Metering Equipment or any act, error, failure or omission in relation to such testing, method of testing or analysis.
The Applicant is responsible for submitting applications for the testing of Metering Equipment, and Asset Metering Equipment arranging for testing to be conducted and any costs associated with testing.
The Applicant is responsible for submitting notification of any amendment to Metering Equipment and Asset Metering Equipment, or data collection system for an existing Approval.
The Compliance and Protocol Testing Agents are responsible for receiving Metering Equipment, and Asset Metering Equipment undertaking the testing of that Metering Equipment or Asset Metering Equipment and providing a written report to BSCCo of the findings of such tests.
The Meter, Asset Meter, or Outstation, manufacturer is responsible for confirming its intention to ensure that BSC Parties have access to the relevant Settlement Outstation Protocols and Asset Meter Protocols.
The Meter, Asset Meter, or Outstation, manufacturer is responsible for confirming its intention to ensure that Meter Operator Agents have access to the Meter, Asset Meter or Outstation manufacturer's Configuration Software.
BSCCo is responsible for the selection of suitably accredited Compliance and Protocol Testing Agents, the scheduling of tests and the determination of successful tests together with the issue of certificates.
Half Hour Data Collector Agents are required to ensure that approval is obtained for each type of Metering Equipment and Asset Metering Equipment that it collects data for Settlement purposes.
The Asset Metering Virtual Lead Party (where they are the Asset Meter manufacturer or the Applicant) is responsible for confirming its intention to ensure that BSC Parties have access to the relevant Asset Meter Protocols.
Asset Metering Half Hourly Data Collectors are required to ensure that approval is obtained for each type of Asset Metering Equipment that it collects data from for Settlement purposes.
AMHHDC | Asset Metering Half Hourly Data Collector (Qualified) |
AMVLP | Asset Metering Virtual Lead Party |
BSCCo | Balancing and Settlement Code Company |
CDCA | Central Data Collection Agent |
CoP | Code of Practice |
CT | Current Transformer |
CTA | Compliance Testing Agent |
HHDC | Half Hourly Data Collector (Qualified) |
MD | Maximum Demand |
ME | Metering Equipment |
MID | Measuring Instruments Directive |
MIR | Measuring Instruments Regulations |
MOA | Meter Operator Agent |
SMETS | Smart Metering Equipment Technical Specifications |
SMRS | Supplier Meter Registration Service |
SVA | Supplier Volume Allocation |
VLP | Virtual Lead Party |
WD | Working Day |
Applicant | Person applying for Compliance and/or Protocol approval |
Asset Meter | means a device for measuring Active Power and/or Active Energy |
Asset Metering Equipment | has, for the purposes of this BSCP601, the meaning ascribed to that term in the Balancing and Settlement Code, but excluding voltage and current measurement transformers |
BSCCo | The Balancing and Settlement Code Company |
Compliance Testing | means the testing of Metering Equipment and Asset Metering Equipment in accordance with this BSCP601 to determine whether it conforms with the relevant Code of Practice to obtain approval from the Panel. |
Compliance Testing Agent | The agent responsible for the testing of Metering Equipment and Asset Metering Equipment, accredited against an appropriate (as determined by BSCCo) body such as the UK Accreditation Service (UKAS). |
Code of Practice One | means the latest version§ of Code of Practice One - CODE OF PRACTICE FOR THE METERING OF CIRCUITS WITH A RATED CAPACITY EXCEEDING 100MVA FOR SETTLEMENT. |
Code of Practice Two | means the latest version§ of Code of Practice Two - CODE OF PRACTICE FOR THE METERING OF CIRCUITS WITH A RATED CAPACITY NOT EXCEEDING 100MVA FOR SETTLEMENT PURPOSES. |
Code of Practice Three | means the latest version§ of Code of Practice Three - CODE OF PRACTICE FOR THE METERING OF CIRCUITS WITH A RATED CAPACITY NOT EXCEEDING 10MVA FOR SETTLEMENT PURPOSES. |
Code of Practice Five | means the latest version§ of Code of Practice Five - CODE OF PRACTICE FOR THE METERING OF ENERGY TRANSFERS WITH A MAXIMUM DEMAND OF UP TO (AND INCLUDING) 1MW FOR SETTLEMENT PURPOSES. |
Code of Practice Six | means the latest version§ of Code of Practice Six - CODE OF PRACTICE FOR THE METERING OF ENERGY IMPORTS VIA LOW VOLTAGE CIRCUITS FUSED AT 100 AMPS OR LESS PER PHASE FOR SETTLEMENT PURPOSES. |
Code of Practice Ten | means the latest version§ of Code of Practice Ten - CODE OF PRACTICE FOR METERING OF ENERGY VIA LOW VOLTAGE CIRCUITS FOR SETTLEMENT PURPOSES. |
Code of Practice Eleven | means the latest version§ of Code of Practice Eleven - Code of Practice for the Metering of Balancing Services Assets for Settlement Purposes |
Embedded Metering Device | Embedded Metering Device means an Asset Meter, measuring Active Power and/or Active Energy that is embedded within equipment used for other purposes (e.g. an EV charging unit or a small-scale domestic battery storage unit) and is not a dedicated meter, i.e. one whose primary purpose is to measure Active Power and/or Active Energy. |
Instation | means a computer based system which sends data to, or receives data from Outstation Systems or Asset Metering Systems on a routine basis. |
Interrogation Unit | means a Hand Held Unit “HHU” (also known as Local Interrogation Unit “LIU”) or portable computer which can program Metering Equipment or Asset Metering Equipment parameters and extract information from the Metering Equipment or Asset Metering Equipment and store this for later retrieval. |
Metering Equipment | has, for the purposes of this BSCP601, the meaning ascribed to that term in the Balancing and Settlement Code, but excluding voltage and current measurement transformers |
person | includes any individual, company, corporation, firm, partnership, joint venture, association, committee, organisation or trust (in each case, whether or not having separate legal personality). |
Protocol | means a set of rules or procedures for transmitting data between a Meter, Asset Meter or Outstation and a data collection system used for collecting data from Settlement Metering Systems to exchange information. |
Protocol Approval | means a process by which the Protocol implemented in a Qualified HHDC’s (and, where applicable, Qualified AMHHDC’s) data collection system is tested against a known version of the Protocol (e.g. the Meter, Asset Meter or Outstation manufacturer’s software) to confirm it has been correctly implemented in order to collect metered data from a Meter, Asset Meter or Outstation for Settlement purposes. The BSC Panel approves the protocol for use in Settlement in accordance with this BSCP601. |
Settlement | has the meaning ascribed to that term in the Balancing and Settlement Code. |
Smart Metering Equipment Technical Specifications | As defined in Section X Annex X-1 of the Balancing and Settlement Code. |
Test Laboratory | means the testing body so agreed with BSCCo to perform Compliance Testing to this BSCP601 |
Type Approval | refers to the approval of a given meter types’ pattern or construction under Schedule 7 of the Electricity Act 1989 and supporting regulations, where used for billing. Meters were formally approved against the EU Measuring Instruments Directive (MID). From January 2021 new meter designs are approved under the Measuring Instruments Regulations (MIR). Meters outside the scope of the MID/MIR must be approved by the Office for Product Safety & Standards under national legislation. |
UTC | means Co-ordinated Universal Time based on atomic clocks as distinct from Greenwich Mean Time (GMT). |
REF | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
2.1.1 | At any time. | Submit Application for Protocol Approval and any supporti1ng documentation. | Applicant | BSCCo | Notification of Metering Equipment or Asset Metering Equipment and HHDC Agent or AMHHDC Agent to be approved. Form F601/ 03 | Fax, Post. |
2.1.2 | Within 2 WD of receipt of 2.1.1 above. | Validate application. | BSCCo |
|
| Internal Process. |
2.1.3 | Within 5 WD of 2.1.1 above. | Notify Applicant of acceptance or rejection of Application. If accepted, provide copy of testing schedule and notification of Application reference number. | BSCCo | Applicant | Protocol Approval test schedule and Application reference number. | E-mail, Fax, Post. |
2.1.4 | Within 10 WD of receipt of 2.1.3 above. | Agree any re-drafting of test schedule. | Applicant | BSCCo | Re-drafted schedule (if required). | E-mail, Fax, Post. |
2.1.5 | Within 5 WD of 2.1.4 above. | Arrange with nominated HHDC or AMHHDC to conduct testing and liaise with BSCCo to witness testing. | Applicant | HHDC or AMHHDC BSCCo |
| As agreed. |
2.1.6 | Within 10 WD of 2.1.5 above. | Submit 2 Outstations and any software for testing to the nominated HHDC or AMHHDC. | Applicant | HHDC or AMHHDC |
| As agreed. |
2.1.7 | Within 10 WD of 2.1.5 above. | Undertake testing of Protocol in accordance with agreed Test Schedule. | HHDC or AMHHDC | BSCCo |
|
|
|
| Prepare and submit report including test results. | HHDC or AMHHDC | BSCCo | Test Report2. | E-mail, Fax, Post. |
2.1.8 | Within 5 WD of 2.1.7 above. | Notify Applicant of test result determination. If testing successful, update Protocol Approval list (see section 3.2), notify Parties and Party Agents and issue certificate to Applicant. | BSCCo | Applicant Parties Party Agents | Form F601/02 Approval details. Approval details. | E-mail, Fax, Post. E-mail, Fax, Post, BSC Website. |
2.1.9 | Next opportune meeting. | Notify Panel of certificates issued and updates to Protocol Approval list (see section 3.2). | BSCCo | Panel | Panel report. | Panel Paper. |
REF | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
2.2.1 | At any time | Submit Application for Compliance Testing. | Applicant | BSCCo | Form F601/03 | E-mail, Fax, Post. |
2.2.2 | Within 2 WD of receipt of 2.2.1 above. | Validate Application. | BSCCo |
|
| Internal Process. |
2.2.3 | Within 5 WD of 2.2.1 above. | Notify Applicant of acceptance or rejection of Application. If accepted, provide copy of testing schedule and notification of Application reference number. | BSCCo | Applicant | Compliance test schedule and Application reference number. | E-mail, Fax, Post. |
2.2.4 | Within 10 WD of receipt of 2.2.3 above. | Agree any re-drafting to test schedule. | Applicant | BSCCo | Re-drafted schedule (if required). | E-mail, Fax, Post. |
2.2.5 | Within 10 WD of 2.2.4 above. | Agree Compliance Testing Agent with BSCCo. Liaise with CTA to undertake Compliance testing. | Applicant | BSCCo CTA | Notification of CTA. | E-mail, Fax, Post. |
2.2.6 | Within 3 Months of 2.2.5 above. | Undertake testing and submit report to BSCCo. | CTA | BSCCo | Compliance test report3. | E-mail, Fax, Post. |
2.2.7 | Within 5 WD of 2.2.6 above. | Notify Applicant of test result determination. If testing successful, update Compliance Approval list (see section 3.2). Notify Parties and Party Agents of new approval and issue certificate of Compliance to Applicant. | BSCCo | Applicant Parties Party Agents | Form F601/01. Approval details. Approval details. | E-mail, Fax, Post.
E-mail, Fax, Post, BSC Website. |
2.2.8 | Next opportune meeting. | Notify Panel of certificates issued and updates to Compliance Approval list (see section 3.2). | BSCCo | Panel | Panel report. | Panel Paper. |
REF | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
2.3.1 | At any time | Submit notification of amendment to Metering Equipment, Asset Metering Equipment or Data Retrieval system for an existing Approval and agree impact of change. | Applicant | BSCCo | Details and impact of change. | E-mail, Fax, Post. |
2.3.2 | Within 30 WD of 2.3.1 above. | Consult with affected Parties (if required) and determine whether Approval for the amendment to Metering Equipment, Asset Metering Equipment or Data Retrieval system can be given. | BSCCo | Affected Parties | Details and impact of change. | As agreed. |
2.3.3 | Within 5 WD of 2.3.3 above. | Notify Applicant of determination and if new Approval given, update Approval list (see section 3.2). | BSCCo | Applicant Parties Party Agents | BSCCo determination. Approval details. Approval details | E-mail, Fax, Post, BSC Website. |
2.3.4 | Next opportune meeting | Notify Panel of any updates to Approval list (see section 3.2). | BSCCo | Panel | Panel Report | Internal Process |
REF | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
2.4.1 | At any time | Submit notification of approval issue. | Any party | BSCCo | Details and impact of issue. | E-mail, Fax, Post. |
2.4.2 | Within 30 WD of 2.4.1 above | Clarify and substantiate issue. Consult with and obtain additional information from affected parties (if necessary). | BSCCo | Affected parties | Additional Information. | As agreed. |
2.4.3 | Within 10 WD of 2.4.2 above | Agree findings with notifying party. | BSCCo | Notifying party |
| As agreed. |
2.4.4 | Next opportune meeting. | If issue substantiated, prepare and submit report with recommendations to the Panel. | BSCCo | Panel | Report to the Panel. | Internal Process. |
2.4.5 | Within 5 WD of 2.4.4 above | Notify Parties and Party Agents of Panel decision and if necessary update Compliance and/or Protocol Approval list. | BSCCo | Parties Party Agents | Issue and Panel decision. | Circular. |
Half Hourly Data Collector / Asset Metering Half Hourly Data Collector | System or Process4 | Instation Version | Outstation Version |
|
|
|
|
|
|
|
|
|
|
|
|
Section C: REQUEST FOR COMPLIANCE TESTING
Metering Equipment/Asset Metering Equipment Description
| ||||||||
Manufacturer | Type | Serial No. | TYPE APPROVAL STATUS | |||||
APPROVED | IN PROGRESS | NONE | ||||||
1 |
|
|
|
|
| |||
2 |
|
|
|
|
| |||
3 |
|
|
|
|
| |||
Note: For Manufacturers or AMVLPs seeking Compliance Approval for Asset Metering Equipment the Asset Meter Type number (i.e. 1 to 5) must be included in the Applicable Codes of Practice for Metering Equipment and Asset Metering Equipment table.
I intend to provide Settlement Outstation Protocols, Asset Meter Protocols and Configuration Software to relevant Party Agents on request: tick as appropriate
Applicable Codes of Practice for Metering Equipment and Asset Metering Equipment Testing | ||||||||
Code of Practice *
ONE TWO THREE FIVE | Issue |
| Code of Practice *
SIX SEVEN TEN ELEVEN Asset Meter Type 1, 2, 3, 4, 5 | Issue |
|
Testing of Metering Equipment for Codes of Practice One, Two, Three, Five, Six and Ten (3.3.2); or
Testing of Asset Metering Equipment for Code of Practice Eleven (3.3.3)6.
technical requirements for testing;
testing facilities to be provided; and
Test Procedures to be followed,
Data retrieval;
Data security;
Time reset; and
Data file creation.
Date and time;
Location; and
Parties present
Serial number;
Type reference;
Make and model;
Record whether the Asset Meter has half hourly data storage capability;
Record whether the Asset Meter is using an instantaneous power output and if so the method used;
Record whether the Asset Meter has an internal clock;
Number and type of measured quantities available in the Asset Meter;
Record energy flow direction capability (i.e. active import and/or active export); and
Record any software and firmware versions.
Record number of measured quantities configured (i.e. Import and/or Export);
Record Asset Meter cumulative register data constant and scale factor (e.g. MWh x 10), if applicable;
Record Asset Meter instantaneous outputs configured (e.g. Import Power and/or Export Power) and any scaling factors for instantaneous outputs (e.g. 4mA = 10MW), if applicable;
Confirm if applicable, that Asset Meter time is set to UTC; and
Confirm the security access required.
Confirm if AMHHDC data retrieval Instation or HHDC Instation;
Record Type, version and operating platform;
Record the software version of any relevant module details; and
Configure the Instation for the Asset Meter set up in c. above.
the technical requirements for the Test Laboratory in order for it to carry out its obligations under the terms of the Compliance Testing agreement;
the testing facilities to be provided by the Test Laboratory; and
the test procedures to be followed by the Test Laboratory,
BS 7856 | ‘Code of Practice for Design of Alternating Current Watt-Hour Meters for Active Energy (Classes 1 and 2)’ |
BS EN/IEC 62053-22 | Electricity metering equipment (a.c.) - Particular requirements – Part 22: Static meters for active energy (classes 0.2S and 0.5S) |
BS EN/IEC 62053-11 | Electricity metering equipment (a.c.) - Particular requirements – Part 11: Electromechanical meters for active energy (classes 0.5, 1 and 2) |
BS EN/IEC 62053-23 | Electricity metering equipment (a.c.) - Particular requirements – Part 23: Static meters for reactive energy (classes 2 and 3) |
BS EN/IEC 62056-21 | Electricity metering – Data exchange for meter reading, tariff and load control – Part 21: Direct local data exchange |
BS EN/IEC 62053-21 | ‘Alternating current static watt-hour meters for active energy (classes 1 and 2)’ |
BS EN/IEC 61000-4-3 | Electromagnetic Compatibility (EMC) – Part 4-3: Testing and Measurement techniques – Radiated, radio-frequency, electromagnetic field immunity test. |
Electricity Act 1989 | ‘Schedule 7, as amended by Schedule 1, to the Competition and Services (Utilities) Act 1992.’ |
Statutory Instrument 1998 No. 1565 | ‘The Meters (Approval of Pattern or Construction and Manner of Installation) Regulations 1998.’ |
Statutory Instrument 1998 No.1566 | ‘Electricity – The Meters (Certification) Regulations 1998.’ |
Statutory Instruments 2016 No.1153
Statutory Instruments 2019 No. 696 | ‘The Measuring Instruments Regulations 2016, as amended by the Product Safety & Metrology etc (Amendment etc.) Regulations (EU Exit) (SI 2019/696) legislation.’
‘The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019.’ |
(a) | i) Establish if the Pulse Multiplier can be of a value other than 1 (under any circumstance); and ii) Where the value can be other than 1 record the values and circumstances. | 001 |
(b) | establish the number and type of Measured Quantities available on the Meter; | 002 |
(c) | if more than one Measured Quantity configuration is available, list all configurations; | 003 |
(d) | confirm that a cumulative register display is available for each Measured Quantity (see also 3.4.12); | 004 |
(e) | Import Active Energy is measured in kWh; Import Reactive Energy is measured in kvarh; | 005 |
(f) | Export Active Energy is measured in kWh; Export Reactive Energy is measured in kvarh; and | 006 |
(g) | confirm that Measured Quantities are available in both kilo and Mega values. (CoPs 1, 2, 3 and 5) | 007 |
(a) | confirm that a kW value is provided for each Demand Period for each Active Energy Measured Quantity; and kvar value is provided for each Demand Period for each Reactive Energy Measured Quantity. | 008 |
(b) | Confirm that Reactive Import and Export quantities (kvar and kvarh) can be provided separately for both Import and Export Active Power conditions. (CoP1, 2, 3 and 5)
| 009 |
(c) | Confirm that reactive quantities (kvar and kvarh) can be provided cumulatively as both Import and Export regardless of Active Power conditions.
| 010 |
(d) | where Active Import and Active Export values are provided confirm that each value is gross and recorded separately. (CoP3, 5, and 10); and | 011 |
(e) | confirm that Demand Values are available in both kilo and Mega values. (CoPs 1, 2, 3 and 5) | 012 |
Tests shall be carried out at fundamental frequency (50Hz) to verify that the Active Energy measurements are within the limits shown in Table 1 below. The measurement uncertainty at fundamental frequency of the measurement system used shall not be greater than: ±0.01% (CoP1); ±0.05% (CoP2); ±0.1% (CoP3); or ±0.2% (CoP5). | 013 |
Value of Current (I) | Power factor (Cos φ) | Percentage error limits10 for Meters of Class | |||||
For whole current Meters | For transformer operated Meters11 | 0.2S (CoP1) | 0.5S (CoP2) | 0.5 (CoP2) | 1 (CoP3) | 2 (CoP5) | |
- | 0.01 In ≤ I < 0.05In | 1 | ±0.4 | ±1.0 | - | - | - |
- | 0.05 In ≤ I ≤ Imax | 1 | ±0.2 | ±0.5 | - | - | - |
- | 0.02 In ≤ I < 0.1In | 0.5 ind 0.8 cap | ±0.5 ±0.5 | ±1.0 ±1.0 | - | - | - |
- | 0.1 In ≤ I ≤ Imax | 0.5 ind 0.8 cap | ±0.3 ±0.3 | ±0.6 ±0.6 | - | - | - |
0.05 Ib ≤ I < 0.1 Ib12 | 0.02 In ≤ I < 0.05 In | 1 | - | - | ±1.0 | ±1.5 | ±2.5 |
0.1 Ib ≤ I ≤ Imax | 0.05 In ≤ I ≤ Imax | 1 | - | - | ±0.5 | ±1.0 | ±2.0 |
0.1 Ib ≤ I < 0.2 Ib13 | 0.05 In ≤ I < 0.1 In | 0.5 ind 0.8 cap | - | - | ±1.3 ±1.3 | ±1.5 ±1.5 | ±2.5 - |
0.2 Ib ≤ I ≤ Imax | 0.1 In ≤ I ≤ Imax | 0.5 ind 0.8 cap | - | - | ±0.8 ±0.8 | ±1.0 ±1.0 | ±2.0 - |
Tests shall be carried out at fundamental frequency (50Hz) to verify that the Reactive Energy measurements are within the limits show in Table 2 below. The measurement uncertainty at fundamental frequency of the measurement system used shall not be greater than ±0.4%. (CoPs 1, 2, 3 and 5) | 014 |
Value of Current (I) | Sin φ | Percentage error limits10 for Meters of Class | Applicable BS EN Standard for Test Criteria | ||
For whole current Meters | For transformer operated Meters | 2 (CoP1 ) | 3 (CoPs 2, 3 and 5) | ||
0.05 Ib ≤ I < 0.1 Ib | 0.02 In ≤ I < 0.05 In | 1 | ±2.5 | ±4.0 | BS EN/IEC 62053-23 |
0.1 Ib ≤ I ≤ Imax | 0.05 In ≤ I ≤ Imax | 1 | ±2.0 | ±3.0 | |
0.1 Ib ≤ I < 0.2 Ib | 0.05 In ≤ I < 0.1 In | 0.5 ind or cap | ±2.5 | ±4.0 | |
0.2 Ib ≤ I ≤ Imax | 0.1 In ≤ I ≤ Imax | 0.5 ind or cap | ±2.0 | ±3.0 | |
0.2 Ib ≤ I ≤ Imax | 0.1 In ≤ I ≤ Imax | 0.25 ind or cap | ±2.5 | ±4.0 | BS EN/IEC 62053-23 |
0.2 Ib ≤ I ≤ Ib | 0.1 In ≤ I ≤ In | 0.25 ind or cap | - | ±10.0 | BS EN/IEC 62053-23 |
† Permission to reproduce extracts from BS EN 62053–22, BS EN 62053–11, BS EN 62053-21 and BS EN 62053–23 is granted by BSI. British Standards can be obtained in PDF or hard copy formats from the BSI online shop: www.bsigroup.com/Shop or by contacting BSI Customer Services https://shop.bsigroup.com/Contact-Us/ • This permission does not cover any other editions. • On no account shall the extracts used be distributed as part of any other work not permitted under this licence. • This permission relates to the extracts listed above. Where the standard is updated and/or if there is a requirement for further reproduction of extracts you will need to make a new application. PERMISSION TO USE THE EXTRACTS LISTED IS GRANTED ONLY ON THE ABOVE CONDITIONS |
Record the available range of measurement transformer compensation adjustment provided for both current and voltage measurements. (CoPs 1, 2, 3 and 5) | 015 |
Record the available range of power transformer compensation adjustment provided. (If this adjustment is recorded as part of test 3.4.9 above then record that no additional adjustment is available) (CoPs 1, 2, 3 and 5) | 016 |
(a) | record whether the Meter is of a Static or induction disc type; | 017 |
(b) | record whether the Meter has an integral Outstation; | 018 |
(c) | establish that the Active Energy Meter meets the requirements of: i. CoP1 BS EN/IEC 62053-22 Class 0.2S; ii. CoP2 BS EN/IEC 62053-22 Class 0.5S or BS EN/IEC 62053-11 Class 0.5; iii. CoP3 BS EN/IEC 62053-21 Class 1; iv. CoP5 BS EN/IEC 62053-21 Class 2 and BS 7856 Class 2; or v. CoP10 SI 1998 No 1566 or SI 2016 No 1153. | 019 |
(d) | establish whether the Import Active Energy Meter meets the requirements of Schedule 7 of the Electricity Act 1989; | 020 |
(e) | establish that the Reactive Energy Meter meets the requirements of; i. CoP1 BS EN/IEC 62053-23 Class 2; ii. CoP2 BS EN/IEC 62053-23 Class 3; iii. CoP3 BS EN/IEC 62053-23 Class 3; or iv. CoP5 BS EN/IEC 62053-23 Class 3. | 021 |
(f) | establish whether the number of measuring elements is one less or equal to the number of primary system conductors; | 022 |
(g) | record whether provision has been made for the recording of measurement transformer ratios on the Meter’s name plate; (CoPs 1, 2, 3 and 5) | 023 |
(h) | if the Meter is a static Meter with combined display and/or Outstation, then confirm that the ratios can be displayed and downloaded during the interrogation process; | 024 |
(i) | Also confirm that any compensation factors that have been applied for measurement transformer errors and/or system losses, and where this is a constant factor applied at security Level 3, can be similarly displayed and downloaded; (CoPs 1, 2, 3 and 5) | 025 |
(j) | confirm that the Meter includes a non-volatile Meter register of cumulative energy for each Measured Quantity; | 026 |
(k) | confirm that the Meter Register(s) do not roll-over more than once within the normal reading cycle [90 days at full load]; and (CoPs 1, 2, 3 and 5) | 027 |
(l) | where the Meter is to be used with an external Outstation, confirm that the Meter is fitted with at least one output pulse facility for each Measured Quantity (two output pulse facilities are required in the case of CoP1). (CoPs 1, 2, 3 and 5) | 028 |
(a) | the total cumulative energy values for each Measured Quantity in actual scaled values and that such values are stored in non–volatile memory; | 029 |
(b) | the current time and date; | 030 |
(c) | the CT and/or VT ratios that have been programmed into the Meter; | 031 |
(d) | any compensation factor applied for measurement transformer errors and/or system losses; and (CoPs 1, 2, 3 and 5) | 032 |
(e) | that, where the Meter is combined with the display and/or Outstation and a constant factor is applied, such factor is applied at security Level 3. (CoPs 1, 2, 3 and 5) | 033 |
(a) | the Maximum Demand (“MD”) for kW or MW (CoPs 1, 2, 3 and 5) per month; | 034 |
(b) | the Maximum Demand (“MD”) for kW or MW (CoPs 1, 2, 3 and 5) for other programmable charging periods; | 035 |
(c) | the Maximum Demand (“MD”) for kVA or MVA (CoPs 1, 2, 3 and 5) per month can; | 036 |
(d) | the Maximum Demand (“MD”) for kVA or MVA (CoPs 1, 2, 3 and 5) for other programmable charging periods; | 037 |
(e) | twice the kWh or MWh advance from the commencement of the current Demand Period; (CoPs 1, 2, 3 and 5) | 038 |
(f) | twice the kVAh or MVAh advance from the commencement of the current Demand Period; (CoPs 1, 2, 3 and 5) | 039 |
(g) | the cumulative Maximum Demand; | 040 |
(h) | the number of Maximum Demand resets; | 041 |
(i) | the multi rate display sequence, for at least 8 rates selectable over the calendar year; | 042 |
(j) | whether a reverse running indication for Active Energy is provided. (CoPs 3 and 5); | 043 |
(k) | the indicated Maximum Demand is re-settable at midnight of the last day of the selected charging period; | 044 |
(l) | the indicated Maximum Demand is re-settable for a part of a charging period; and | 045 |
(m) | any Maximum Demand manual reset button is sealable. | 046 |
Establish whether the Meter is capable of providing different voltage free pulsed outputs for local use. | 047 |
If test 047 is confirmed then confirm that the facilities meet the following requirements as shown in Table 3. | 048 |
Requirement | Code of Practice | |||
1 | 2 | 3 | 5 | |
Number of Outputs | 1 per Measured Quantity | 1 per Measured Quantity | 3 min (See 3.4.13 (a)) | 3 min (See 3.4.13 (a)) |
Pulse Rate | Min at full load 1000 per Demand Period | Min at full load 1000 per Demand Period | Between 0.1 and 2/ second | Between 0.1 and 2/ second |
Nominal Pulse Duration (mS) | 80 | 80 | 80 | 80 |
(a) | confirm that at least two of the outputs can be allocated to the Measured Quantities identified in {5.4.2}. (CoPs 3 and 5); and | 049 |
(b) | confirm that one output can be allocated to the Demand Period reset (usually 30 minutes) within a tolerance of ±0.1% and a duration of between 0.5 and 10 seconds. | 050 |
(a) | The Outstation has a unique Outstation identification code; | 051 |
(b) | For Meters with integral Outstations an auxiliary terminal provides for the Outstation's energisation for remote interrogation purposes (CoP1). For Meters with integral Outstations record whether an auxiliary terminal provides for the Outstation’s energisation for remote interrogation purposes (CoP2); | 052 |
(c) | Facilities are provided to select a relevant demand period from one of the following values: 30, 20, 15, 10 and 5 minutes with, in each case, one demand period ending on the hour. | 053 |
(d) | The Outstation is capable of communicating with more than one Instation (not simultaneously and of similar type or otherwise); | 054 |
(e) | It is possible to repeatedly retrieve data throughout the Outstation data storage period; | 055 |
(f) | Any “read” operation does not alter or delete any stored metered data; and | 056 |
(g) | The Outstation can provide all metered data stored from the time of commencement of any specified date upon request by the Instation during the data storage period of the outstation. | 057 |
(h) | In addition, establish whether the Outstation is capable of sending metering data automatically (CoPs 5 and 10). If this test is satisfied then: | 058 |
(i) | Verify that the metering data sent complies with section 3.4.22 ‘Level 1 Passwords’ of this test specification (CoPs 5 and 10); and | 059 |
(j) | Establish whether the Outstation is capable of sending metering data on a daily basis as a minimum (CoPs 5 and 10). | 060 |
(a) | from the beginning of the current Demand Period, twice the kWh or MWh (CoPs 1, 2, 3 and 5) is being registered in the kW or MW (CoPs 1, 2, 3 and 5) Maximum Demand register; and | 061 |
(b) | from the beginning of the current Maximum Demand period, twice the kVAh or MVAh (CoPs 1, 2, 3 and 5) is being registered in the kVA or MVA (CoPs 1, 2, 3 and 5) Maximum Demand register. | 062 |
(a) | each Demand Value is identifiable to its respective date and time; and | 063 |
(b) | a storage capacity of 48 periods per day in accordance with Table 4 below is available for all Demand Values as integer multiples of kW or MW (CoPs 1, 2, 3 and 5); | 064 |
Code of Practice | Minimum Storage Period(days) |
1 | 90 |
2 | 90 |
3 | 90 |
5 | 90 |
10 | 90 |
(a) | for each of the initial five days, the sum of the Demand Values for each block of 48 half-hour periods are within 0.1% of the advance of the total cumulative register of the associated Meter for the same interval; | 065 |
(b) | the value of any energy measured in a Demand Period, but not stored in that Demand Period are carried forward to the next Demand Period; | 066 |
(c) | for each of the twenty days under test that the contents of the kW or MW (CoPs 1, 2, 3 and 5) data stored facility have been stored correctly; and | 067 |
(d) | for separate Meter/Outstation combinations, that the Outstation registers can be set to match and increment with the Meter registers. (CoPs 1, 2, 3 and 5) | 068 |
(a) | on reaching maximum memory storage capacity, that any new data overwrites the oldest stored data; and | 069 |
(b) | no other data has been altered or removed. | 070 |
(a) | all stored data has been correctly stored and is not corrupt; | 071 |
(b) | the Metering Equipment internal clock is accurate to within ±10 seconds14; and | 072 |
(c) | partial Demand Values in which an Outstation supply failure and/or restoration occurs and any zero values associated with the Outstation supply failure are marked so that they can be identified by the Instation. | 073 |
(a) | the Metering Equipment internal time clock is accurate to within ±10 seconds16; and | 074 |
(b) | the duration of each Demand Period is within ±0.1% of 30 minutes, this being achieved by the comparison of stored energy values or pulse counts in each Demand Period. | 075 |
Set the Metering Equipment internal time clock to five minutes slow with respect to UTC. Then synchronise the internal time clock using the remote Instation and check that the Demand Period has been marked with an alarm indication. | 076 |
Repeat the synchronisation test using the Local Interrogation Unit and check that the Demand Period has been marked with an alarm indication. | 077 |
(a) | disconnect one phase from the Metering Equipment and ensure that a phase failure has occurred and is assigned to the relevant Demand Period; | 078 |
(b) | repeat the disconnection process for each of the remaining phases in separate Demand Periods; | 079 |
(c) | repeat the disconnection process for combinations of multiple phase failure; and | 080 |
(d) | verify phase failure alarm resets on restoration of normal supply after each test. | 081 |
If battery fitted, establish the method of battery monitoring and test for alarms and indications tagged to the relevant Demand Periods, if necessary by disconnecting the battery. | 082 |
For Outstations using other methods of time synchronisation, such as a Radio Teleswitch, confirm that any truncated or extended Demand Period is tagged with a separate alarm indication. | 083 |
Using the Local Interrogation Unit access the local port and change data other than time and/or date. Confirm that the relevant Demand Period is tagged with a separate alarm indication. | 084 |
Using the Instation to access the remote port, change data other than time and/or date. Confirm that the relevant Demand Period is tagged with a separate alarm indication. | 085 |
Where an Active Energy reverse running display is provided, determine that the requirements of BS EN/IEC 62053-21 or BS EN/IEC 62053-22 as appropriate are met. Establish under what conditions the reverse running flag is activated and record those conditions. Tests should include single and polyphase power reversals and set the appropriate flag for the Demand Period affected (CoPs 3 and 5, and if fitted). | 086 |
Test that upon return to normal power flow, the reverse running flag is no longer present in the unaffected Demand Period (CoPs 3 and 5, and if fitted). | 087 |
Verify that two communications ports are available for interrogating the Outstation | 088 |
(a) | The local port provides data to a Local Interrogation Unit via an opto port to BS EN/IEC 62056-21; or | 089 |
(b) | The local port provides data to a Local Interrogation Unit via another type of port; and | 090 |
(c) | Repeat collections of stored data are available throughout the storage period and verify that any “read” operation does not delete or modify any stored metering data. | 091 |
(a) | The remote port is sealable; and | 092 |
(b) | Repeat collections of stored data are available throughout the storage period and verify that any “read” operation does not delete or modify any stored metering data | 093 |
(a) | For separate Outstations establish that a password is required to read or change any data. (CoPs 1, 2, 3 and 5) | 094 |
(b) | For integral Outstations establish that four17 discrete password controlled access levels are provided for both local and remote interrogation. | 095 |
(c) | For alpha numeric character passwords, ensure that passwords are no less than six characters and no more than twelve characters long. Ensure that passwords are formed from case insensitive or sensitive alpha characters (A to Z) and/or digits (0 to 9) and/or the underscore character (_); or (CoPs 1, 2, 3 and 5) | 096 |
(d) | For hexadecimal character passwords, ensure that passwords are no less than eight characters and no more than twelve characters long. Ensure that passwords are formed from upper case hexadecimal characters (0 to F). (CoPs 1, 2, 3 and 5) | 097 |
(a) | Outstation ID; | 098 |
(b) | all programmable Demand Values; | 099 |
(c) | all programmable cumulative Measured Quantities; | 100 |
(d) | the Maximum Demand for kW and/or kVA per programmable charging period; | 101 |
(e) | the multi-rate cumulative Active Energy values; | 102 |
(f) | the VT and CT transformer ratios, where appropriate; | 103 |
(g) | (for combined Meter and Outstation only), the VT and CT transformer error correction factor and/or system loss factor applied as a constant factor to the entire dynamic range; (CoPs 1, 2, 3 and 5) | 104 |
(h) | all alarm indications; and | 105 |
(i) | Outstation time and date | 106 |
Establish that it is not possible to change any of the above values at Level 1 Password. | 107 |
Using the Level 2 Password, establish that all the data listed at Level 1 can be retrieved and in addition that the following actions can be performed: | 108 | |
(a) | changes to time and date; and | 109 |
(b) | resetting of all Maximum Demands. | 110 |
Using the Level 3 Password, establish that all the functionality listed at Level 2 can be performed and in addition that the following programming can be performed: | 111 | |
(a) | Displays and Facilities as defined in clauses 3.4.12 ‘Displays {5.4.1}’ and 3.4.13 ‘Facilities {5.4.2}’ of this test specification; | 112 |
(b) | measurement transformer ratios as defined in clause 3.4.11 ‘Meter {5.3}’ of this test specification; | 113 |
(c) | (for combined Meter and Outstation only), the VT and CT transformer error correction factor and/or system loss factor applied as a constant factor to the entire dynamic range; and (CoPs 1, 2, 3 and 5) | 114 |
(d) | passwords for Levels 1, 2 and 3. | 115 |
(e) | where applicable, confirm it is possible to programme the schedule for automated transfer of Level 1 metering data via Level 3 access (CoPs 5 and 10). | 116 |
Establish that it is possible to read additional information within the Metering Equipment to enable the programmed information to be confirmed. | 117 |
(a) | establish that all the functionality listed at Level 3 can be performed and in addition that the following alterations can be performed: | 118 |
(b) | calibration of the Meter (only where the Meter is integral with the Outstation); | 119 |
(b) | setting the measurement transformer ratios, where appropriate; | 120 |
(d) | setting the measurement transformer error correction and/or system loss factors applied as a complex factor; and | 121 |
(e) | programming the Level 3 & 4 Passwords. | 122 |
(a) | calibration of the Meter (only where the Meter is integral with the Outstation); | 123 |
(b) | setting the measurement transformer ratios, where appropriate; and | 124 |
(c) | setting the measurement transformer error correction and/or system loss factors applied as a complex factor. | 125 |
Using the Approved Protocol18, verify that the password offered determines the Level of access to the data within the Metering Equipment. | 126 |
(a) | the illegal password counter resets to zero every hour on the hour change; and | 127 |
(b) | after the seventh illegal password attempt entered between counter resets, that access is prohibited at all levels until the counter resets. | 128 |
(a) | any stored data and time/date is not corrupted or has been destroyed; and | 129 |
(b) | the metering accuracy remains within the requirements of clause 3.4.8 ‘Accuracy Requirements {5.3}’ of this test specification. | 130 |
the voltage and auxiliary circuits energised with reference voltage;
a frequency band of 26MHz to 1GHz;
a test field strength of 12.5V/m; and
a carrier of 80% amplitude modulated with a 1kHz sine wave.
(a) | that without any current in the current circuits and the current terminals open circuit the application of the HF fields shall not produce a change in the Meter Register reading of more than 0.01kWh and the test output shall not produce a signal equivalent to more than 0.01kWh. (Where VT and CT connected Meter(s) is under test, equivalent scaled values should be used taking into account the transformer ratios); and | 131 |
(b) | that with basic current Ib, and power factor equal to 1.0, at sensitive frequencies or frequencies of dominant interest, the variation of error does not exceed 3%. | 132 |
(a) | any stored data is not corrupted or has been destroyed; and | 133 |
(b) | the metering accuracy remains within the requirements of clause 3.4.8 ‘Accuracy Requirements {5. 3}’of this test specification. | 134 |
Ensure that adequate sealing facilities are provided for Settlement requirements. | 135 |
IEC 1334-4-41 | Application Protocols: Distribution Line Message. |
BS EN/IEC 62053-21 | AC Static Watthour Meters for Active Energy (Class 1 and 2) |
|
|
BS EN/IEC 62056-21 | Data Exchange for Meter Reading, Tariff and Load Control. Direct Local Exchange. |
Retail Energy Code Metering Operations Schedule | Sealing Requirements |
This specification 3.6 sets out:-
the technical requirements for the Test Laboratory in order for it to carry out its obligations under the terms of the Compliance Testing agreement;
the testing facilities to be provided by the Test Laboratory; and
the test procedures to be followed by the Test Laboratory to determine the accuracy and functionality of items of Asset Metering Equipment as conforming, or otherwise, to the requirements of the Balancing and Settlement Code and Code of Practice Eleven.
An Asset Meter approved for use in Code of Practice 1, 2, 3, 5 and 10 that is a Half Hourly Integral Outstation Meter. These Meters and Outstations shall be approved under 3.4 of this BSCP (Specification for Compliance Testing of Metering Equipment for Codes of Practice One, Two, Three, Five and Ten);
An Asset Meter whose primary purpose is the measurement of Active Power and/or Active Energy that is not a Half Hourly Integral Outstation Meter approved for use under Code of Practice 1, 2, 3, 5 and 10; and
An Asset Meter whose primary purpose is not the measurement of Active Power and/or Active Energy and is not a Half Hourly Integral Outstation Meter approved for use under Code of Practice 1, 2, 3, 5 and 10. These Embedded Metering Devices are embedded within equipment used for purposes other than the measurement of Active Power and/or Active Energy, such as an EV charging unit or a small-scale domestic battery storage unit.
The Compliance Testing requirements as detailed in this Appendix apply only to parts of the Asset Metering System (i.e. Asset Meters) and therefore satisfactory test results from this Compliance Testing do not constitute a compliant Asset Metering System as required by the Code, Balancing and Settlement Code Procedures (“BSCPs”) and Code of Practice Eleven.
This test applies to Code of Practice Eleven for the Asset Metering Types described in category ii) and iii) above and should be used by the Compliance Testing Agent to confirm compliance with the relevant Asset Metering Type the Asset Metering Equipment is intended to be approved against.
Unless agreement has been received in writing from BSCCo prior to the commencement of any testing to this specification, this specification is applicable only to one Asset Metering Type at any one time and Asset Metering Equipment requiring compliance with multiple Asset Metering Types shall be subject to a full and complete testing schedule for each Asset Metering Type.
Asset Metering Type 1 - Metering of circuits with a rated capacity greater than 100MVA;
Asset Metering Type 2 - Metering of circuits with a rated capacity not exceeding 100MVA;
Asset Metering Type 3 - Metering of circuits with a rated capacity not exceeding 10MVA;
Asset Metering Type 4 - Metering of energy transfers with a Maximum Demand of up to (and including) 1MW; and
Asset Metering Type 5 - Metering (embedded within another device) for energy transfers with a Maximum Demand of up to (and including) 100kW.
BS EN/IEC 62053-21 | Electricity metering equipment - Particular requirements – Part 21: Static meters for AC active energy (classes 0,5, 1 and 2) |
BS EN/IEC 62053-22 | Electricity metering equipment - Particular requirements - Part 22: Static meters for AC active energy (classes 0,1S, 0,2S and 0,5S) |
BS EN 50470-3 | Electricity metering equipment (a.c.). Particular requirements. Static meters for active energy (class indexes A, B and C) |
BS EN/IEC 61000-4-3 | Electromagnetic compatibility (EMC) - Part 4-3: Testing and measurement techniques - Radiated, radio-frequency, electromagnetic field immunity test |
BS EN/IEC 62052-11 | Electricity Metering Equipment – General Requirements, Tests and Test Conditions – Part 11: Metering equipment |
BS EN/IEC 61557-12 | Electrical safety in low voltage distribution systems up to 1000 V a.c. and 1500 V d.c. Equipment for testing, measuring or monitoring of protective measures. Performance measuring and monitoring devices (PMD) |
BS EN/IEC 60688 | Electrical measuring transducers for converting a.c. electrical quantities to analogue or digital signals |
BS EN/IEC 62056-21 | Electricity metering. Data exchange for meter reading, tariff and load control. Direct local data exchange |
(a) | i) Establish if the Pulse Multiplier can be of a value other than 1 (under any circumstance); and ii) Where the value can be other than 1 record the values and circumstances. | 001 |
(b) | establish the number and type of Measured Quantities available on the Meter; | 002 |
(c) | if more than one Measured Quantity configuration is available, list all configurations; | 003 |
(d) | confirm if a display is fitted | 004 |
(e) | confirm if a cumulative register display is available for each Measured Quantity (see also 3.6.12); | 005 |
(f) | confirm if Import Active Energy is measured in either kWh or MWh; | 006 |
(g) | confirm if Export Active Energy is measured in either kWh or MWh; and | 007 |
(h) | confirm if Measured Quantities are available in kilo values for Asset Metering Type 3, 4 or 5 and Mega values for Asset Metering Type 1 or 2. | 008 |
(a) | Confirm that a kW or MW value is provided for each Demand Period for each Active Energy Measured Quantity; | 009 |
(b) | where Active Import and Active Export values are provided confirm that each value is gross and recorded separately; and | 010 |
(c) | confirm if Demand Values are available in kilo values for Asset Metering Type 3, 4 or 5 and Mega values for Asset Metering Type 1 or 2. | 011 |
For Asset Meters compliant with a relevant standard20 that quotes accuracy classes and limits of error a Test Certificate proving compliance with the relevant standard and accuracy class shall be provided for Active Energy or Active Power measurements, as applicable. Confirm the following:
| 012 |
For a.c. Asset Meters not compliant with a relevant standard20 that quotes accuracy classes and limits of error a Test Certificate for Active Energy or Active Power proving measurements are within the limits shown in Table 5 below. Confirm the following:
| 013 |
For d.c. Asset Meters not compliant with a relevant standard20 that quotes accuracy classes and limits of error a Test Certificate for Active Energy or Active Power proving measurements are within the limits shown in Table 6 below. Confirm the following:
| 014 |
CONDITION | LIMITS OF ERROR AT STATED SYSTEM POWER FACTOR | |||
Frequency range | Voltage expressed as the operational range of the device | Current expressed as the operational range of the device | Power Factor | Limits of Error |
From 49.0 Hz to 51.0 Hz | 90% to 110% Un inclusivea | 50% Imax to Imax inclusive In to 50% Imax In to Imax inclusive | 1 1 0.5 lag and 0.8 lead | ± 2.0% ± 2.5% ± 2.5% |
a. Where Un is one of the nominal voltage values for a.c. meters specified in BS EN/IEC 62052-11 section 4.1.1 Table 1 |
CONDITION | LIMITS OF ERROR AT STATED SYSTEM POWER FACTOR | ||
Voltage expressed as the operational range of the device | Current expressed as the operational range of the device | Power Factor | Limits of Error |
90% to 110% Un inclusivea | 50% Imax to Imax inclusive In to 50% Imax | N/A N/A | ± 2.0% ± 2.5% |
a. Where Un is one of the nominal voltage values for d.c. meters specified in BS EN/IEC 62052-11 section 4.1.1 Table 1 |
| 015 |
| 016 |
Confirm the losses in Watts associated with the inverter and/or rectifier.
| 017 |
(a) | confirm that the Asset Meter has a unique identification code; | 018 |
(b) | confirm that the Asset Meter is capable of communicating with more than one Instation (not simultaneously and of similar type or otherwise); | 019 |
(c) | Where the Asset Meter has data storage functionality, confirm that it is possible to repeatedly retrieve data throughout the Asset Meter data storage period; | 020 |
(d) | Any “read” operation does not alter or delete any stored metered data; and | 021 |
(e) | Where the Asset Meter has data storage functionality, confirm the Asset Meter can provide all metered data stored from the time of commencement of any specified date upon request by the Instation during the data storage period of the Asset Meter. | 022 |
(f) | establish whether the number of measuring elements is one less or equal to the number of primary system conductors; | 023 |
(g) | record whether provision has been made for the recording of measurement transformer ratios on the Asset Meter’s name plate; | 024 |
(h) | Where the Asset Meter is combined with a display, then confirm that the measurement transformer ratios can be displayed and downloaded during the interrogation process; | 025 |
(i) | confirm that any compensation factors that have been applied for measurement transformer errors can be downloaded, and where this is a constant factor applied whether it can be similarly displayed (should a display be fitted); | 026 |
(j) | confirm that the Asset Meter includes a non-volatile register of cumulative energy for each Measured Quantity; | 027 |
(k) | confirm that the cumulative energy register(s) (both displayed registers should a display be fitted and internal registers) do not roll-over more than once within the normal reading cycle [90 days at full load]; and | 028 |
(l) | where the Asset Meter is using an analogue or digital output connected to a separate Outstation/Instation, confirm that the Asset Meter is fitted with at least one output facility capable of transmitting data for each Measured Quantity | 029 |
(a) | the total cumulative energy values for each Measured Quantity in actual scaled values and that such values are stored in non–volatile memory; | 030 |
(b) | the instantaneous parameters (e.g. power, voltage current); | 031 |
(c) | the measurement transformer (i.e. current transformer and/or voltage transformer) ratios that have been programmed into the Asset Meter; | 032 |
(d) | any compensation factor applied, where this is a constant factor, for measurement transformer errors and/or system losses (i.e. power transformer and/or cable/line losses) or inverter losses or rectifier losses; and | 033 |
(e) | any scaling factor applied to an analogue or digital output used to transmit data to a Settlement Instation to convert to energy values for any Measured Quantity (e.g. 50kWh/imp). | 034 |
(a) | Establish whether the Asset Meter is capable of providing an analogue or a digital output | 035 |
(b) | If an analogue output establish whether the Asset Meter is capable of providing different voltage free pulsed outputs. | 036 |
(c) | If test 036 is confirmed then confirm that the facilities have the option of having a suitable value at full load e.g. the between 0.1 and 2 pulses per second with a nominal duration of 80mS per pulse. | 037 |
(d) | If an analogue output is converting a.c. electrical quantities to analogue signals confirm the conversion value options (e.g. Wh/imp). | 038 |
(e) | If a digital output converting a.c. electrical quantities to digital signals confirm the method and any scaling value required. | 039 |
(f) | For all output methods confirm that the output meets the required accuracy class limits for the relevant Asset Metering Type and where the Asset Meter has a cumulative Active Energy register the output cumulative total should be within ±0.1% of the cumulative Active Energy register over the period of test. | 040 |
(a) | the type of port used to provide data to a Local Interrogation Unit | 041 |
(b) | that the following parameters can be downloaded locally:
| 042 |
(c) | Repeat collections of stored data are available throughout the storage period and that any “read” operation does not delete or modify any stored metering data. | 043 |
(a) | the method used to provide data to an Instation remotely (e.g. modem) | 044 |
(b) | that the following parameters can be downloaded remotely:
| 045 |
(c) | Repeat collections of stored data are available throughout the storage period and that any “read” operation does not delete or modify any stored metering data. | 046 |
(a) | Confirm the method of data security used for local interrogation; | 047 |
(b) | Confirm the method of data security used for remote interrogation; | 048 |
(c) | Where passwords are used by the Asset Meter, confirm the number of access levels and what they are limited to (e.g. read only), format and maximum length; | 049 |
(d) | Confirm that a password is required to read or change any parameters programmed into the Asset Meter; and | 050 |
(e) | Confirm that an incorrect password will not read or change any parameters programmed into the Asset Meter. | 051 |
(a) | all stored data has been correctly stored and is not corrupt; | 052 |
(b) | the Asset Meter internal clock is accurate to within ±10 seconds of UTC for Asset Metering Type 1 and 2 or ±20 seconds of UTC for Asset Metering Type 3, 4 and 5; and | 053 |
(c) | partial Demand Values in which an Asset Meter supply failure and/or restoration occurs and any zero values associated with the Asset Meter supply failure are marked so that they can be identified by the Instation. | 054 |
(a) | the Asset Meter internal time clock is accurate to within ±10 of UTC for Asset Metering Type 1 and 2 or ±20 seconds of UTC for Asset Metering Type 3, 4 and 5; and | 055 |
(b) | the duration of each Demand Period is within ±0.1% of the Demand Period length (e.g. 30 minutes), this being achieved by the comparison of stored energy values in each Demand Period (i.e. the stored energy values in the Asset Meter should be constant and the energy value in each Demand Period should be within ±0.1% of the load injected from the stable power supply). | 056 |
(a) | Using the remote Instation synchronise the internal time clock of the Asset Meter and confirm it can be synchronised back to UTC. | 057 |
(b) | Repeat test 057 synchronisation test using the Local Interrogation Unit. | 058 |
(a) | Using the remote Instation synchronise the internal time clock of the Asset Meter and confirm it can be synchronised back to UTC. | 059 |
(b) | Repeat test 059 synchronisation test using the Local Interrogation Unit. | 060 |
(a) | Where the Asset Meter can store Demand Period data, confirm how many days of Demand Period (30 minute length) data can be stored per Measured Quantity (i.e. accounting for all required Measured Quantities22 being programmed into the Asset Meter); | 061 |
(b) | Where the Asset Meter can store Demand Period data, confirm how many Measured Quantities can be stored and what they are (e.g. Active Import, Active Export); | 062 |
(c) | Where the Asset Meter can store Demand Period data, confirm the units of measurement (Asset Metering Type 1 and 2 should be Mega; Asset Metering Type 3, 4 and 5 should be kilo); | 063 |
(d) | Where the Asset Meter can store Demand Period data, confirm each Demand Value is identifiable to its respective date and time; | 064 |
(e) | Where the Asset Meter can store Demand Period data, confirm for each of the twenty days under test that the metered volumes have been stored correctly; | 065 |
(f) | Where the Asset Meter can store Demand Period data, confirm for each of the first five days, the sum of the Demand Values for each block of 48 half-hour periods are within ±0.1% of the advance of the total cumulative register of the associated Asset Meter for the same interval; | 066 |
(g) | Where the Asset Meter can store cumulative energy register data, confirm how many Measured Quantities can be stored and what they are (e.g. Active Import, Active Export); | 067 |
(h) | Where the Asset Meter can store cumulative energy register data, confirm the units of measurement (Asset Metering Type 1 and 2 should be MWh; Asset Metering Type 3, 4 and 5 should be kWh); | 068 |
(a) | on reaching maximum memory storage capacity, that any new data overwrites the oldest stored data; and | 069 |
(b) | no other data has been altered or removed. | 070 |
(a) | that the Asset Meter is compliant with BE EN/IEC 62052-11 EMC requirements; | 071 |
(b) | any stored data and time/date is not corrupted or has been destroyed; and | 072 |
(c) | the metering accuracy remains within the requirements of clause 3.6.8 ‘Accuracy Requirements {6.1.2; 6.1.3}’ of this test specification. | 073 |
the voltage and auxiliary circuits energised with reference voltage;
a frequency band of 26MHz to 1GHz;
a test field strength of 12.5V/m; and
a carrier of 80% amplitude modulated with a 1kHz sine wave.
(a) | that without any current in the current circuits and the current terminals open circuit, the application of the HF fields shall not produce a change in the Asset Meter Register reading of more than 0.01kWh and the test output shall not produce a signal equivalent to more than 0.01kWh. (Where VT and CT connected Asset Meter(s) is under test, equivalent scaled values should be used taking into account the measurement transformer ratios); and | 074 |
(b) | that with basic current Ib, and power factor equal to 1.0, at sensitive frequencies or frequencies of dominant interest, the variation of error does not exceed 3%. | 075 |
(a) | any stored data is not corrupted or has been destroyed; and | 076 |
(b) | the metering accuracy remains within the requirements of clause 3.6.8 ‘Accuracy Requirements {6.1.2; 6.1.3}’of this test specification. | 077 |
(a) | Ensure that adequate facilities are provided for securing the Asset Meter to prevent unauthorised access going undetected. This may include the use of a tamper evident seal or where an Asset Meter is an Embedded Metering Device embedded within equipment used for other purposes that equipment shall be manufactured in such a way so as to prevent unauthorised access. | 078 |
1 Confidentiality agreements shall not prohibit Party Agents from fulfilling their BSC obligations.
§§ The latest versions of the Codes of Practice can be found on the BSC Website.
2 [P375]Copies of the Test Report will be made available by BSCCo to Parties, Meter Operator Agents, Virtual Lead Parties and Half Hourly Data Collectors on request to BSCCo.
3 Copies of the compliance test report will be made available by BSCCo to Parties, Meter Operator Agents, Half Hourly Data Collectors and Asset Metering Half Hourly Data Collectors on request to BSCCo.
4 So approved in accordance with BSCP537.
5 Reference No. obtainable from Elexon Limited
6 Any Half Hourly Integral Outstation Meter approved under 3.3.3 cannot be used for Code of Practice 1, 2, 3, 5 and 10 unless it has been tested as per 3.3.2
7 Period data may be populated by any means providing it enables data retrieval to be differentiated.
8 Metering Equipment should be tested and stamped to the latest iteration of the applicable standard named in this document at the time of initial registration.
9 Viewed from the front of the Meter, as though reading the display.
10 Single-phase Meters and polyphase Meters with balanced loads.
11 BS EN/IEC 62053-11 specifies values of current as ‘basic’ (i.e. see figures in whole current Meters column)
12 BS EN/IEC 62053-11 specifies one test point (0.05 Ib)
13 BS EN/IEC 62053-11 specifies one test point (0.1 Ib)
14 For tests to Code of Practice 3, 5 and 10, period of disconnection is 20 days and the acceptable tolerance is ±20 Seconds.
15 For tests to Codes of Practice 3, 5 and 10, this period is 20 days
16 For tests to Code of Practice 3, 5 and 10, the acceptable tolerance is ±20 Seconds.
17 For CoP 10 only three are required
18 If the protocol has not yet received Approval, record the status and description of the protocol used for testing purposes.
19 Asset Metering Equipment should be tested and stamped to the latest iteration of the applicable standard named in this document at the time of initial registration.
20 a recognised national or international standard such as International Electrotechnical Commission (IEC); European Committee for Electrotechnical Standardization (CENELEC); International Organization for Standardization (ISO); British Standards Institution (BSI), etc
21 Viewed from the front of the Asset Meter, as though reading the display.
22 Code of Practice Eleven only requires a maximum number of two Measured Quantities (i.e. Active Import and Active Export)
23 Electricity Metering Equipment – General Requirements, Tests and Test Conditions – Part 11: Metering equipment
24 Electromagnetic compatibility (EMC) - Part 4-3: Testing and measurement techniques - Radiated, radio-frequency, electromagnetic field immunity test