Balancing and Settlement Code
BSC PROCEDURE
SHARED SVA METER ARRANGEMENT OF HALF HOURLY IMPORT AND EXPORT ACTIVE ENERGY
BSCP550
Date: |
Intellectual Property Rights, Copyright and Disclaimer The copyright and other intellectual property rights in this document are vested in Elexon or appear with the consent of the copyright owner. These materials are made available for you for the purposes of your participation in the electricity industry. If you have an interest in the electricity industry, you may view, download, copy, distribute, modify, transmit, publish, sell or create derivative works (in whatever format) from this document or in other cases use for personal academic or other non-commercial purposes. All copyright and other proprietary notices contained in the document must be retained on any copy you make. All other rights of the copyright owner not expressly dealt with above are reserved. No representation, warranty or guarantee is made that the information in this document is accurate or complete. While care is taken in the collection and provision of this information, Elexon Limited shall not be liable for any errors, omissions, misstatements or mistakes in any information or damages resulting from the use of this information or action taken in reliance on it. |
Version | Date | Description of Changes | Changes Included | Mods/ Panel/ Committee Refs |
2.0 | Code Effective Date | Approved for use by the Panel |
|
|
3.0 | Code Effective Date | Incorporation of SMRS to CMRS Transfers. (Including peer review comments) | NCR114 |
|
4.0 | 08/03/02 | P67 ‘Facilitation of Further Consolidation Options for Licence Exempt Generators (DTI Consolidator Working Group ‘Option 4’)’ changes embodied. | AR1177 | SVG12/153 |
5.0 | 26/04/02 | MTC changes embodied to identify actual and pseudo MSIDs. | CP765 | SVG14/179 |
6.0 | 01/08/03 | Updated for Modification P62 | P62 | SVG29/390 |
7.0 | 28/08/03 | August 03 SVA Document Batch Release | CP854 CP912 | SVG29/389 SVG30/397 |
8.0 | 04/11/03 | SVA November 03 Release | CP811 | SVG33/442 |
9.0 | BETTA Effective Date | SVA February 05 Release and BETTA 6.3 | CP1091 BETTA 6.3 | SVG48/004 |
10.0 | 23/08/07 | P197 Release | P197 CP1176 | 115/04 SVG67/16 ISG68/02 |
11.0 | 28/02/08 | February 08 Release | CP1214 | SVG81/01 |
12.0 | 06/11/08 | November 08 Release | CP1234 | SVG85/02 |
13.0 | 28/06/12 | June 12 Release | CP1369 | SVG135/031 |
14.0 | 22/02/18 | February 2018 Release | CP1483 | SVG197/04 |
15.0 | 01/09/21 | September 2021 Release | P420 | P316/05 |
16.0 | 18/07/22 | July 2022 Release | P436 | P325/05 |
17.0 | 05/10/22 | October 2022 Release | P425 | P329/03 |
Percentage Method;
Capped Block Method;
Fixed Block Method; or
Multiple Fixed Block Method.
BSCP68 | Transfer of Registration of Metering Systems between CMRS and SMRS. |
BSCP501 | Supplier Meter Registration Service. |
BSCP502 | Half Hourly Data Collection for Metering Systems Registered in SMRS. |
BSCP503 | Half Hourly Data Aggregation for Metering Systems Registered in SMRS. |
CMRS | Central Meter Registration Service |
CSS | Central Switching Service |
ERDA | Electricity Retail Data Agent |
HHDA | Half Hourly Data Aggregator |
HHDC | Half Hourly Data Collector |
Id | Identifier |
LDSO | Licensed Distribution System Operator |
MS | Metering System |
MSID | Metering System Identifier |
MTC | Meter Timeswitch Code |
MTD | Meter Technical Details |
REC | Retail Energy Code |
SMRA | Supplier Meter Registration Agent |
SMRS | Supplier Meter Registration Service |
SSD | Supply Start Date (also known as Effective from Settlement Date {REGI}). |
SVA | Supplier Volume Allocation |
SVA MOA | Supplier Volume Allocation Meter Operator Agent |
WD | Working Day |
REF. | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
3.1.1 | As required.9 | Agree:- 1. Primary Supplier and Secondary Supplier(s); 2. Fixed and Variable Supplier(s) if either the Fixed Block or Multiple Fixed Block Methods are to be used; and 3. The contract SSD and the initial Allocation Schedule. | Primary Supplier | Secondary Supplier(s) | Allocation Schedule to comply with Appendices 4.3 & 4.4. | By post, fax or electronic media. |
3.1.2 | At least 15 WD prior to contract SSD. | Notify LDSO that Shared SVA Meter Arrangement being initiated and that Primary and pseudo Secondary MSIDs will be required. | Primary Supplier | LDSO | Provide details of intended Suppliers and/or MSIDs required for Shared SVA Meter Arrangement. | By post, fax or electronic media. |
3.1.3 | Within 2 WD of 3.1.2. | Allocate Primary and pseudo Secondary MSIDs, record association and ensure no duplication. | LDSO | SMRA | As per BSCP501. | By post, fax or electronic media. |
3.1.4 | Within 2 WD of 3.1.2. | Send Primary and pseudo Secondary MSIDs to Primary Supplier. | LDSO | Primary Supplier | As per BSCP501. | By post, fax or electronic media. |
3.1.5 | Within 2 WD of 3.1.3. | Record details for Primary and pseudo Secondary MSIDs. | SMRA |
| As per BSCP501. | Internal process. |
3.1.6 | At least 11 WD prior to contract SSD, and following registration in CSS and synchronisation with SMRS via the ERDA. | Complete Primary Supplier and Party Agent registration details for all MSIDs in SMRS. | Primary Supplier | SMRA | As per BSCP501. | Electronic or other agreed method. |
3.1.7 | Within 2 WD of 3.1.6. | Record registration details for Primary and pseudo Secondary MSIDs in accordance with BSCP501. | SMRA |
| As per BSCP501. | Internal process. |
3.1.8 | At least 5 WD before Appointment Date. | Send Party Agent appointment details for the Primary and pseudo Secondary MSIDs. | Primary Supplier | SVA MOA, HHDC, HHDA | As per Appendices 4.1, 4.5 & 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.1.9 | At the same time as 3.1.8 | Notify HHDC and Secondary Supplier(s) where appropriate of the initial Allocation Schedule. (HHDC and Secondary Supplier(s) should receive the initial Allocation Schedule by Gate Closure) | Primary Supplier | HHDC, Secondary Supplier(s) | Allocation Schedule to comply with Appendices 4.2 & 4.3 | By fax or electronic media. |
3.1.10 | Within 2 WD of 3.1.9 | Confirm that Allocation Schedule was received. | HHDC | Primary Supplier, Secondary Supplier(s) |
| |
3.1.11 | Within 2 WD of 3.1.9. | Advise Secondary Supplier(s) where applicable of pseudo Secondary MSID(s), SVA MOA, HHDC and HHDA details. | Primary Supplier | Secondary Supplier(s) |
| By post, fax or electronic media. |
3.1.12 | By contract SSD-1 WD. | Follow change of Supplier procedure for pseudo Secondary MSID(s). | Secondary Supplier(s) | CSS and SMRA | As per BSCP501 and the REC. | Electronic or other agreed method. |
3.1.13 | Within 2 WD of 3.1.11. | Update record for pseudo Secondary MSID(s). | SMRA |
| As per BSCP501. | Internal process. |
3.1.14 | At least 5 WD before Appointment Date. | Send Party Agent appointment details for the pseudo Secondary MSID(s). | Secondary Supplier(s) | SVA MOA, HHDC, HHDA(s) | As per Appendices 4.1, 4.5 & 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.1.15 | Within 2 WD of 3.1.13. | Confirm appointment details are complete and consistent for pseudo Secondary MSID(s). Resolve errors with Secondary Supplier(s). | SVA MOA, HHDC, HHDA(s) | Secondary Supplier(s) | As per BSCP502 / BSCP503 and REC Metering Operations Schedule. | Electronic or other agreed method. |
3.1.16 | At least 5 WD before Primary Supplier Appointment Termination Date. | Send appointment termination date for pseudo Secondary MSID(s) to SVA MOA, HHDC and HHDA. | Primary Supplier | SVA MOA, HHDC, HHDA | As per Appendix 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.1.17 | Within 2 WD of 3.1.15. | Confirm appointment termination details are complete and consistent. Resolve errors with Primary Supplier. | SVA MOA, HHDC | Primary Supplier | As per Appendices 4.1 & 4.6 / BSCP502 / REC Metering Operations Schedule. | Electronic or other agreed method.. |
3.1.18 | At least 5 WD before Primary Supplier Appointment Termination Date. | Confirm appointment termination details are complete and consistent for pseudo Secondary MSID(s). Resolve errors with Primary Supplier. | HHDA | Primary Supplier | As per BSCP503. | Electronic, or other agreed method |
3.1.19 | As soon as practicable after receipt. | Confirm that Allocation Schedule was received by Gate Closure. | HHDC | Primary Supplier, Secondary Supplier(s) |
|
REF. | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
3.2.1.1 | As required. | Agree:- 1 Primary Supplier and Secondary Supplier(s); 2. Fixed and Variable Supplier(s) if either the Fixed Block or Multiple Fixed Block Methods are to be used; and 3. the contract SSD and the initial Allocation Schedule. | Primary Supplier | Secondary Supplier(s) | Allocation Schedule to comply with Appendices 4.2 & 4.3. | By post, fax or electronic media. |
3.2.1.2 | Prior to 3.2.1.3 | Notify LDSO that Shared SVA Meter Arrangement being initiated, provide Primary MSID and notify that pseudo Secondary MSID(s) will be required. | Primary Supplier | LDSO | Provide details of intended Supplier(s) and/or MSIDs required for Shared SVA Meter Arrangement. |
|
3.2.1.3 | At least 15 WD prior to contract SSD. | Follow change of Supplier procedure for Primary MSID with agreed SSD. | Primary Supplier | CSS and SMRA | As per BSCP501 and the REC. | Electronic or other agreed method. |
3.2.1.4 | Within 2 WD of 3.2.1.3. | Record details for Primary MSID. | SMRA |
| As per BSCP501. | Internal process |
3.2.1.5 | At least 13 WD prior to contract SSD. | Notify change to Primary MSID and apply for the pseudo Secondary MSID(s) and identify as a request for pseudo MSID(s). | Primary Supplier | LDSO | As per BSCP501. | By post, fax or electronic media. |
3.2.1.6 | Within 2 WD of 3.2.1.5. | Designate original MSID as Primary MSID, allocate pseudo Secondary MSID(s), record association and ensure no duplication. | LDSO | SMRA | As per BSCP501. | Manual interface. |
3.2.1.7 | Within 2 WD of 3.2.1.5. | Send MSIDs to Primary Supplier. | LDSO | Primary Supplier | As per BSCP501. | Electronic or other agreed method. |
3.2.1.8 | At least 11 WD prior to contract SSD, and following registration in CSS and synchronisation with SMRS via the ERDA. | Complete Supplier and Party Agents registration details for pseudo MSIDs in SMRS, with an appropriate SSD. (see Section 1.3) | Primary Supplier | SMRA | As per BSCP501. | Electronic or other agreed method. |
3.2.1.9 | Within 2 WD of 3.2.1.8. | Record details for pseudo Secondary MSID(s). | SMRA |
| As per BSCP501. | Internal process. |
3.2.1.10 | At least 5 WD before Secondary Supplier Appointment Date | Send Party Agent appointment details for the Primary and pseudo Secondary MSID(s). | Primary Supplier | SVA MOA, HHDC, HHDA | As per Appendices 4.1, 4.5 & 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.2.1.11 | At the same time as 3.2.1.10 | Notify HHDC and Secondary Supplier(s) of the initial Allocation Schedule. (HHDC and Secondary Supplier(s) should receive the initial Allocation Schedule by Gate Closure) | Primary Supplier | HHDC, Secondary Supplier(s) | Allocation Schedule to comply with Appendices 4.2 & 4.3 | By fax or electronic media. |
3.2.1.12 | Within 2 WD of 3.2.1.11 | Confirm that Allocation Schedule was received. | HHDC | Primary Supplier, Secondary Supplier(s) |
| |
3.2.1.13 | Within 2 WD of 3.2.1.11. | Advise Secondary Supplier(s) of pseudo Secondary MSID(s), SVA MOA, HHDC and HHDA details. | Primary Supplier | Secondary Supplier(s) |
| By post, fax or electronic media. |
3.2.1.14 | By contract SSD-1 WD. | Follow change of Supplier procedure for pseudo Secondary MSID(s). | Secondary Supplier(s) | CSS and SMRA | As per BSCP501 and the REC. | Electronic or other agreed method. |
3.2.1.15 | Within 2 WD of 3.2.1.13. | Update record for pseudo Secondary MSID(s). | SMRA |
| As per BSCP501. | Internal process. |
3.2.1.16 | At least 5 WD before Secondary Supplier Appointment Date. | Send Party Agent appointment details for the pseudo Secondary MSID(s). | Secondary Supplier(s) | SVA MOA, HHDC. HHDA(s) | As per Appendices 4.1, 4.5 & 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.2.1.17 | At least 5 WD before Primary Supplier Appointment Termination Date. | Send appointment termination date for pseudo Secondary MSID(s) to SVA MOA, HHDC and HHDA. | Primary Supplier | SVA MOA, HHDC, HHDA | As per Appendix 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.2.1.18 | Within 2 WD of 3.2.1.17. | Confirm appointment termination details are complete and consistent. Resolve errors with Primary Supplier. | SVA MOA, HHDC. HHDA | Primary Supplier | As per BSCP502 / BSCP503 and REC Metering Operations Schedule. | Electronic or other agreed method. |
REF. | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD | |
3.2.2.1 | As required. | Agree:-
2. Fixed and Variable Supplier(s) if either the Fixed Block or Multiple Fixed Block Methods are to be used; and 3. Contract SSD and initial Allocation Schedule. | Primary Supplier | Secondary Supplier(s) | Allocation Schedule to comply with Appendices 4.2 & 4.3. | By post, fax or electronic media. | |
3.2.2.2 | Prior to 3.2.2.3 | Notify LDSO of intention to amend Shared SVA Meter Arrangement. | Primary Supplier | LDSO | Provide details of intended Suppliers and MSIDs required for Shared SVA Meter Arrangement. |
| |
3.2.2.3 | At least 1 WD prior to contract SSD. | Follow change of Supplier procedure for Primary MSID with agreed contract SSD. | Primary Supplier | CSS and SMRA | As per BSCP501 and the REC. | Electronic or other agreed method. | |
3.2.2.4 | Within 2 WD of 3.2.2.3 | Record details for Primary MSID. | SMRA |
| As per BSCP501. | Internal process | |
3.2.2.5 | At least 1 WD prior to contract SSD. | Advise Secondary Supplier(s) of SVA MOA, HHDC and HHDA appointment details. | Primary Supplier | Secondary Supplier(s) |
| By post, fax or electronic media. | |
3.2.2.6 | By contract SSD-1 WD. | Follow change of Supplier procedure for pseudo Secondary MSID(s), with agreed contract SSD. | Secondary Supplier(s) | CSS and SMRA | As per BSCP501 and the REC. | Electronic or other agreed method. | |
3.2.2.7 | Within 2 WD of 3.2.2.6. | Update record for pseudo Secondary MSID(s). | SMRA |
| As per BSCP501. | Internal process. | |
3.2.2.8 | At least 5 WD before Appointment Date. | Send Party Agent appointment (or de-appointment) details for the Primary MSID. | New Primary Supplier | SVA MOA, HHDC, HHDA | As per Appendices 4.1, 4.5 & 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. | |
3.2.2.9 | At least 5 WD before Appointment Date. | Send Party Agent appointment (or de-appointment) details for the pseudo Secondary MSID(s). | New Secondary Supplier(s) | SVA MOA, HHDC, HHDA | As per Appendices 4.1, 4.5 & 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. | |
3.2.2.10 | By Gate Closure. | Notify HHDC and Secondary Supplier(s) of the revised Allocation Schedule. (HHDC and Secondary Supplier(s) shall receive the revised Allocation Schedule by Gate Closure) | Primary Supplier | HHDC, Secondary Suppliers(s) | Allocation Schedule to comply with Appendices 4.2 & 4.3. | By fax or electronic media. | |
| 3.2.2.11 | As soon as practicable after receipt. | Confirm that revised Allocation Schedule was received by Gate Closure. | HHDC | Primary Supplier, Secondary Supplier(s) |
| Email. |
REF. | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD | ||
3.2.3.1 | As required. | Agree contract SSD and revised Allocation Schedule. | Current Supplier(s) | New Supplier | Allocation Schedule to comply with Appendices 4.2 & 4.3. | By post, fax or electronic media. | ||
3.2.3.2 | Prior to 3.2.3.3 | Notify LDSO of intention to amend Shared SVA Meter Arrangement. | Primary Supplier | LDSO | Provide details of intended Suppliers and MSIDs required for Shared SVA Meter Arrangement. |
| ||
3.2.3.3 | At least 1 WD prior to contract SSD. | Follow change of Supplier procedure for MSID with agreed contract SSD. | New Supplier | CSS and SMRA | As per BSCP501 and the REC. | Electronic or other agreed method. | ||
3.2.3.4 | Within 2 WD of 3.2.3.3. | Record details for changing Supplier. | SMRA |
| As per BSCP501. | Internal process | ||
3.2.3.5 | At least 1 WD prior to contract SSD. | Notify new Supplier of SVA MOA, HHDC and HHDA appointment details. | Primary Supplier | New Supplier |
| By post, fax or electronic media. | ||
3.2.3.6 | At least 5 WD before New Supplier Appointment Date. | Send Party Agent appointment details for the changing MSID. | New Supplier | SVA MOA, HHDC, HHDA | As per Appendices 4.1, 4.5 & 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. | ||
3.2.3.7 | At least 5 WD before Old Supplier Appointment Termination Date. | Send appointment termination date for changing Supplier to SVA MOA, HHDC and HHDA. | Old Supplier | SVA MOA, HHDC, HHDA | As per BSCP502 / BSCP503 and REC Metering Operations Schedule. | Electronic or other agreed method. | ||
3.2.3.8 | By Gate Closure. | Notify HHDC and Secondary Supplier(s) of the revised Allocation Schedule. (HHDC and Secondary Supplier(s) shall receive the revised Allocation Schedule by Gate Closure) | Primary Supplier | HHDC, Secondary Suppliers(s) | Allocation Schedule to comply with Appendices 4. 2 & 4.3. | By fax or electronic media. | ||
| 3.2.3.9 | As soon as practicable after receipt. | Confirm that revised Allocation Schedule was received by Gate Closure. | HHDC | Primary Supplier, Secondary Supplier(s) |
| Email. |
REF. | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD | |
3.2.4.1 | As required. | Agree contract SSD and revised Allocation Schedule. | Primary Supplier | Additional & Current Secondary Suppliers | Allocation Schedule to comply with Appendices 4.2 & 4.3. | By post, fax or electronic media. | |
3.2.4.2 | Prior to 3.2.4.3 | Notify LDSO of intention to amend Shared SVA Meter Arrangement. | Primary Supplier | LDSO | Provide details of intended Suppliers and/or MSIDs required for Shared SVA Meter Arrangement. |
| |
3.2.4.3 | At least 13 WD prior to contract SSD. | Apply for additional pseudo Secondary MSID(s) and identify as a request for pseudo Secondary MSID(s). | Primary Supplier | LDSO | As per BSCP501. | By post, fax or electronic media. | |
3.2.4.4 | Within 2 WD of 3.2.4.3. | Allocate additional pseudo Secondary MSID(s), record association and ensure no duplication. | LDSO | SMRA | As per BSCP501. | Manual interface. | |
3.2.4.5 | Within 2 WD of 3.2.4.3. | Send MSID details to Primary Supplier for pseudo Secondary MSID(s). | LDSO | Primary Supplier | As per BSCP501. | Electronic or other agreed method. | |
3.2.4.6 | At least 11 WD prior to contract SSD, and following registration in CSS and synchronisation with SMRS via the ERDA. | Complete Supplier and Party Agents registration details for additional pseudo Secondary MSID(s) in SMRS, with an appropriate SSD. (see Section 1.3) | Primary Supplier | SMRA | As per BSCP501. | Electronic or other agreed method. | |
3.2.4.7 | Within 2 WD of 3.2.4.6. | Record details for additional pseudo Secondary MSID(s). | SMRA |
| As per BSCP501. | Internal process. | |
3.2.4.8 | At least 5 WD before Primary Supplier Appointment Date. | Send Party Agent appointment details for the additional pseudo Secondary MSID(s). | Primary Supplier | SVA MOA, HHDC, HHDA | As per Appendices 4.1, 4.5 & 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. | |
3.2.4.9 | Within 2 WD of 3.2.4.8. | Confirm details for additional MSID are complete and consistent. Resolve errors with Primary Supplier. | SVA MOA, HHDC, HHDA(s) | Primary Supplier | As per BSCP502 / BSCP503 and REC Metering Operations Schedule. | Electronic or other agreed method. | |
3.2.4.10 | Within 2 WD of 3.2.4.9. | Advise additional Secondary Supplier(s) of MSID(s), SVA MOA, HHDC and HHDA details. | Primary Supplier | Additional Secondary Supplier(s) |
| By post, fax or electronic media. | |
3.2.4.11 | By contract SSD-1 WD. | Follow change of Supplier procedure for new pseudo Secondary MSID(s). | Additional Secondary Supplier(s) | CSS and SMRA | As per BSCP501 and the REC. | Electronic or other agreed method. | |
3.2.4.12 | Within 2 WD of 3.2.4.11. | Update record for new pseudo Secondary MSID(s). | SMRA |
| As per BSCP501. | Internal process. | |
3.2.4.13 | At least 5 WD before Appointment Date. | Send Party Agent appointment details for the new pseudo Secondary MSID(s). | Additional Secondary Supplier | SVA MOA, HHDC. HHDA | As per Appendices 4.1, 4.5 & 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. | |
3.2.4.14 | At least 5 WD before Primary Supplier Appointment Termination Date. | Send appointment termination date for additional pseudo Secondary MSID(s) to SVA MOA, HHDC and HHDA. | Primary Supplier | SVA MOA, HHDC, HHDA | As per BSCP502 / BSCP503 and REC Metering Operations Schedule. | Electronic or other agreed method. | |
3.2.4.15 | By Gate Closure. | Notify HHDC and all Secondary Suppliers of the revised Allocation Schedule. (HHDC and Secondary Suppliers shall receive the revised Allocation Schedule by Gate Closure) | Primary Supplier | HHDC, Secondary Suppliers | Allocation Schedule to comply with Appendices 4.2 & 4.3. | By fax or electronic media. | |
| 3.2.4.16 | As soon as practicable after receipt. | Confirm that revised Allocation Schedule was received by Gate Closure. | HHDC | Primary Supplier, Secondary Suppliers |
| Email. |
REF. | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
| |
3.2.5.1 | As required. | Inform Primary Supplier of SSD for removal of pseudo Secondary MSID(s). | De-registering Secondary Supplier(s) | Primary Supplier | MSID to be removed and SSD | By post, fax or electronic media. |
| |
3.2.5.2 | Prior to 3.2.5.3 | Notify LDSO of intention to amend Shared SVA Meter Arrangement. | Primary Supplier | LDSO | Provide details of intended Suppliers and MSIDs required for Shared SVA Meter Arrangement. |
|
| |
3.2.5.3 | As required. | Agree revised Allocation Schedule with remaining Secondary Supplier(s) and inform them of the applicable SSD. | Primary Supplier | Remaining Secondary Suppliers | Allocation Schedule to comply with Appendices 4.2 & 4.3. | By post, fax or electronic media |
| |
3.2.5.4 | At least 1 WD prior to contract SSD. | Follow change of Supplier procedure for MSID(s) with agreed contract SSD. | Primary Supplier | CSS and SMRA | As per BSCP501 and the REC. | Electronic or other agreed method. |
| |
3.2.5.5 | Within 2 WD of 3.2.5.4. | Update record for de-registering pseudo Secondary MSID(s). | SMRA |
| As per BSCP501. | Internal process |
| |
3.2.5.6 | Within 3 WD of 3.2.5.5. | Request logical disconnection with date for de-registering pseudo Secondary MSID(s). | Primary Supplier | LDSO | As per BSCP501. | Electronic or other agreed method. |
| |
3.2.5.7 | Within 1 WD of 3.2.5.6. | Record de-registering pseudo Secondary MSID(s) as disconnected. | LDSO | SMRA | As per BSCP501. | Electronic or other agreed method. |
| |
3.2.5.8 | At least 1 WD prior to contract SSD. | Confirm disconnection of de-registering pseudo Secondary MSID(s) to Primary Supplier. | LDSO | Primary Supplier | As per BSCP501. | Electronic or other agreed method. |
| |
3.2.5.9 | Following registration deactivation of the pseudo Secondary MSID(s) in CSS. | Send appointment termination date for de-registering pseudo Secondary MSID(s) to SVA MOA, HHDC and HHDA. | Primary Supplier | SVA MOA, HHDC, HHDA | As per Appendix 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. |
| |
3.2.5.10 | Before Secondary Supplier Appointment Termination Date. | Confirm appointment termination date for de-registering MSID with de-registering Supplier. | Primary Supplier | De-registering Supplier | MSID appointment termination date | Electronic or other agreed method |
| |
3.2.5.11 | By Gate Closure. | Notify HHDC and all existing Secondary Suppliers of the revised Allocation Schedule. (HHDC and Secondary Suppliers shall receive the revised Allocation Schedule by Gate Closure) | Primary Supplier | HHDC, Secondary Suppliers | Allocation Schedule to comply with Appendices 4.2 & 4.3. | By post, fax or electronic media. |
| |
| 3.2.5.12 | Within 1 WD of 3.2.5.11. | Confirm that revised Allocation Schedule was received by Gate Closure. | HHDC | Primary Supplier, Secondary Suppliers |
| Email. |
REF. | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
3.2.6.1 | Following agreement with other Secondary Suppliers or Single Supplier to terminate Shared SVA Meter Arrangement. | Notify LDSO of intention to terminate Shared SVA Meter Arrangement. | Primary Supplier | LDSO |
| Electronic or other agreed method. |
3.2.6.2 | At least 5 WD prior to contract SSD. | Follow change of Supplier procedure for Primary and pseudo Secondary MSIDs. | Primary Supplier | CSS and SMRA | As per BSCP501 and the REC. | Electronic or other agreed method. |
3.2.6.3 | Within 2 WD of 3.2.6.1. | Update record for Primary and pseudo Secondary MSIDs. | SMRA |
| As per BSCP501. | Internal process |
3.2.6.4 | At least 3 WD prior to contract SSD. | Request disconnection with date for pseudo Secondary MSID(s). | Primary Supplier | LDSO | As per BSCP501. | Electronic or other agreed method. |
3.2.6.5 | At least 1 WD prior to contract SSD. | Record pseudo Secondary MSID(s) as disconnected and change Primary MSID to normal MSID in records. | LDSO | SMRA | As per BSCP501. | Electronic or other agreed method. |
3.2.6.6 | Within 2 WD of 3.2.6.5. | Update record for Primary and pseudo Secondary MSID(s). | SMRA |
| As per BSCP501. | Internal process. |
3.2.6.7 | At least 1 WD prior to contract SSD. | Confirm disconnection of pseudo Secondary MSID(s) to Supplier. | LDSO | Primary Supplier | As per BSCP501. | Electronic or other agreed method. |
3.2.6.8 | At least 5 WD before Appointment Date. | Send appointment details for the remaining MSID to SVA MOA, HHDC and HHDA. | Primary Supplier | SVA MOA, HHDC HHDA | As per Appendices 4.1, 4.5 & 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.2.6.9 | Following registration deactivation of the pseudo Secondary MSID(s) in CSS. | Send appointment termination date to SVA MOA, HHDC & HHDA(s). | Primary & Secondary Suppliers | SVA MOA HHDC, HHDA(s) | As per Appendix 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. |
REF. | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
3.3.1 | As required. | Notify SMRA of new HHDC appointment for Primary MSID. | Primary Supplier13 | SMRA | As per BSCP501. | Electronic or other agreed method. |
3.3.2 | Within 2 WD of 3.3.1. | Update record for Primary MSID. | SMRA |
| As per BSCP501. | Internal process |
3.3.3 | Within 2 WD of 3.3.1. | Notify Secondary Supplier(s) of the new HHDC appointment. | Primary Supplier | Secondary Supplier(s) | As per Appendix 4.8 | By post, fax or electronic media. |
3.3.4 | Within 2 WD of 3.3.3. | Update SMRS with new HHDC for pseudo Secondary MSID(s). | Secondary Supplier(s)14 | SMRA | As per BSCP501. | Electronic or other agreed method. |
3.3.5 | Within 2 WD of 3.3.4. | Update record for pseudo Secondary MSID(s). | SMRA |
| As per BSCP501. | Internal process |
3.3.6 | At least 5 WD before Appointment Date. | Send appointment details of the new HHDC and the termination date for the old HHDC for the Primary MSID. | Primary Supplier | SVA MOA, New HHDC, HHDA, Old HHDC | As per Appendices 4.1, 4.5 & 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.3.7 | At the same time as 3.3.6 | Notify HHDC and Secondary Supplier(s) of the revised Allocation Schedule. (HHDC and Secondary Supplier(s) shall receive the revised Allocation Schedule by Gate Closure) | Primary Supplier | New HHDC, Secondary Supplier(s) | Allocation Schedule to comply with Appendices 4.2 & 4.3 | By fax or electronic media. |
3.3.8 | Within 2 WD of 3.3.7 | Confirm that revised Allocation Schedule was received. | HHDC | Primary Supplier, Secondary Supplier(s) |
| Email. |
3.3.9 | At least 5 WD before Appointment Date. | Send appointment details of the new HHDC and the termination date for the old HHDC for the pseudo Secondary MSID(s). | Secondary Supplier(s)14 | SVA MOA, New HHDC, HHDA(s), Old HHDC | As per Appendices 4.1, 4.5 & 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.3.10 | As required. | Send Meter history details. | Old HHDC | New HHDC | As per BSCP502 |
|
REF. | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
3.4.1 | As required. | Notify SMRA of new SVA MOA appointment for Primary MSID. | Primary Supplier | SMRA | As per BSCP501. | Electronic or other agreed method. |
3.4.2 | Within 2 WD of 3.4.1. | Update record for Primary MSID. | SMRA |
| As per BSCP501. | Internal Process |
3.4.3 | Within 2 WD of 3.4.1. | Notify Secondary Supplier(s) of new SVA MOA appointment. | Primary Supplier | Secondary Supplier(s) | As per Appendix 4.8 | By post, fax or electronic media. |
3.4.4 | Within 2 WD of 3.4.3. | Update SMRS with new SVA MOA details for pseudo Secondary MSID(s). | Secondary Supplier(s)14 | SMRA | As per BSCP501. | Electronic or other agreed method. |
3.4.5 | Within 2 WD of 3.4.4. | Update record for pseudo Secondary MSID(s). | SMRA |
| As per BSCP501. | Internal Process |
3.4.6 | At least 5 WD before Appointment Date. | Send appointment details of the new SVA MOA and termination of old SVA MOA for the Primary MSID. | Primary Supplier | New SVA MOA, Old SVA MOA, HHDC | As per Appendices 4.1, 4.5 & 4.6 / BSCP502 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.4.7 | At least 5 WD before Appointment Date. | Send appointment details of the new SVA MOA and termination date for the Old SVA MOA for the pseudo Secondary MSID(s). | Secondary Supplier(s)14 | New SVA MOA, Old SVA MOA, HHDC | As per Appendices 4.1, 4.5 & 4.6 / BSCP502 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.4.8 | At least 5 WD before Appointment Termination Date. | Send appointment termination date for Primary MSID to old SVA MOA. | Primary Supplier | Old SVA MOA | As per REC Metering Operations Schedule. | Electronic or other agreed method. |
3.4.9 | At least 5 WD before Appointment Termination Date. | Send appointment termination date for pseudo Secondary MSID(s) to old SVA MOA. | Secondary Supplier(s)14 | Old SVA MOA | As per REC Metering Operations Schedule. | Electronic or other agreed method. |
3.4.10 | Before Appointment Termination Date. | Send MTD. | Old SVA MOA | New SVA MOA | As per REC Metering Operations Schedule. |
|
REF. | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
3.5.1 | As required. | Agree:- 1. date supply is to be energised; 2. the initial Allocation Schedule; and 3. whether LDSO or SVA MOA is to energise supply. | Primary Supplier | Secondary Supplier(s) | Allocation Schedule to comply with Appendices 4.2 & 4.3. | By post, fax or electronic media. |
3.5.2 | At least 2 WD prior to planned energisation date. | Notify SMRA of planned energisation date for Primary MSID. | Primary Supplier | SMRA | As per BSCP501. | Electronic or other agreed method. |
3.5.3 | Within 2 WD of 3.5.2. | Update record for Primary MSID. | SMRA |
| As per BSCP501. | Internal Process |
3.5.4 | At least 2 WD prior to planned energisation date. | Notify SMRA of date of planned energisation date for Secondary pseudo MSID(s). | Secondary Supplier(s)14 | SMRA | As per BSCP501. | Electronic or other agreed method. |
3.5.5 | Within 2 WD of 3.5.4. | Update record for Secondary pseudo MSID(s). | SMRA |
| As per BSCP501. | Internal Process |
3.5.6 | At least 5 WD prior to energisation Date. | Send date for planned energisation for the Primary MSID to the LDSO or SVA MOA and HHDC. | Primary Supplier | LDSO or SVA MOA/HHDC | As per BSCP502 and REC Metering Operations Schedule. | Electronic or other agreed method. |
3.5.7 | At least 5 WD prior to energisation Date. | Send date for planned energisation for the Secondary pseudo MSID(s) to the LDSO or SVA MOA and HHDC. | Secondary Supplier(s)14 | LDSO or SVA MOA/HHDC | As per BSCP502 and REC Metering Operations Schedule. | Electronic or other agreed method. |
3.5.8 | On energisation Day. | Carry out energisation and obtain reading for physical MS. Liaise with HHDC to collect HH data | SVA MOA or LDSO | HHDC. |
| Electronic or other agreed method. |
3.5.9 | Within 2 WD of 3.5.8. | Send date of energisation for the MSID to Primary and Secondary Suppliers and HHDC. Confirm that: a) energisation is complete including energisation dates and (for a physical energisation) MS reading; and b) details for all MSIDs are complete and consistent. Resolve errors with Suppliers and notify SVA MOA or LDSO. | LDSO or SVA MOA | Primary & Secondary Suppliers, HHDC | As per BSCP502 and REC Metering Operations Schedule. | Electronic or other agreed method. |
3.5.10 | Following energisation date. | Notify of actual energisation date (which may be different from planned energisation date). | Primary and Secondary Suppliers | SMRA, HHDC | As per BSCP501 | Electronic or other agreed method. |
3.5.11 | Upon receiving actual Energisation date. | Update SMRA with actual energisation date. | SMRA |
| As per BSCP501 | Internal Process |
3.5.12 | Within 2 WD of 3.5.10. | Confirm energisation details are complete and consistent. Resolve errors with Supplier(s). | HHDC | Primary & Secondary Suppliers | As per Appendices 4.4 & 4.6 / BSCP502 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.5.13 | By Gate Closure. | Notify HHDC and Secondary Supplier(s) of the revised Allocation Schedule. (HHDC and Secondary Supplier(s) shall receive the revised Allocation Schedule by Gate Closure) | Primary Supplier | HHDC, Secondary Supplier(s) | Allocation Schedule to comply with Appendices 4.2 & 4.3. | By fax or electronic media. |
3.5.14 | As soon as practicable after receipt. | Confirm that revised Allocation Schedule was received by Gate Closure. | HHDC | Primary Supplier, Secondary Supplier(s) |
| Email. |
REF. | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
3.6.1 | As required. | Agree:- 1. date supply is to be de-energised; and 2. whether LDSO or SVA MOA is to de-energise supply. | Primary Supplier | Secondary Supplier(s) | As per BSCP502 and REC Metering Operations Schedule. | By post, fax or electronic media. |
3.6.2 | At least 2 WD prior to planned de-energisation date. | Notify SMRA of planned de-energisation date for Primary MSID. | Primary Supplier | SMRA | As per BSCP501. | Electronic or other agreed method. |
3.6.3 | Within 2 WD of 3.6.2. | Update record for Primary MSID. | SMRA |
| As per BSCP501. | Internal process |
3.6.4 | At least 2 WD prior to planned de-energisation date. | Notify SMRA of planned de-energisation date for pseudo Secondary MSID(s). | Secondary Supplier(s)14 | SMRA | As per BSCP501. | Electronic or other agreed method. |
3.6.5 | Within 2 WD of 3.6.4. | Update record for pseudo Secondary MSID(s). | SMRA |
| As per BSCP501. | Internal process. |
3.6.6 | At least 5 WD prior to de-energisation Date. | Send date for de-energisation for the Primary MSID to the HHDC and LDSO or SVA MOA. | Primary Supplier | HHDC & LDSO or SVA MOA | As per Appendices 4.5 & 4.6 / BSCP502 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.6.7 | At least 5 WD prior to planned de-energisation Date. | Send date for planned de-energisation for the pseudo Secondary MSID(s) to the HHDC and LDSO or SVA MOA. | Secondary Supplier(s)14 | HHDC & LDSO or SVA MOA | As per Appendices 4.5 & 4.6 / BSCP502 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.6.8 | On de-energisation Day. | Carry out de-energisation and obtain reading for physical MS. Liaise with HHDC to collect HH data. | SVA MOA or LDSO | HHDC |
| Electronic or other agreed method. |
3.6.9 | Within 2 WD of 3.6.8. | Send date of de-energisation for the MSID. Confirm that:
Resolve errors with Suppliers and notify LDSO or SVA MOA. | LDSO or SVA MOA | Primary and Secondary Suppliers, HHDC | As per Appendices 4.5 & 4.6 / BSCP502 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.6.10 | Following de-energisation date. | Notify of actual de-energisation date (which may be different from planned de-energisation date). | Primary and Secondary Suppliers. | SMRA, HHDC |
| Electronic or other agreed method. |
3.6.11 | Upon receiving actual De-energisation date. | Update SMRA with actual de-energisation date. | SMRA |
| As per BSCP501 | Internal process |
3.6.12 | Within 2 WD of 3.6.6. | Confirm that details for all MSIDs are complete and consistent. Resolve errors with Supplier(s). | HHDC | Supplier(s) | As per Appendix 4.5 / BSCP502 / REC Metering Operations Schedule. | Electronic, or other agreed method. |
REF. | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
3.7.1 | As required. | Agree date that Shared SVA Metering System is to be disconnected. | Primary Supplier | Secondary Supplier(s) |
| By post, fax or electronic media. |
3.7.2 | At least 5 WD prior to disconnection Date. | Send date for the Primary MSID to be disconnected. | Primary Supplier | LDSO | As per BSCP502. | By post, fax or electronic media. |
3.7.3 | At least 5 WD prior to disconnection Date. | Send date for the Secondary pseudo MSID(s) to be disconnected. | Secondary Supplier(s)14 | LDSO | As per BSCP502. | By post, fax or electronic media. |
3.7.4 | By physical disconnection date. | Arrange for physical Shared SVA Metering System associated with the Primary and pseudo Secondary MSIDs to be disconnected, provided details are complete and consistent. Resolve errors with LDSO. | LDSO | SMRA, Supplier(s) | As per BSCP501. | Electronic, or other agreed method. |
3.7.5 | Within 1 WD of 3.7.4. | Record intended disconnection date for Primary and pseudo Secondary MSIDs. | SMRA |
| As per BSCP501. | Internal process. |
3.7.6 | Within 5 WDs of actual disconnection | Update/confirm disconnection date for MSIDs. | LDSO | SMRA |
| By post, fax or electronic media. |
3.7.7 | Following registration deactivation of the Shared SVA Metering System in CSS. | Send appointment termination date to SVA MOA, HHDC & HHDA for Primary MSID. | Primary Supplier | SVA MOA HHDC HHDA(s) | As per Appendices 4.5 & 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.7.8 | Within 2 WD of 3.7.6. | Confirm details are complete and consistent. Resolve errors with Supplier. | SVA MOA, HHDC, HHDA(s) | Primary Supplier | As per Appendix 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.7.9 | At least 5 WD before Appointment Termination Date. | Send appointment termination date to SVA MOA, HHDC & HHDA(s) for pseudo Secondary MSID(s). | Secondary Supplier(s)14 | SVA MOA, HHDC, HHDA(s) | As per Appendices 4.5 & 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. |
3.7.10 | Within 2 WD of 3.7.8. | Confirm details are complete and consistent. Resolve errors with Supplier(s). | SVA MOA, HHDC, HHDA(s) | Primary Supplier, Secondary Supplier(s) | As per Appendix 4.6 / BSCP502 / BSCP503 / REC Metering Operations Schedule. | Electronic or other agreed method. |
REF. | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
3.8.1 | As agreed with Suppliers’ schedule. | Collect and validate the metering data for the physical Shared SVA Metering System as per BSCP502. The Shared SVA Metering System data is split between the Primary MSID and the pseudo Secondary MSID(s) in accordance with the method specified in the Allocation Schedule | HHDC18 |
| As per BSCP502 and Appendix 4.4. Utilise the Allocation Schedule.19 | Internal process.
|
3.8.2 | As agreed with Suppliers’ schedule. | Send validated metered data to relevant Supplier(s), and HHDA and LDSO. | HHDC | Primary & Secondary HHDAs, Primary & Secondary Suppliers and LDSO | Appendix 4.4. D0036 Validated Half Hourly Advances for Inclusion in Aggregated Supplier Matrix. D0275 Validated Half Hourly Advances. | Electronic or other agreed method. |
3.8.3 | As agreed with LDSO. | Send validated raw metered data to LDSO. | HHDC | LDSO | Validated raw meter data (based on D0010 Meter Reading and / or D0036 Validated Half Hourly Advances for Inclusion in Aggregated Supplier Matrix, as agreed between the HHDC and the LDSO). |
REF. | WHEN | ACTION | FROM | TO | INFORMATION REQUIRED | METHOD |
3.9.1 | As agreed with Suppliers’ schedule. | Primary and Secondary Suppliers agree Measurement Class based on the total consumption at the Site or alternatively select Measurement Class C for the Site20. | Primary Supplier. | Secondary Supplier(s). |
| Manual Process. |
3.9.2 | As agreed with Suppliers’ schedule. | Send Measurement Class details. | Primary Supplier. | HHDC. | D0289 Notification of MC/EAC/PC. | Electronic or other agreed method. |
SMRA. | D0205 Update Registration Details. | |||||
3.9.3 | As agreed with Suppliers’ schedule. | Send Measurement Class details. | Secondary Supplier(s). | SMRA. | D0205 Update Registration Details. | Electronic or other agreed method. |
Percentage Method;
Capped Block Method;
Fixed Block Method; or
Multiple Fixed Block Method.
Settlement Period | Active Energy | Primary Supplier Active Energy | Secondary Supplier Active Energy | |
13 | % | 100 | 70 | 30 |
kWh | 30 | 21 | 9 | |
14 | % | 100 | 60 | 40 |
kWh | 20 | 12 | 8 | |
15 | % | 100 | 80 | 20 |
kWh | 40 | 32 | 8 |
the value has a non-integer component greater than 0.5 kWh, the value will be rounded up to the next integer value e.g. 4.6 kWh will be rounded up to 5 kWh;
the value has a non-integer component less than 0.5 kWh, the value will be rounded down to the next integer value e.g. 4.4 kWh will be rounded down to 4 kWh;
the value has a non-integer component equal to 0.5 kWh, the value will be rounded up to the next integer value when the Settlement Period is an odd number e.g. 4.5 kWh will be rounded up to 5 kWh in Settlement Periods 1, 3, 5 etc.; and
the value has a non-integer component equal to 0.5 kWh, the value will be rounded down to the next integer value when the Settlement Period is an even number e.g. 4.5 kWh will be rounded down to 4 kWh in Settlement Periods 2, 4, 6 etc.
Settlement Period | Active Energy kWh | Primary Supplier Nominated kWh | Primary Supplier Actual Active Energy kWh | Secondary Supplier Actual Active Energy kWh |
13 | 100 | 60 | 60 | 40 |
14 | 20 | 30 | 20 | 0 |
15 | 40 | 40 | 40 | 0 |
16 | 0 | 40 | 0 | 0 |
Settlement Period | Actual Active Export Energy (kWh)
| Fixed Supplier Nominated Active Export (kWh) | Fixed Supplier Active Export (kWh) | Variable Supplier22 | |
Active Export (kWh) | Virtual Active import (kWh) | ||||
12 | 100 | 100 | 100 | 0 | 0 |
13 | 100 | 60 | 60 | 40 | 0 |
14 | 50 | 40 | 40 | 10 | 0 |
15 | 20 | 30 | 30 | 0 | 10 |
16 | 0 | 60 | 60 | 0 | 60 |
Settlement Period | Active Energy kWh Export | Fixed Suppliers Active Export (kWh) | Variable Supplier 20 | |||||
A | B | C | D | E | Active Export (kWh) | Virtual Active import (kWh) | ||
13 | 100 | 10 | 5 | 20 | 15 | 10 | 40 | 0 |
14 | 50 | 5 | 10 | 15 | 10 | 10 | 0 | 0 |
15 | 20 | 2 | 8 | 5 | 5 | 10 | 0 | 10 |
16 | 0 | 2 | 8 | 5 | 5 | 10 | 0 | 30 |
The non-Settlement Meter(s) associated with each Supplier. Note that these Meters must be capable of providing half hourly data, and must be recording the same Measurement Quantity as the Settlement Meter at the Boundary Point.
The agreed method for allocating between Suppliers the ‘unaccounted for’ Active Energy (i.e. the difference between the Boundary Point Meter reading and the total of the non-Settlement Meter readings). Such ‘unaccounted for’ Active Energy may be allocated in proportion to the non-Settlement Meter readings, or using other methods agreed by the Suppliers.
Each of the third party Suppliers shall be allocated the Active Import recorded on their customer’s non-Settlement Meter, adjusted by an agreed factor to allow for losses on the private network; and
The landlord’s Supplier shall be allocated the remaining Active Import.
1 The Approved Headline Report for SVG136 contains the SVG’s decision to move CP1369 to the June 12 Release
2 This section numbering used in the BSC Procedure must not change in order to keep the document in line with the other BSCPs listed in Section 1.5.
3 For the purposes of this BSCP, all references to the term ‘Import’ shall refer to that definition which is contained in the BSC SVA Data Catalogue. Where the term ‘import’ is used this shall refer to the virtual import which will apply if either the Fixed Block Method or the Multiple Fixed Block Method is being utilised in accordance with Appendix 4.2.
4 For the purposes of this BSCP, all references to the term ‘Export’ shall refer to that definition which is contained in the BSC SVA Data Catalogue. Where the term ‘export’ is used this shall refer to the virtual export which will apply if either the Fixed Block Method or the Multiple Fixed Block Method is being utilised in accordance with Appendix 4.2.
5 If a Registration Transfer from CMRS, the Supply Start Date will be the “Effective From Date” defined in BSCP68, Section 3.2.
6 Each Supplier will allocate the appropriate half hourly MTC for each MSID (either actual Primary MSID or pseudo Secondary MSID(s)) that they are responsible for as defined in Market Domain Data.
7 Refer to the REC Metering Operations Schedule for the method of installation of the MS.
8 For a single Supplier Shared SVA Meter Arrangement, any reference to Secondary Supplier will be taken to relate to the pseudo Secondary MSID.
9 If Registration is a Transfer of Registration from CMRS, proceed in accordance with BSCP68.
10 Where the existing Supplier continues on as either the Primary or Secondary Supplier, the appropriate parts of this procedure shall be followed.
11 Where either of the existing Suppliers continue on as the sole Supplier, only the appropriate parts of this section of this BSCP shall be followed.
12 If a HHDC does not receive notification of a start of appointment by the Primary Supplier, although he may have received a start of appointment from the Secondary Supplier(s) refer to Appendix 4.1.
13 Where a common Outstation is being utilised for the Import and Export Energy, the Primary Supplier shall ensure that there are no technical issues where different HHDCs collect from the same Outstation.
14 A single Supplier using the Shared SVA Meter Arrangements acts as both the Primary and Secondary Supplier and will be able to perform this role for the pseudo Secondary MSID(s).
15 For a pseudo MSID, energisation will be a logical not a physical process.
16 For a pseudo MSID, de-energisation will be a logical not a physical process.
17 For a pseudo MSID, disconnection will be a logical not a physical process.
18 The HHDC shall record the total half hourly metered data values collected from the relevant SVA Metering Equipment in a separate file marked to identify the relevant SVA Metering Equipment and shall maintain records so as to identify the Metering Equipment with the relevant SVA MS Numbers.
19 On each occasion that the HHDC applies a valid Allocation Schedule in respect of the total half hourly metered data values from the relevant SVA Metering Equipment to provide an output file of data to the HHDA, it shall record a history identifying the output file reference, the Allocation Schedule and the metered data for the relevant day to which it was applied.
20 The same Measurement Class must be agreed for use at both the Primary and Secondary MSIDs.
21 Where Relevant Capacity is defined at Section K 2.5.5 (g) of the Code.
22 Where the Variable Supplier is nominated as exporting or importing for a Settlement Period, then the HHDC will need to ensure that a value is present for either the export or the import MSID but not for both MSIDs. Where the Active Energy equals the Fixed Supplier’s nominated value, a value of zero must be present for both the export and the import MSIDs.