BSCP513: BULK CHANGE OF NHH SUPPLIER AGENT
Date : 1 September 2021
|
Intellectual Property Rights, Copyright and Disclaimer The copyright and other intellectual property rights in this document are vested in Elexon or appear with the consent of the copyright owner. These materials are made available for you for the purposes of your participation in the electricity industry. If you have an interest in the electricity industry, you may view, download, copy, distribute, modify, transmit, publish, sell or create derivative works (in whatever format) from this document or in other cases use for personal academic or other non-commercial purposes. All copyright and other proprietary notices contained in the document must be retained on any copy you make. All other rights of the copyright owner not expressly dealt with above are reserved. No representation, warranty or guarantee is made that the information in this document is accurate or complete. While care is taken in the collection and provision of this information, Elexon Limited shall not be liable for any errors, omissions, misstatements or mistakes in any information or damages resulting from the use of this information or action taken in reliance on it. |
Version | Date | Description of Changes | CPs Included | Mods Panel Ref |
1.0 | 17/02/03 | Incorporates changes for P63. | P63 | SVG/20/251 SVG/21/256 |
2.0 | 23/02/05 | SVA February 05 Release and BETTA 6.3 | P159, BETTA 6.3, CP1091 | SVG/47/004 |
3.0 | 01/09/21 | 1 September 2021 Non-Standard Release | P420 | P316/05 |
BSC | Balancing and Settlement Code |
BSCCo | Balancing and Settlement Code Company |
BSCP | BSC Procedure |
DA | Data Aggregator |
DC | Data Collector |
ID | Identifier |
NHH | Non-Half Hourly |
SVA MOA | SVA Meter Operator Agent |
SMRA | Supplier Meter Registration Agent |
SMRS | Supplier Meter Registration Service |
SVA | Supplier Volume Allocation |
WD | Working Day |
REF | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
3.1.1 | Prior to submitting a bulk change of agent / revised bulk change of agent application. | Liaise with Supplier Agent(s) and SMRA to put together the bulk change of agent application / revised application. | Supplier. | Supplier Agent(s), SMRA. | Determine the information to be provided in the bulk change of agent application. | Verbal /Email. |
3.1.2 | Prior to next Panel meeting and sufficiently in advance of bulk change of agent transfer date4. | Submit bulk change of agent application / revised application. | Supplier. | BSCCo. | Complete form BSCP513/01 Part A in accordance with Appendix 4.1. | Post /Email. |
3.1.3 | Within 1WD of receipt of 3.1.2. | Acknowledge receipt of application. | BSCCo. | Supplier. | Date of receipt of application. | Fax/Email. |
3.1.4 | At next Panel meeting. | Verify that all information required has been provided in 3.1.2 and determine whether or not to approve bulk change of agent application. | Panel. |
| Information provided in accordance with Appendix 4.1, and any previous experience Supplier has in bulk changes of agents. | Internal Process. |
3.1.5 | Following Panel meeting. | If necessary, request additional information from Supplier in support of bulk change of agent application. | BSCCo. | Supplier. | Request for additional information, as necessary. | Fax/Email. |
3.1.6 | If required, within 2WD of 3.1.5. | Submit additional information. | Supplier. | BSCCo. | Additional information as requested. | Fax/Email. |
3.1.7 | Within 1WD of 3.1.4 or 3.1.6, as the case may be. | Notify Supplier of determination. | BSCCo. | Supplier. | BSCP513/01 Part B, including details of Panel decision, reasons for decision and any other requirements that must be met by Supplier (e.g. a test run or a reduction in volume). | Fax/Email. |
3.1.8 | If application refused. | If required, return to 3.1.1 and submit revised bulk change of agent application. | Supplier | BSCCo. | Complete form BSCP513/01 Part A in accordance with Appendix 4.1. | Post /Email. |
3.1.9 | If application approved, at same time as 3.1.7. | Publish notice of approval of bulk change of agent application. | BSCCo. | BSC Website users. | Details of application as submitted in 3.1.1. | BSC Website. |
3.1.10 | If application approved, following 3.1.9. | Proceed with bulk change of agent on an SMRS by SMRS basis, in accordance with BSCP501, 504 and/or 505 (as the case may be) and any additional requirements specified in 3.1.7. | Supplier. |
|
|
|
3.1.11 | Within 5WD of processing the bulk change of agent. | Provide status of bulk change of agent. | Supplier. | Panel. | Status of bulk change of agent including:
| Fax/Email. |
each SMRA affected by proposed bulk change of agent, including their contact details;
each Supplier Agent affected (both old and new), including their contact details; and
the total number of SVA Metering Systems involved in the process.
the bulk change of agent transfer date;
the effective date of the agent appointment registration change(s) (ie. Effective from Date {SVA MOA} and / or Effective from Date {DCA} and / or Effective from Settlement Date {DAA}) in SMRS(s);
a confirmation date (subsequent to the effective date of the appointment registration change(s)) that the bulk change of agent has been completed; and
the extent of the resolution period for resolving any issues arising during or after the bulk change of agent.
written confirmation, at company director level, that the Supplier has sufficient resources and expertise in place to administer the bulk change of agent without adversely impacting operations;
separate written confirmation from the relevant Supplier Agent(s) and SMRA(s) that they can proceed with the bulk change of agent without adversely impacting their day-to-day operational activities; and
a methodology statement for managing implementation and issue resolution.
| Tick |
Written confirmation that Supplier is able to administer the proposed |
|
bulk change of agent |
|
|
|
Written confirmation from relevant SMRA that they are able to proceed |
|
|
|
|
|
Written confirmation from relevant Supplier Agent(s) that they are able to |
|
proceed |
|
|
|
Methodology statement for processing bulk change of agent |
|
1 A Supplier considering initiating a bulk change of agent may choose to initiate a test run with the affected SMRAs and / or Supplier Agents.
2 In order to address any data quality issues, the Supplier may choose to instruct its Supplier Agents to cleanse their records prior to submitting a bulk change of agent application; therefore reducing the potential for issues to arise once the bulk change of agent has been initiated.
3 All obligations on the Panel within this BSCP may be delegated to an appropriate Panel Committee.
4 When submitting the bulk change of agent application / revised bulk change of agent application, the Supplier will take into account, wherever possible any changes that are in progress or will be in progress by the bulk change of agent transfer date.
5 If multiple SMRA’s affected by the bulk change of agent, a separate form must be completed for each SMRA affected.