Commissioning of measurement transformers for
Settlement
purposes (
Code
of Practice
4)
Background
Process
Scenarios
Scenario 1
LDSO
/
NETSO
Process
MOA Process
Registrant process
Scenario 2
LDSO
Process
MOA Process
Registrant process
Scenario 3
System
Operator Process
MOA Process
Registrant process
Scenario 4
LDSO
Process
MOA Process
Registrant process
Scenario 5
LDSO
Process
MOA Process
Registrant process
Scenario 6
MOA Process
Registrant process
Sample Measurement Transformers Commissioning Record
Risk Matrix
Process flow diagram
Further Information?
Commissioning Measurement Transformers Code of Practice four V7.0
Effective From Date:
22/09/2025
Status:
LIVE
Other versions
Download
Defined Terms
Cross-references