CoP | >5% of Max Value for channel | At >2% to ≤ 5% of Max Value for channel | At ≤ 2% of Max Value for channel |
1 | ± 0.30 % | ± 0.50 % | ± 1.00 % |
2 | ± 0.75 % | ± 1.00 % | ± 2.25 % |
3 | ± 1.50 % | ± 2.00 % | ± 2.50 % |
5 | ± 3.00 % | ± 4.00 % | ± 5.00 % |
A | ± 0.75 % | ± 1.00 % | ± 2.25 % |
B | ± 0.30 % | ± 0.50 % | ± 1.00 % |
C | ± 0.75 % | ± 1.00 % | ± 2.25 % |
D | ± 0.75 % | ± 1.00 % | ± 2.25 % |
E | ± 0.30 % | ± 0.50 % | ± 1.00 % |
F | ± 0.30 % | ± 0.50 % | ± 1.00 % |
G | ± 0.75 % | ± 1.00 % | ± 2.25 % |
H | ± 0.75 % | ± 1.00 % | ± 2.25 % |
I | ± 0.75 % | ± 1.00 % | ± 2.25 % |
J | ± 0.30 % | ± 0.50 % | ± 1.00 % |
K1 | ± 0.30 % | ± 0.50 % | ± 1.00 % |
K2 | ± 0.30 % | ± 0.50 % | ± 1.00 % |
N1 | ± 0.30 % | ± 0.50 % | ± 1.00 % |
Scenario No. | Scenario | Data Used |
1 | The nominated Main Metered Data from the Primary Outstation validates satisfactorily (i.e. is ‘A’ flagged) | Validated Primary Outstation Main Metered Data is used for settlement, irrespective of data which may be missing or incorrect in the Secondary Outstation. This also covers sites that have only one Outstation under a dispensation. |
2 | The Main Metered Data from the Primary Outstation is either missing or fails validation but three out of four possible metered values (Main and Check meters in each Outstation) validate satisfactorily and agree with the other value from the precedent Outstation. | Data will be copied from the Main Meter from the Secondary Outstation and used in Settlement. This will be carried out automatically. The relevant BSC Party will be notified but their agreement will not be sought. |
3 | The Primary Outstation Data is either missing or incorrect, but the Secondary Main and Check validates satisfactorily. | Data will be copied from the Main Meter from the Secondary Outstation and used in Settlement. This will be carried out automatically. The relevant BSC Party will be notified but their agreement will not be sought. |
4 | The Main Metered Data is missing or incorrect in both Outstations, but the Check Metered Data in each Outstation validates against each other. | A Data Substitution will be performed using the Check Metered Data. Agreement to use this data will be sought from the relevant BSC Party and the data will be flagged as ‘estimated’. |
5 | The Main Metered Data is missing or incorrect in both Outstations, and the Check Metered Data in each Outstation does not validate satisfactorily. | A data estimation will be carried out using the Check Metered Data. Agreement to use this data will be sought from the relevant BSC Party and the data will be flagged as ‘estimated’. |
CDCA | Central Data Collection Agent |
CoP | Code of Practice |
CVA | Central Volume Allocation |
DCE | Demand Control Event |
GSP | Grid Supply Point |
II | Interim Information |
LDSO | Licensed Distribution System Operator |
MOA | Meter Operator Agent |
MSID | Metering System Identifier |
MAR | Meter Advance Reconciliation |
MSN | Meter Serial Number |
NETSO | National Electricity Transmission System Operator |
SMRS | Supplier Meter Registration Service |
SD | Settlement Day |
WD | Working Day |
Non Owner Party | A Non Owner Party is a Party to the BSC whose metered data is determined from a meter that is not registered by that Party. Where there is a difference metering arrangement where a Party’s data is calculated by a netting relationship, the Party should receive data for the minority circuit which is netted off their data. This type of relationship is generally where there is shared, bulk supply point metering, inter GSP Group circuits and embedded Generating Plants. |
REF | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
3.1.1 | SD+1WD | Send Raw Metered Data Report. | CDCA | Registrant and LDSO and/or NETSO and/or Non Owner Party | Raw Metered Data Report (CDCA-I012) | Electronic |
3.1.2 | By II Run | Send a Metering Status Exception Report and Meter Status Report. | CDCA | Registrant/ MOA and/or Non Owner Party (Distributors) | Metering Status Exception Report (CDCA-I010), Meter Status Report (CDCA-I054) and Reporting Metering System Reports (CDCA-I038), where appropriate, as defined in Section 1.6 | Electronic (for CDCA-I010 & CDCA-I054) Fax / Email (for CDCA-I038) |
3.1.3 | By II Run or when required | Provide all information as may be required by the CDCA to assist in the retrieval of data where possible or in the preparation of a data estimate. | Registrant or MOA | CDCA | Reason for missing data, whether data is available etc. | Fax / Email |
3.1.4 | By SD+5WD By II Run or when necessary | Provide an estimation of the metered data with reference to section 1.7, including the reason code. | CDCA | Registrant, MOA | BSCP03/4.1, Authorisation Form for Estimation and Data Substitution (Part A) BSCP03/4.2, Data Estimation /Substitution Sheet (CDCA-I037) | Fax / Email
|
3.1.5 | By II+3WD or prior to Settlement Run | Agree or disagree the estimated or substituted values. | Registrant | CDCA | BSCP03/4.1 (Part B), Authorisation form for Estimation and Data Substitution Signed by an authorised person, registered via BSCP38 | Fax / Email |
3.1.6 | By SD+13WD | Where a Registrant disagrees with the estimated or substituted values they may submit their own data for consideration. | Registrant | CDCA | BSCP03/4.2, Data Estimation/Substitution Sheet. | Fax / Email. |
3.1.7 | Immediately upon detection | In the event of any occurrence likely to result in missing or suspect data the CDCA shall be informed as soon as possible. | Registrant or MOA | CDCA | Identifier of affected equipment such as site name, circuit name, MSID, metering subsystem ID, register ID and MSN(s), the nature of the fault and Settlement Days affected, all via a Reporting Metering System Faults flow (CDCA-I015). | Fax / Email. |
3.1.8 | Immediately upon being informed of 3.1.7 | The CDCA will investigate and resolve any issues reported. | CDCA | Relevant Parties | Details of issues and methods of resolution. | Fax / Email. |
3.1.9 | By SD+13WD | Where the CDCA agrees with the Registrant’s own data, the CDCA shall submit data to Settlement and send confirmation to the Registrant. | CDCA | Registrant |
| Fax / Email. |
3.1.10 | By SD+13WD | Where the CDCA disagrees with the Registrant’s own data, the CDCA shall use original estimated data in the Initial Settlement Run and refer to the Registrant for discussion and attempt to reach agreement in time for the next Reconciliation Run. Where the CDCA and the Registrant cannot agree an estimate, the Registrant can invoke the disputes procedure. | CDCA | Registrant |
| Phone / Fax / Email. |
3.1.11 | By SD+13WD | Notify the Non-Owner Party that the estimate has been agreed by the Registrant and input into Settlements for the Initial Settlement Run or, if appropriate, that the Registrant has rejected the estimated data and that the disputes procedure has been invoked. | CDCA | Non-Owner Party | BSCP03/4.1 (Part A), Authorisation Form for Estimation and Data Substitution BSCP03/4.2, Data Estimation/Substitution Sheet | Fax / Email |
3.1.12 | Daily as required and after all estimation has been completed for that day | Send Estimated Data Report. | CDCA | Relevant Parties, BSCCo (upon request) | Estimated Data Report (CDCA I0-14), giving details of all data estimations for the relevant Metering Systems processed by CDCA on that calendar day | Electronic |
REF | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
3.2.1 | From SF - 1 WD and immediately upon detection but no later than RF - 60 WD3 | In the event of any occurrence likely to result in suspect data, the CDCA shall be informed as soon as possible. | MOA or any Party | CDCA | Identifier of affected equipment such as site name, circuit name, MSID, metering subsystem ID, register ID and MSN(s), the nature of the fault and Settlement Days affected, all via a Reporting Metering System Faults flow (CDCA-I015). | Fax / Email. |
3.2.2 | No later than RF – 52WD | The CDCA will investigate and resolve any issues reported. | CDCA | Relevant Parties | Details of issues and methods of resolution | Fax / Email. |
3.2.3 | Within 1 WD of resolving issue in 3.2.2 | If applicable provide an estimation of the metered data with reference to section 1.7. | CDCA | Registrant | BSCP03/4.1, Authorisation Form for Estimation and Data Substitution (Part A) BSCP03/4.2, Data Estimation / Substitution Sheet (CDCA_I037) | Fax / Email |
3.2.4 | Within 5 WD of receiving an estimation/ substitution report | Agree or disagree the estimated or substituted values. | Registrant | CDCA | BSCP03/4.1 (Part B) Authorisation form for Estimation and Data Substitution signed by an Authorised person registered via BSCP38 | Fax / Email |
3.2.5 | Following 3.2.4 and no later than RF – 46 WD | Where the CDCA and Registrant agree with the estimation, the CDCA shall submit estimated data to Settlement and send confirmation to the Registrant. | CDCA | Registrant |
| Fax / Email. |
3.2.6 | Following 3.2.4 and no later than RF – 46 WD | Where a Registrant disagrees with the estimated or substituted values they may submit their own data for consideration. | Registrant | CDCA | BSCP03/4.2, Data Estimation/Substitution Sheet. | Fax / Email. |
3.2.7 | Following 3.2.4 and no later than RF – 46 WD | Where the CDCA and Registrant disagree with the estimation, the CDCA shall use its own estimated data in the next Reconciliation Run and refer to the Registrant for discussion and attempt to reach agreement. Where the CDCA and the Registrant cannot agree an estimate, the Registrant can invoke the disputes procedure. Any disputes must be submitted according to the procedures and timescales as set out in BSCP11. | CDCA | Registrant |
| Phone / Fax / Email. |
3.2.8 | Following 3.2.4 or 3.2.7 and no later than RF - 41 WD | Where applicable, notify the Non-Owner Party that the estimate has been agreed by the Registrant and input into Settlements for subsequent Settlement Run or, if appropriate, that the Registrant has rejected the estimated data. | CDCA | Non-Owner Party | BSCP03/4.1 (Part A), Authorisation Form for Estimation and Data Substitution BSCP03/4.2, Data Estimation/Substitution Sheet | Fax / Email |
3.2.9 | Monthly as required (for BSCCo) | Send Estimated Data Report. | CDCA | Relevant Parties, BSCCo (upon request) | Estimated Data Report (CDCA-I014), giving details of all data estimations for the relevant Metering Systems over the past month. | Electronic |
REF | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
3.3.1 | Within 20 WD following the day on which the operational switching was carried out | If a Party believes an error has occurred in Trading Charges as a result of the CDCA not applying the Aggregation Rules for a Switching Group until midnight following the time of the change, the Lead Party may request that the error is corrected. | Lead Party | BSCCo | - Copy of aggregation rule change request; - Reason why trading volumes are incorrect; and - Proposed correct trading volumes | Fax / Email. |
3.3.2 | Following 3.3.1 | ELEXON confirms the validity of the correction request by assessing the following criteria: - there is an impact on the Party’s trading charges for the affected Settlement Periods; and - the request was made for a valid registered set of Aggregation Rules. | BSCCo | Relevant Party |
| Fax / Email. |
3.3.3 | Following confirmation that the data correction request is invalid 4 | Notify Party of decision. | BSCCo | Relevant Party | Reason for judgement that the application is invalid | Fax / Email. |
3.3.4 | Following 3.3.2 and no later than 2 WD after the validation | Where the data correction request has been confirmed to be valid, authorise CDCA to correct data. | BSCCo | CDCA |
| Fax / Email. |
3.3.5 | Within 2 WD of 3.3.4 | Notify Party of whether criteria are met. | CDCA | BSCCo |
| Fax / Email. |
3.3.6 | At the same time as 3.3.5 | Notify relevant Party of data correction outcome. | CDCA/BSCCo | Relevant Party |
| Fax / Email. |
REF | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
3.4.1 | Within the period of 1WD commencing on the Business Day after the BMRA receives the data from the NETSO specified in Section Q6.9.5 | Notice of the DCE sent to all Category A Authorised Persons, to establish the appropriate operational contact. The Category A Authorised Persons will be used as the contact unless another contact is provided | BSCCo | Category A Authorised Persons from BSC Parties and Party Agents | Notice of the DCE | Email or other method, as agreed. |
3.4.2 | Within the period of 1WD commencing on the Business Day after the BMRA receives the data from the NETSO specified in Section Q6.9.5 | BSCCo will assess the costs and value of the DCE in accordance with the Demand Disconnection Event Threshold Rules and notify BSC Parties, Party Agents and BSC Panel Members of the outcome of its assessment | BSCCo | BSC Parties, Party Agents and BSC Panel | Notice of the outcome of BSCCo assessment | Email, Circular, BSC Website |
3.4.3 | Within 5WD of 3.4.2 | Notify CDCA of Demand Control event and all disconnected Embedded BM Units | LDSO | CDCA | CDCA-I067 Disconnected BM Units affected by Demand Control Event | |
3.4.4 | Within 5WD of 3.4.2 | Notify CDCA of Demand Control event and all disconnected Directly-Connected BM Units | NETSO | CDCA | CDCA-I067 Disconnected BM Units affected by Demand Control Event | |
3.4.5 | Within 1 WD of 3.4.3 or 3.4.4 | Forward details of Disconnected BM Units to BSCCo | CDCA | BSCCo | CDCA-I067 Disconnected BM Units | |
3.4.6 | Within 2 WDs of 3.4.5 | Estimate BM Unit Demand Disconnection Volume(s) in accordance with Appendix 4.7 for each affected BMU and impacted Settlement Period Send estimates of Demand Disconnection Volume(s) to Registrant | BSCCo
BSCCo |
Registrant |
BSCP03/4.3 Estimated Demand Control Volume – Part 1 form | Internal
|
3.4.7 | Within 3WDs of 3.4.6 | Agree or disagree the estimated values Where the Registrant disagrees with the estimated values, they may submit their own for consideration | Registrant | BSCCo | BSCP03/4.3 Estimated Demand Control Volume – Part 1 form, signed by an Authorised person registered via BSCP38 And BSCP03/4.4 Demand Disconnection Volume Data Estimation/Substitution Sheet | |
3.4.8 | Following 3.4.7 and at least 1 WD prior to next Settlement Run | Where the Registrant agrees with the BSCCo’s estimate(s), the BSCCo will confirm to the Registrant which estimates it will submit and will submit those estimate(s) to the CDCA CDCA shall submit the estimated data to Settlement and send confirmation to the Registrant and BSCCo | BSCCo
BSCCo
CDCA | Registrant
CDCA
SAA
BSCCo and Registrant | BSCP03/4.3 Estimated Demand Control Volume – Part 1 form BSCP03/4.5 Estimated Demand Control Volume – Part 2 form CDCA-I068 Aggregated BM Unit Disconnection Volumes BSCP03/4.5 Estimated Demand Control Volume – Part 2 form |
Via shared database
|
3.4.9 | Following 3.4.7 and at least 1 WD prior to next Settlement Run | Should BSCCo agree with the Registrant’s alternative estimate(s), BSCCo will confirm the use of the alternative estimate(s) with the Registrant and send these to CDCA. Otherwise the BSCCo shall submit its own estimated data to the CDCA for use in the next Settlement Run and confirm this to the Registrant. The CDCA shall submit the estimated data to Settlement and send confirmation to the Registrant and BSCCo | BSCCo
BSCCo
CDCA | Registrant
CDCA
SAA BSCCo and Registrant | BSCP03/4.3 Estimated Demand Control Volume – Part 1 form BSCP03/4.5 Estimated Demand Control Volume – Part 2 form
CDCA-I068 Aggregated BM Unit Disconnection Volumes BSCP03/4.5 Estimated Demand Control Volume – Part 2 form |
Via shared database
|
3.4.10 | Following 3.4.7 | Where the BSCCo disagrees with an estimate provided to it by the Registrant, BSCCo will contact the Registrant to discuss and attempt to reach agreement. Where the BSCCo and the Registrant cannot agree an estimate, the Registrant can invoke the disputes procedure. Any disputes must be submitted according to the procedures and timescales as set out in BSCP11. | BSCCo | Registrant |
|
PART A To Registrant Ref. No: Details to be included: MSN: Registrant: Metering Subsystem ID: Non-Owner Party: MSID: Register ID: Affected dates and times: to: Reason Code used for Estimation/Substitution: Reasons for Estimation/Substitution and origin of data: Signed: Name: Date: (For CDCA) NOTE: ALL ESTIMATIONS/SUBSTITUTIONS ARE CLOCK TIME |
PART B To CDCA I hereby agree/disagree* with the Estimated/Substituted* data submitted with this form and authorise/do not authorise* the use of such data for the date and times detailed in PART A above. [*delete as appropriate] Reasons for disagreement to be provided on separate attached sheet. Name: Password:........................... Signed: Date: (For Registrant)
BSC Party ID: |
PART C From CDCA to Registrant I hereby confirm that the Estimated/Substituted data associated with the above Reference No. detailed in Part A/B* has been entered into Settlements on the date detailed below. *Delete as appropriate Input by: Signed: Name: Date:.................... Checked by: Signed: Name: Date:.................... (For CDCA) |
BSC Party ID |
| MSID: |
| Outstation ID: |
| Originator: |
| Date: |
|
| Channel No. |
|
|
|
|
|
|
| ||||
|
| MWh |
|
| MWh |
|
| MWh | ||||
Settlement | Original | Data Estimate | Party supplied | Settlement | Original | Data Estimate | Party supplied | Settlement | Original | Data Estimate | Party supplied | |
Period | Data | by BSC Agent | Estimate | Period | Data | by BSC Agent | Estimate | Period | Data | by BSC Agent | Estimate | |
1 |
|
|
| 19 |
|
|
| 37 |
|
|
| |
2 |
|
|
| 20 |
|
|
| 38 |
|
|
| |
3 |
|
|
| 21 |
|
|
| 39 |
|
|
| |
4 |
|
|
| 22 |
|
|
| 40 |
|
|
| |
5 |
|
|
| 23 |
|
|
| 41 |
|
|
| |
6 |
|
|
| 24 |
|
|
| 42 |
|
|
| |
7 |
|
|
| 25 |
|
|
| 43 |
|
|
| |
8 |
|
|
| 26 |
|
|
| 44 |
|
|
| |
9 |
|
|
| 27 |
|
|
| 45 |
|
|
| |
10 |
|
|
| 28 |
|
|
| 46 |
|
|
| |
11 |
|
|
| 29 |
|
|
| 47 |
|
|
| |
12 |
|
|
| 30 |
|
|
| 48 |
|
|
| |
13 |
|
|
| 31 |
|
|
| 49 |
|
|
| |
14 |
|
|
| 32 |
|
|
| 50 |
|
|
| |
15 |
|
|
| 33 |
|
|
| 51 |
|
|
| |
16 |
|
|
| 34 |
|
|
| 52 |
|
|
| |
17 |
|
|
| 35 |
|
|
|
|
|
|
| |
18 |
|
|
| 36 |
|
|
|
|
|
|
|
PART A |
From BSCCo To Registrant |
Ref No: _________________ | ||||||
Details to be included: | ||||||||
BM Unit ID: ____________________ | Registrant: ___________________________________ | |||||||
Estimate of Demand Disconnection Volumes: |
|
| ||||||
Settlement Date:___________ | Settlement Period: _____ | Volume: _______ MWh | ||||||
Settlement Date:___________ | Settlement Period: _____ | Volume: _______ MWh | ||||||
Settlement Date:___________ | Settlement Period: _____ | Volume: _______ MWh | ||||||
Settlement Date:___________ | Settlement Period: _____ | Volume: _______ MWh | ||||||
Settlement Date:___________ | Settlement Period: _____ | Volume: _______ MWh | ||||||
Settlement Date:___________ | Settlement Period: _____ | Volume: _______ MWh | ||||||
Settlement Date:___________ | Settlement Period: _____ | Volume: _______ MWh | ||||||
| ||||||||
Signed: ______________________ (Part A is for BSCCo to complete) | Name: ___________________ | Date: ______________ | ||||||
PART B |
From Registrant To BSCCo | |||||||
I hereby agree/disagree* with the Estimated Demand Disconnection Volumes submitted with this form and authorise/do not authorise* the use of such data for the date and times detailed in PART A above. [*delete as appropriate] The Registrant shall attach its reasons for disagreement and any alternative calculation(s) using the BSCP03/4.4 form. | ||||||||
Name: _____________________________ | Password: ______________________________ | |||||||
Signed: ____________________________ | Date: __________________________________ | |||||||
BSC Party ID: ____________________________________________________________________________ | ||||||||
(Part B is for the Registrant to complete) | ||||||||
PART C |
From BSCCo To Registrant | |||||||
I hereby confirm that the Estimated/Substituted data associated with the above Reference No. detailed in Part A/B* has been submitted to the CDCA for entry into Settlements on the date detailed below. | ||||||||
Name: __________________________ | Signed: ____________________ | Date: _________________ | ||||||
Job Title: _______________________ (Part C is for BSCCo to complete) |
|
|
BSC Party ID |
| BMU ID: |
| Originator: |
| Date: |
|
|
| MWh |
|
| MWh |
|
| MWh | |||||
Settlement | Original | Data Estimate | Party supplied | Settlement | Original | Data Estimate | Party supplied | Settlement | Original | Data Estimate | Party supplied | ||
Period | Data | by BSC Agent | Estimate | Period | Data | by BSC Agent | Estimate | Period | Data | by BSC Agent | Estimate | ||
1 |
|
|
| 19 |
|
|
| 37 |
|
|
| ||
2 |
|
|
| 20 |
|
|
| 38 |
|
|
| ||
3 |
|
|
| 21 |
|
|
| 39 |
|
|
| ||
4 |
|
|
| 22 |
|
|
| 40 |
|
|
| ||
5 |
|
|
| 23 |
|
|
| 41 |
|
|
| ||
6 |
|
|
| 24 |
|
|
| 42 |
|
|
| ||
7 |
|
|
| 25 |
|
|
| 43 |
|
|
| ||
8 |
|
|
| 26 |
|
|
| 44 |
|
|
| ||
9 |
|
|
| 27 |
|
|
| 45 |
|
|
| ||
10 |
|
|
| 28 |
|
|
| 46 |
|
|
| ||
11 |
|
|
| 29 |
|
|
| 47 |
|
|
| ||
12 |
|
|
| 30 |
|
|
| 48 |
|
|
| ||
13 |
|
|
| 31 |
|
|
| 49 |
|
|
| ||
14 |
|
|
| 32 |
|
|
| 50 |
|
|
| ||
15 |
|
|
| 33 |
|
|
|
|
|
|
| ||
16 |
|
|
| 34 |
|
|
|
|
|
|
| ||
17 |
|
|
| 35 |
|
|
|
|
|
|
| ||
18 |
|
|
| 36 |
|
|
|
|
|
|
|
PART A |
From BSCCo To CDCA |
Ref No: _________________ | |||||
Details to be included: | |||||||
BM Unit ID: ____________________ | Registrant: ___________________________________ | ||||||
Estimate of Demand Disconnection Volumes: |
|
| |||||
Settlement Date:___________ | Settlement Period: _____ | Volume: _______ MWh | |||||
Settlement Date:___________ | Settlement Period: _____ | Volume: _______ MWh | |||||
Settlement Date:___________ | Settlement Period: _____ | Volume: _______ MWh | |||||
Settlement Date:___________ | Settlement Period: _____ | Volume: _______ MWh | |||||
Settlement Date:___________ | Settlement Period: _____ | Volume: _______ MWh | |||||
Settlement Date:___________ | Settlement Period: _____ | Volume: _______ MWh | |||||
Settlement Date:___________ | Settlement Period: _____ | Volume: _______ MWh | |||||
Signed: (Part A is for BSCCo to complete) | Name: ___________________ | Date: ______________
| |||||
PART B | From CDCA To BSCCo and Registrant | ||||||
I hereby confirm that the Estimated data associated with the above Reference No. detailed in Part A has been submitted to the CDCA for entry into Settlements on the date detailed below. | |||||||
Input By: __________________________ | Signed: ____________________ | Date: _________________ | |||||
Checked By: _______________________ (Part B is for CDCA to complete) | Signed: ____________________ | Date: _________________ |
Method Code | Reason for Estimation/Substitution | Method Used |
A | Generation: Main Metered Data missing or incorrect in Primary and Secondary Outstations, Check Metered Data available | Copied from Primary Check |
K | Generation: Main and Check Metered Data missing or incorrect in Primary and Secondary Outstations, data estimated to zero awaiting confirmation of generation | Manual Estimate to zero |
D | Demand: Main Metered Data missing or incorrect, Check Metered Data available | Copied from Primary Check |
E | Demand: Main Metered Data missing or incorrect, Check meter not fully functional, but Main or Check meter register advance available | Profile using Meter Reading Estimation Tool |
M | Demand: Main Metered Data missing or incorrect, data copied from suitable settlement day | Manual Estimate |
I | Demand: Main Metered Data missing or incorrect, Check meter not fully functional, Check meter register advance NOT available | Profile using Trend |
J | Generation: Main meter data missing or incorrect in Primary Outstation, Secondary Outstation Main meter data available | Substituted from Secondary Main |
L | Demand: Main meter data missing or incorrect, Secondary Outstation Main meter data available | Substituted from Secondary Main |
N | Validation Failure: Main data deemed correct | Quality Promoted |
U | Parties’ own readings used | Manual Estimate |
X | Other estimation method used | Manual Estimate |
VERSION | DATE | DESCRIPTION OF CHANGES | CRs INCLUDED | MODS/PANEL REF |
1.0 | Code Effective Date | Designated Version | n/a | n/a |
2.0 | 11/01/01 | Work outstanding at Go Active resolution of inclusion of consultation comments | 214 & 217 | 10/005 |
3.0 | 13/08/2002 | Change Proposals for BSC Systems Release 2 | CP563 | ISG 16/166 |
4.0 | 10/12/2002 | CDCA Improvement Project & December 02 Release CPs | CP511, CP751 |
|
5.0 | 24/06/2003 | Change Proposals for June 03 Release | CP747, CP841 |
|
6.0 | 01/08/2003 | Approved Modification P62 | P62 | P62 48/003 |
7.0 | 30/06/2004 | Change Proposal for the CVA Programme June 04 Release | CP988 | ISG/40/003 |
8.0 | 03/11/2004 | Change Proposal for the CVA Programme Nov 04 Release | CP1032 | TDC/58/03 |
9.0 | BETTA Effective Date | BETTA 6.3 rebadging for the CVA Feb 05 Release | BETTA 6.3 |
|
10.0 | 28/06/06 | June 06 Release | P190 | ISG/64/001 |
11.0 | 06/11/08 | November 08 Release | CP1245 | ISG89/01 |
12.0 | 27/01/10 | Modification P240 | P240 | Panel |
13.0 | 05/11/15 | November 15 Release | P305 | ISG172/04 |
14.0 | 29/03/19 | 29 March 2019 Standalone Release | P369 | P285/12 |
15.0 | 12/10/20 | P397 Standalone Release | P397 | P298/05 |
16.0 | 03/11/22 | November 03 2022 Release | CP1660 | ISG253/05,SVG255/04 |
17.0 | 29/06/23 | June 29 2023 Release | CP1580 | P338/04 |
18.0 | 01/10/2024 | 01 October Non-Standard Release | ORD009 | Directed by the Secretary of State |
Intellectual Property Rights, Copyright and Disclaimer The copyright and other intellectual property rights in this document are vested in Elexon or appear with the consent of the copyright owner. These materials are made available for you for the purposes of your participation in the electricity industry. If you have an interest in the electricity industry, you may view, download, copy, distribute, modify, transmit, publish, sell or create derivative works (in whatever format) from this document or in other cases use for personal academic or other non-commercial purposes. All copyright and other proprietary notices contained in the document must be retained on any copy you make. All other rights of the copyright owner not expressly dealt with above are reserved. No representation, warranty or guarantee is made that the information in this document is accurate or complete. While care is taken in the collection and provision of this information, Elexon Limited shall not be liable for any errors, omissions, misstatements or mistakes in any information or damages resulting from the use of this information or action taken in reliance on it. |
1 Where there is no Code of Practice defined by the Registrant, CoP 1 values shall be applied.
2 Please note that any disputes procedure invoked must be done so according to the timescales and procedures as set out in BSCP11 – Trading Queries and Trading Disputes.
3 For any data prior to SF identified as being suspect, the processes described in 3.1 should be followed.
4 Party can raise a Trading Dispute if they are unsatisfied with the outcome.