Balancing and Settlement Code
Half Hourly Instruction Processing Specification
Version
Effective Date:
|
Intellectual Property Rights, Copyright and Disclaimer The copyright and other intellectual property rights in this document are vested in Elexon or appear with the consent of the copyright owner. These materials are made available for you for the purposes of your participation in the electricity industry. If you have an interest in the electricity industry, you may view, download, copy, distribute, modify, transmit, publish, sell or create derivative works (in whatever format) from this document or in other cases use for personal academic or other non-commercial purposes. All copyright and other proprietary notices contained in the document must be retained on any copy you make. All other rights of the copyright owner not expressly dealt with above are reserved. No representation, warranty or guarantee is made that the information in this document is accurate or complete. While care is taken in the collection and provision of this information, Elexon Limited shall not be liable for any errors, omissions, misstatements or mistakes in any information or damages resulting from the use of this information or action taken in reliance on it. |
Metering System identifiers are associated with a Distribution Business such that it appears to the system that Metering Systems can never change Distribution Businesses;
the appointment of PRS Agents is to a Distribution Business and not to a GSP Group;
the subject of a refresh of data from a PRS Agent is a Distribution Business;
instruction file sequence numbers are unique and sequential between source and target;
instruction sequence numbers are unique and sequential between source and target.
explains the terms “relevant relationship”, “relevant relationship change” and “significant date”;
describes the use, input/output structure, content and update processing of each instruction type;
describes instructions life cycle processing.
define what relationships are relevant to a HH Data Aggregator;
define what changes to these relationships constitute a change that the HH Data Aggregator must be informed about;
provide a method for ensuring the instruction production logic is consistent with the instruction processing logic.
the HH Data Aggregator’s Data Aggregator Appointments for the Metering System;
the Registrations that any of these Data Aggregator Appointments are for;
the Data Collector Appointments that are for any of these Registrations;
the Measurement Class in Registrations and Energisation Status in Registrations that are for any of these Registrations and overlap with any of the HH Data Aggregator’s Data Aggregator Appointments for the Metering System;
the Metering System Line Loss Factor Classes and Metering System GSP Groups that overlap with any of the HH Data Aggregator’s Data Aggregator Appointments for the Metering System;
the Half Hourly Period Metered Consumptions for the Metering System that overlap with any of the HH Data Aggregator’s Data Aggregator’s Appointments for the Metering System;
is relevant to the HH Data Aggregator post the change taking place; and/or
was relevant to the HH Data Aggregator prior to the change taking place.
for relationship types without explicit end dates, it is the start date prior to the change or the start date post the change, whichever is the earlier;
for relationship types with explicit end dates:
it is the end date prior to the change or the end date post the change, whichever the earlier - if it is only the end date that has changed;
it is the start date prior to the change or the start date post the change, whichever the earlier - if data other than the end date has changed.
begin on or after the significant date; or
begin prior to the significant date and there is no Data Collector Appointment for the same registration with a start date that is both after the start date of the Data Aggregator Appointment being considered and on or prior to the significant date.
the PRS Agent who sent the instruction is currently appointed to the Distribution Business associated with the Metering System;
applying the instruction will not result in any of the Metering System’s registrations being without a Data Collector Appointment, Measurement Class or Energisation Status at any time during any of its Data Aggregator Appointments;
applying the instruction will not result in the Metering System being without a GSP Group or Line Loss Factor Class at any time during any of its Data Aggregator Appointments;
there is not an existing Data Aggregator Appointment which:
is not contained in the instruction; and
begins prior to the significant date and either doesn’t end or ends on or after the significant date.
the content of the instruction is consistent with the collation logic.
In order to cater for PRS developments which, because of timescale pressures, cannot support creation of a Data Aggregator Appointment Details instruction as specified when a previously open ended Data Aggregator Appointment has its Effective To Settlement Date set, the following dedicated processing is included. It should be noted that this processing is not considered as part of the instruction processing specification. |
If: |
|
|
|
set the Effective To Settlement Date of the Data Aggregator Appointment to the significant date, and do not perform the usual update processing. Delete any relationships of the following type for the Metering System which start after the significant date:
|
Measurement Class;
Energisation Status;
Registration and their Data Collector Appointments;
Line Loss Factor Class;
GSP Group.
Registration;
Data Aggregator Appointment;
Data Collector Appointment;
Measurement Class;
Energisation Status;
Line Loss Factor Class;
GSP Group.
begin on or after the significant date; or
begin prior to the significant date and there is no Data Collector Appointment for the same registration with a start date that is both after the start date of the Data Aggregator Appointment being considered and on or prior to the significant date.
the PRS Agent who sent the instruction is currently appointed to the Distribution Business associated with the Metering System;
the registration for each Data Collector Appointment relationship in the instruction already exists;
applying the instruction will not result in any of the Metering System’s registrations being without a Data Collector Appointment at any time;
the content of the instruction is consistent with the collation logic.
the PRS Agent who sent the instruction is currently appointed to the Distribution Business associated with the Metering System;
the registration for each Measurement Class relationship in the instruction already exists;
applying the instruction will not result in any of the Metering System’s registrations being without a Measurement Class at any time during a Data Aggregator Appointment;
the content of the instruction is consistent with the collation logic stated above in c.
the PRS Agent who sent the instruction is currently appointed to the Distribution Business associated with the Metering System;
the registration for each Energisation Status relationship in the instruction already exists;
applying the instruction will not result in any of the Metering System’s registrations being without an Energisation Status at any time during a Data Aggregator Appointment;
the content of the instruction is consistent with the collation logic.
the PRS Agent who sent the instruction is currently appointed to the Distribution Business associated with the Metering System;
applying the instruction will not result in the Metering System being without a GSP Group at any time during any of its Data Aggregator Appointments;
the content of the instruction is consistent with the collation logic.
the PRS Agent who sent the instruction is currently appointed to the Distribution Business associated with the Metering System;
applying the instruction will not result in the Metering System being without a Line Loss Factor Class at any time during any of its Data Aggregator Appointments;
the content of the instruction is consistent with the collation logic.
the PRS Agent who sent the instruction is currently appointed to the Distribution Business associated with the Metering System;
applying the instruction will not result in any of the Metering System’s registrations being without a Data Collector Appointment, Measurement Class or Energisation Status at any time during any of its Data Aggregator Appointments;
applying the instruction will not result in the Metering System being without a GSP Group or Line Loss Factor Class at any time during any of its Data Aggregator Appointments;
the content of the instruction is consistent with the collation logic.
Measurement Class;
Energisation Status;
Registration and their Data Collector Appointments;
Line Loss Factor Class;
GSP Group.
Registration;
Data Aggregator Appointment;
Data Collector Appointment;
Measurement Class;
Energisation Status;
Line Loss Factor Class;
GSP Group.
Measurement Class;
Energisation Status;
Registration and their Data Collector Appointments;
Line Loss Factor Class;
GSP Group.
a problem on the part of the HH Data Aggregator;
a problem on the part of the source;
a transmission problem.
resolves the problem;
generates a revised file containing all instructions required to rectify the situation bearing in mind that the erroneous file and any subsequent files sent are void;
advises the HH Data Aggregator of the file sequence number of the revised file;
sends the revised file to the HH Data Aggregator.
unprocessed;
applied;
failed;
superseded;
discarded.
have a significant date on or after the significant date of the applied instruction;
are for a Metering System associated with the Distribution Business in the applied instruction;
are either:
from the same PRS Agent as the applied instruction and have an instruction sequence number less than that of the applied instruction; or
from a different PRS Agent than the applied instruction and this different PRS Agent does not have a future appointment to the Distribution Business.
have a significant date on or after the significant date of the applied instruction;
are for the same Metering System;
are either:
from the same PRS Agent as the applied instruction and have an instruction sequence number less than that of the applied instruction; or
from a different PRS Agent than the applied instruction and this different PRS Agent does not have a future appointment to the Metering System’s Distribution Business.
have a significant date on or after the significant date of the applied instruction;
are for the same Metering System;
are either:
from the same PRS Agent as the applied instruction and have an instruction sequence number less than that of the applied instruction; or
from a different PRS Agent than the applied instruction and this different PRS Agent does not have a future appointment to the Metering System’s Distribution Business.
are of the same instruction type as the applied instruction.
the Metering System identifier;
the instruction number;
instruction type;
instruction source;
latest processing attempt date/time;
the reasons for failure/discard encountered in the latest processing attempt;
whether the HH Data Aggregator is able resolve each reason for failure/discard;
whether each reason for failure/discard that the HH Data Aggregator is able to resolve has been resolved;
whether the HH Data Aggregator wants the instruction to be reprocessed (only allowed when valid);
whether the HH Data Aggregator wants data in the instruction to be resent by the appropriate PRS Agent (only allowed for failed instructions);
whether the PRS Agent has been asked to resend data in the instruction since the latest processing attempt and if so when the request was issued to them.
failed Data Aggregator Appointment Details instructions from a PRS Agent where:
no subsequent instructions for the Metering System and from the same PRS Agent have been applied; and
no subsequent PRS Refresh instructions for the Distribution Business associated with the Metering System and from the same PRS Agent have been applied;
other failed instructions from a PRS Agent where:
no subsequent instructions of the same type for the Metering System and from the same PRS Agent have been applied; and
no subsequent Data Aggregator Appointment Details instructions for the Metering System and from the same PRS Agent have been applied; and
no subsequent PRS Refresh instructions for the Distribution Business associated with the Metering System and from the same PRS Agent have been applied;
discarded PRS Refresh instructions from a PRS Agent where:
no subsequent PRS Refresh instructions for the Distribution Business and from the same PRS Agent have been applied; and
no subsequent instructions for any Metering Systems associated with the Distribution Business and from the same PRS Agent have been applied.
the Metering System identifier;
the earliest significant date across the set of failed instructions that:
are for the Metering System; and
are from a PRS Agent; and
the HH Data Aggregator wants data resent for;
the instruction number and its reasons for failure which the HH Data Aggregator cannot resolve for all failed instructions that:
are for the Metering System; and
are from a PRS Agent; and
the HH Data Aggregator has requested a resend of data for.
Data Group | Data Items |
Data Aggregator Appointment Details | Effective From Settlement Date {DAA} Effective To Settlement Date {DAA} |
Data Collector Appointment Details | Data Collector Id Effective From Date {DCA} |
Energisation Status Details | Energisation Status Effective From Settlement Date {ESR} |
GSP Group Details | GSP Group Id Effective From Settlement Date {MSGG} |
Line Loss Factor Class Details | Distributor Id Line Loss Factor Class Id Effective From Settlement Date {MSLLFC} |
Measurement Class Details | Measurement Class Id Effective From Settlement Date {MCR} |
Registration Details | Supplier Id |
Registration Identifier | Effective From Settlement Date {REGI} |
all the details shown are included in the same instruction. This is important in the case of the Data Aggregator Appointments where there are two sources for the PRS information which may provide the data in different timescales. Note that the Data Aggregator will fail any instructions without all the required relevant relationships;
objection processing is not considered;
the values used are in no way representative or valid examples of the data expected for each data item;
dates have been abbreviated to two digits for the year;
instruction sequence numbers are not shown in the instructions contents.
Relationship Type | From | Value |
Registration | 3 Oct 98 | S1 |
Data Aggregator Appointment | 3 Oct 98 | DA 1 |
Data Collector Appointment | 3 Oct 98 | DC 1 |
Measurement Class | 3 Oct 98 | MC 3 |
Energisation Status | 3 Oct 98 | E |
Line Loss Factor Class | 3 Oct 98 | DB1, LLF 2 |
GSP Group | 3 Oct 98 | G7 |
Instruction Type | Data Aggregator Appointment Details | ||
Metering System Id | MS200 | ||
Significant Date | 3 Oct 98 | ||
Relationship Type | Item 1 | Item 2 | Item 3 |
Registration | 3 Oct 98 | N/A | S1 |
Data Aggregator Appointment | 3 Oct 98 | 3 Oct 98 | N/A |
Data Collector Appointment | 3 Oct 98 | 3 Oct 98 | DC 1 |
Measurement Class | 3 Oct 98 | 3 Oct 98 | MC 3 |
Energisation Status | 3 Oct 98 | 3 Oct 98 | E |
Line Loss Factor Class | 3 Oct 98 | N/A | DB1, LLF 2 |
GSP Group | 3 Oct 98 | N/A | G7 |
Relationship Type | From | Value |
Registration | 3 Oct 98 | S1 |
Data Aggregator Appointment | 3 Oct 98 | DA 1 |
Data Collector Appointment | 3 Oct 98 | DC 1 |
Measurement Class | 3 Oct 98 | MC 3 |
Energisation Status | 3 Oct 98 | E |
Line Loss Factor Class | 3 Oct 98 | DB1, LLF 2 |
GSP Group | 3 Oct 98 | G7 |
Relationship Type | From | Value |
Registration | 3 Oct 98 | S1 |
Data Aggregator Appointment | 3 Oct 98 | DA 1 |
Data Collector Appointment | 3 Oct 98 | DC 1 |
Measurement Class | 3 Oct 98 | MC 3 |
Energisation Status | 3 Oct 98 | E |
Line Loss Factor Class | 3 Oct 98 | DB1, LLF 2 |
| 1 Jan 99 | DB1, LLF 5 |
GSP Group | 3 Oct 98 | G7 |
Instruction Type | Line Loss Factor Class Details | ||
Metering System Id | MS200 | ||
Significant Date | 1 Jan 99 | ||
Relationship Type | Item 1 | Item 2 | Item 3 |
Line Loss Factor Class | 1 Jan 99 | N/A | DB1, LLF 5 |
Relationship Type | From | Value |
Registration | 3 Oct 98 | S1 |
Data Aggregator Appointment | 3 Oct 98 | DA 1 |
Data Collector Appointment | 3 Oct 98 | DC 1 |
Measurement Class | 3 Oct 98 | MC 3 |
Energisation Status | 3 Oct 98 | E |
Line Loss Factor Class | 3 Oct 98 | DB1, LLF 2 |
| 1 Jan 99 | DB1, LLF 5 |
GSP Group | 3 Oct 98 | G7 |
Relationship Type | From | Value |
Registration | 3 Oct 98 | S1 |
| 1 Apr 99 | S2 |
Data Aggregator Appointment | 3 Oct 98 to 31 Mar 99 | DA 1 |
| 1 Apr 99 | DA 2 |
Data Collector Appointment | 3 Oct 98 | DC 1 |
| 1 Apr 99 | DC 1 |
Measurement Class | 3 Oct 98 | MC 3 |
| 1 Apr 99 | MC 3 |
Energisation Status | 3 Oct 98 | E |
| 1 Apr 99 | E |
Line Loss Factor Class | 3 Oct 98 | DB1, LLF 2 |
| 1 Jan 99 | DB1, LLF 5 |
GSP Group | 3 Oct 98 | G7 |
Instruction Type | Data Aggregator Appointment Details | ||
Metering System Id | MS200 | ||
Significant Date | 31 Mar 99 | ||
Relationship Type | Item 1 | Item 2 | Item 3 |
Registration | 3 Oct 98 | N/A | S1 |
Data Aggregator Appointment | 3 Oct 98 to 31 Mar 99 | 3 Oct 98 | N/A |
Data Collector Appointment | 3 Oct 98 | 3 Oct 98 | DC 1 |
Measurement Class | 3 Oct 98 | 3 Oct 98 | MC 3 |
Energisation Status | 3 Oct 98 | 3 Oct 98 | E |
Line Loss Factor Class | 1 Jan 99 | N/A | DB1, LLF 5 |
GSP Group | 3 Oct 98 | N/A | G7 |
Instruction Type | Data Aggregator Appointment Details | ||
Metering System Id | MS200 | ||
Significant Date | 31 Mar 99 | ||
Relationship Type | Item 1 | Item 2 | Item 3 |
Data Aggregator Appointment | 3 Oct 98 to 31 Mar 99 | 3 Oct 98 | N/A |
Instruction Type | Data Aggregator Appointment Details | ||
Metering System Id | MS200 | ||
Significant Date | 1 Apr 99 | ||
Relationship Type | Item 1 | Item 2 | Item 3 |
Registration | 1 Apr 99 | N/A | S2 |
Data Aggregator Appointment | 1 Apr 99 | 1 Apr 99 | N/A |
Data Collector Appointment | 1 Apr 99 | 1 Apr 99 | DC 1 |
Measurement Class | 1 Apr 99 | 1 Apr 99 | MC 3 |
Energisation Status | 1 Apr 99 | 1 Apr 99 | E |
Line Loss Factor Class | 1 Jan 99 | N/A | DB1, LLF 5 |
GSP Group | 3 Oct 98 | N/A | G7 |
Relationship Type | From | Value |
Registration | 3 Oct 98 | S1 |
Data Aggregator Appointment | 3 Oct 98 | DA 1 |
Data Collector Appointment | 3 Oct 98 | DC 1 |
Measurement Class | 3 Oct 98 | MC 3 |
Energisation Status | 3 Oct 98 | E |
Line Loss Factor Class | 3 Oct 98 | DB1, LLF 2 |
| 1 Jan 99 | DB1, LLF 5 |
GSP Group | 3 Oct 98 | G7 |
Relationship Type | From | Value |
Registration | 3 Oct 98 | S1 |
| 1 Apr 99 | S2 |
Data Aggregator Appointment | 3 Oct 98 to 31 Mar 99 | DA 1 |
| 1 Apr 99 | DA 1 |
Data Collector Appointment | 3 Oct 98 | DC 1 |
| 1 Apr 99 | DC 1 |
| 1 Apr 99 | I |
Measurement Class | 3 Oct 98 | MC 3 |
| 1 Apr 99 | MC 3 |
Energisation Status | 3 Oct 98 | E |
| 1 Apr 99 | E |
Line Loss Factor Class | 3 Oct 98 | DB1, LLF 2 |
| 1 Jan 99 | DB1, LLF 5 |
GSP Group | 3 Oct 98 | G7 |
Instruction Type | Data Aggregator Appointment Details | ||
Metering System Id | MS200 | ||
Significant Date | 31 Mar 99 | ||
Relationship Type | Item 1 | Item 2 | Item 3 |
Registration | 3 Oct 98 | N/A | S1 |
| 1 Apr 99 | N/A | S2 |
Data Aggregator Appointment | 3 Oct 98 to 31 Mar 99 | 3 Oct 98 | N/A |
| 1 Apr 99 | 1 Apr 99 | N/A |
Data Collector Appointment | 3 Oct 98 | 3 Oct 98 | DC 1 |
| 1 Apr 99 | 1 Apr 99 | DC 1 |
| 1 Apr 99 | 1 Apr 99 | I |
Measurement Class | 3 Oct 98 | 3 Oct 98 | MC 3 |
| 1 Apr 99 | 1 Apr 99 | MC 3 |
Energisation Status | 3 Oct 98 | 3 Oct 98 | E |
| 1 Apr 99 | 1 Apr 99 | E |
Line Loss Factor Class | 1 Jan 99 | N/A | DB1, LLF 5 |
GSP Group | 3 Oct 98 | N/A | G7 |
Instruction Type | Data Aggregator Appointment Details | ||
Metering System Id | MS200 | ||
Significant Date | 31 Mar 99 | ||
Relationship Type | Item 1 | Item 2 | Item 3 |
Data Aggregator Appointment | 3 Oct 98 to 31 Mar 99 | 3 Oct 98 | N/A |
Instruction Type | Data Aggregator Appointment Details | ||
Metering System Id | MS200 | ||
Significant Date | 1 Apr 99 | ||
Relationship Type | Item 1 | Item 2 | Item 3 |
Registration | 1 Apr 99 | N/A | S2 |
Data Aggregator Appointment | 1 Apr 99 | 1 Apr 99 | N/A |
Data Collector Appointment | 1 Apr 99 | 1 Apr 99 | DC 1 |
Measurement Class | 1 Apr 99 | 1 Apr 99 | MC 3 |
Energisation Status | 1 Apr 99 | 1 Apr 99 | E |
Line Loss Factor Class | 1 Jan 99 | N/A | DB1, LLF 5 |
GSP Group | 3 Oct 98 | N/A | G7 |
Relationship Type | From | Value |
Registration | 3 Oct 98 | S1 |
Data Aggregator Appointment | 3 Oct 98 | DA 1 |
Data Collector Appointment | 3 Oct 98 | DC 1 |
Measurement Class | 3 Oct 98 | MC 3 |
Energisation Status | 3 Oct 98 | E |
Line Loss Factor Class | 3 Oct 98 | DB1, LLF 2 |
| 1 Jan 99 | DB1, LLF 5 |
GSP Group | 3 Oct 98 | G7 |
Relationship Type | From | Value |
Registration | 3 Oct 98 | S1 |
Data Aggregator Appointment | 3 Oct 98 to 31 Mar 99 | DA 1 |
| 1 Apr 99 | DA 2 |
Data Collector Appointment | 3 Oct 98 | DC 1 |
Measurement Class | 3 Oct 98 | MC 3 |
Energisation Status | 3 Oct 98 | E |
Line Loss Factor Class | 3 Oct 98 | DB1, LLF 2 |
| 1 Jan 99 | DB1, LLF 5 |
GSP Group | 3 Oct 98 | G7 |
Instruction Type | Data Aggregator Appointment Details | ||
Metering System Id | MS200 | ||
Significant Date | 31 Mar 99 | ||
Relationship Type | Item 1 | Item 2 | Item 3 |
Registration | 3 Oct 98 | N/A | S1 |
Data Aggregator Appointment | 3 Oct 98 to 31 Mar 99 | 3 Oct 98 | N/A |
Data Collector Appointment | 3 Oct 98 | 3 Oct 98 | DC 1 |
Measurement Class | 3 Oct 98 | 3 Oct 98 | MC 3 |
Energisation Status | 3 Oct 98 | 3 Oct 98 | E |
Line Loss Factor Class | 1 Jan 99 | N/A | DB1, LLF 5 |
GSP Group | 3 Oct 98 | N/A | G7 |
Instruction Type | Data Aggregator Appointment Details | ||
Metering System Id | MS200 | ||
Significant Date | 31 Mar 99 | ||
Relationship Type | Item 1 | Item 2 | Item 3 |
Data Aggregator Appointment | 3 Oct 98 to 31 Mar 99 | 3 Oct 98 | N/A |
Instruction Type | Data Aggregator Appointment Details | ||
Metering System Id | MS200 | ||
Significant Date | 1 Apr 99 | ||
Relationship Type | Item 1 | Item 2 | Item 3 |
Registration | 3 Oct 98 | N/A | S1 |
Data Aggregator Appointment | 1 Apr 99 | 3 Oct 98 | N/A |
Data Collector Appointment | 3 Oct 98 | 3 Oct 98 | DC 1 |
Measurement Class | 3 Oct 98 | 3 Oct 98 | I |
Measurement Class | 3 Oct 98 | 3 Oct 98 | MC 3 |
Energisation Status | 3 Oct 98 | 3 Oct 98 | E |
Line Loss Factor Class | 1 Jan 99 | N/A | DB1, LLF 5 |
GSP Group | 3 Oct 98 | N/A | G7 |
Relationship Type | From | Value |
Registration | 1 Apr 98 | S5 |
Data Aggregator Appointment | 1 Apr 98 | DA 1 |
Data Collector Appointment | 1 Apr 98 | DC 2 |
Measurement Class | 1 Apr 98 | MC 1 |
Energisation Status | 1 Apr 98 | E |
| 15 Dec 98 | D |
Line Loss Factor Class | 1 Apr 98 | DB1, LLF 7 |
GSP Group | 1 Apr 98 | G3 |
Relationship Type | From | Value |
Registration | 1 Apr 98 | S5 |
Data Aggregator Appointment | 1 Apr 98 | DA 1 |
Data Collector Appointment | 1 Apr 98 | DC 2 |
Measurement Class | 1 Apr 98 | MC 1 |
Energisation Status | 1 Apr 98 | E |
| 20 Dec 98 | D |
Line Loss Factor Class | 1 Apr 98 | DB1, LLF 7 |
GSP Group | 1 Apr 98 | G3 |
Instruction Type | Energisation Status Details | ||
Metering System Id | MS202 | ||
Significant Date | 15 Dec 98 | ||
Relationship Type | Item 1 | Item 2 | Item 3 |
Energisation Status | 1 April 98 | 1 Apr 98 | E |
| 20 Dec 98 | 1 Apr 98 | D |
Relationship Type | From | Value |
Registration | 3 Oct 98 | S1 |
| 1 Apr 99 | S2 |
Data Aggregator Appointment | 3 Oct 98 to 31 Mar 99 | DA 1 |
| 1 Apr 99 | DA 1 |
Data Collector Appointment | 3 Oct 98 | DC 1 |
| 1 Apr 99 | DC 1 |
| 1 Apr 99 | I |
Measurement Class | 3 Oct 98 | MC 3 |
| 1 Apr 99 | MC 3 |
Energisation Status | 3 Oct 98 | E |
| 1 Apr 99 | E |
Line Loss Factor Class | 3 Oct 98 | DB1, LLF 2 |
| 1 Jan 99 | DB1, LLF 5 |
GSP Group | 3 Oct 98 | G7 |
Relationship Type | From | Value |
Registration | 3 Oct 98 | S1 |
Data Aggregator Appointment | 3 Oct 98 to 31 Mar 99 | DA 1 |
Data Collector Appointment | 3 Oct 98 | DC 1 |
Measurement Class | 3 Oct 98 | MC 3 |
Energisation Status | 3 Oct 98 | E |
Line Loss Factor Class | 3 Oct 98 | DB1, LLF 2 |
| 1 Jan 99 | DB1, LLF 5 |
GSP Group | 3 Oct 98 | G7 |
Instruction Type | Data Aggregator Appointment Details | ||
Metering System Id | MS200 | ||
Significant Date | 31 Mar 99 | ||
Relationship Type | Item 1 | Item 2 | Item 3 |
Registration | 3 Oct 98 | N/A | S1 |
Data Aggregator Appointment | 3 Oct 98 | 3 Oct 98 | N/A |
Data Collector Appointment | 3 Oct 98 | 3 Oct 98 | DC 1 |
Measurement Class | 3 Oct 98 | 3 Oct 98 | MC 3 |
Energisation Status | 3 Oct 98 | 3 Oct 98 | E |
Line Loss Factor Class | 1 Jan 99 | N/A | DB1, LLF 5 |
GSP Group | 3 Oct 98 | N/A | G7 |
Relationship Type | From | Value |
Registration | 3 Oct 98 | S1 |
Data Aggregator Appointment | 3 Oct 98 | DA 1 |
Data Collector Appointment | 3 Oct 98 | DC 1 |
Measurement Class | 3 Oct 98 | MC 3 |
Energisation Status | 3 Oct 98 | E |
Line Loss Factor Class | 3 Oct 98 | DB1, LLF 2 |
GSP Group | 3 Oct 98 | G7 |
Relationship Type | From | Value |
Registration | 3 Oct 98 | S1 |
Data Aggregator Appointment | 3 Oct 98 | DA 2 |
Data Collector Appointment | 3 Oct 98 | DC 1 |
Measurement Class | 3 Oct 98 | MC 3 |
Energisation Status | 3 Oct 98 | E |
Line Loss Factor Class | 3 Oct 98 | DB1, LLF 2 |
GSP Group | 3 Oct 98 | G7 |
Instruction Type | Data Aggregator Appointment Details | ||
Metering System Id | MS200 | ||
Significant Date | 3 Oct 98 | ||
Relationship Type | Item 1 | Item 2 | Item 3 |
Instruction Type | Data Aggregator Appointment Details | ||
Metering System Id | MS200 | ||
Significant Date | 3 Oct 98 | ||
Relationship Type | Item 1 | Item 2 | Item 3 |
Registration | 3 Oct 98 | N/A | S1 |
Data Aggregator Appointment | 3 Oct 98 | 3 Oct 98 | N/A |
Data Collector Appointment | 3 Oct 98 | 3 Oct 98 | DC 1 |
Measurement Class | 3 Oct 98 | 3 Oct 98 | MC 3 |
Energisation Status | 3 Oct 98 | 3 Oct 98 | E |
Line Loss Factor Class | 3 Oct 98 | N/A | DB1, LLF 2 |
GSP Group | 3 Oct 98 | N/A | G7 |
1 Please refer to the D0209 “Instruction(s) to Non Half Hourly or Half Hourly Data Aggregator” data flow.